ML102150055

From kanterella
Jump to navigation Jump to search

Cyber Security Amendment Withdrawal Letter
ML102150055
Person / Time
Site: Pilgrim
Issue date: 08/05/2010
From: James Kim
Plant Licensing Branch 1
To:
Entergy Nuclear Operations
sloan s
References
TAC ME2747
Download: ML102150055 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 5, 2010 Site Vice President Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - WITHDRAWAL OF AN AMENDMENT REQUEST REGARDING CYBER SECURITY PLAN (TAC NO. ME2747)

Dear Sir or Madam:

By letter dated November 22, 2009, you applied for an amendment to the Pilgrim Nuclear Power Station, Operating License No. DPR-35. The proposed change would have modified the Facility Operating License (FOL) Physical Protection license condition pertaining to implementation of the Pilgrim Cyber Security plan in accordance with the approved schedule and maintaining in effect all provisions of the Commission-approved Cyber Security plan. Subsequently, by letter dated July 15, 2010, you withdrew the amendment request.

The purpose of this letter is to advise that the above-cited application is being treated as withdrawn.

Sincerely, q.~~k:-

- -';1/- ~

James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: Distribution via Listserv

August 5, 2010 Site Vice President Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - WITHDRAWAL OF AN AMENDMENT REQUEST REGARDING CYBER SECURITY PLAN (TAC NO. ME2747)

Dear Sir or Madam:

By letter dated November 22,2009, you applied for an amendment to the Pilgrim Nuclear Power Station, Operating License No. DPR-35. The proposed change would have modified the Facility Operating License (FOL) Physical Protection license condition pertaining to implementation of the Pilgrim Cyber Security plan in accordance with the approved schedule and maintaining in effect all provisions of the Commission-approved Cyber Security plan. Subsequently, by letter dated July 15, 2010, you withdrew the amendment request.

The purpose of this letter is to advise that the above-cited application is being treated as withdrawn.

Sincerely, IRA!

James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrDorlLpl1-1 Resource RidsRgn1 MailCenter Resource LPL1-1 rtf RidsNrrDorlDpr Resource RidsNrrLASLittle Resource RidsAcrsAcnw_MailCTR Resource RidsNrrPMPilgrim Resource RidsOgcRp Resource ADAMS Accession No. ML102150055 OFFICE NRRlLPLI-1/PM NRRlLPLI-1/LA NRRlLPLI-1/BC NAME JKim SUttle JBoska for NSalgado DATE 8/4/10 8/4/10 8/5/10 OFFICIAL AGENCY RECORD