Submittal of TS Bases Loes, Revision 100 and Tsb 3.7.8, Revision 107
ML102020309
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 07/13/2010
From: Beaver B
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DUK101940025
Download: ML102020309 (57)


Text

DISPOSITION OF THE ORIGINAL DOCUMENT WILL BE TO Normal THE TRANSMITTAL SIGNATURE UNLESS RECIPIENT IS Date: 07113/10 PRIORITY OTHERWISE IDENTIFIED BELOW Document Transmittal #: DUK101940025

1) 01820J R ELKINS- ECO81
2) 02049 NGO PRA MANAGER ECO81 Duke Energy QA CONDITION [] Yes
  • No
3) 02388 BOB SHOMAKER LYNCHBG, VA OTHER ACKNOWLEDGEMENT REQUIRED N Yes DOCUMENT TRANSMITTAL FORM
4) 02532 NRC RESIDENT INSPECTORS IF QA OR OTHER ACKNOWLEDGEMENT REQUIRED, PLEASE
5) 02546 WC LIBRARY - MG01WC ACKNOWLEDGE RECEIPT BY RETURNING THIS FORM TO:

REFERENCE

6) 03044 MCG DOC CNTRL MISC MAN MG05DM
7) 03283 P R TUCKER MG01RP MCGUIRE NUCLEAR STATION Duke Energy
8) 03614 MCG OPS PROCEDURE GP MG010P McGuire
9) 03743 MCG QA TEC SUP MNT QC MG01MM DCRM MGO2DM RECORD RETENTION # 581188
10) 03744 OPS TRNG MGR. MG03OT 13225 Hagers Ferry Road
11) 03759 US NUC REG WASHINGTON, DC Huntersville, N.C. 28078
12) 03796 SCIENTECH DUNEDIN, FL TECHNICAL SPECIFICATIONS (TS)
13) 04698 D E BORTZ EC08G TECHNICAL SPECIFICATIONS BASES
14) 04809 MCG PLANT ENG. LIBR. MG05SE (TSB)
15) 05162 MCG SHIFT WORK MGRS MG01OP Rec'd By Page 2 of 3 Date DOCUMENT NO QA CONDI REV #/DATE DISTR CODE 11 2 3 4 5 6 17 8 9 10 11 12 13 14 115 TOTAL MEMO NA - 06/29/10 MADM-04B vi vi lvi x Vi i1 Vl V2 VI 44 TSB LIST OF EFFECTIVE SECTIONS NA 100 06/29/10 TBS 3.7.8 NA 107 06/29/10 REMARKS: PLEASE UPDATE ACCORDINGLY R T REPKO VICE PRESIDENT MCGUIRE NUCLEAR STATION BY:

BCB MG02MO BCB/TLC

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) ii Revision 87 8/15/07 iii Revision 87 8/15/07 Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

41 Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 Revision 70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revision102 8/17/09 B 3.7.6 Revision 0, 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 Revision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision 41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal operation. The basic performance requirements are that a,30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate SAFETY

/ANALYSES residual heat from the reactor core following all accidents and anticipated operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82 0 F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to be OPERABLE in these MODES. "

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A.1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is < 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

-.4,7 -*

?

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual-Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section)

Revision 87 8/15/07 ii iii Revision 87 8/15/07 Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I . Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 *: Revision 70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 -. Page 2 Revision 100

Page Number Amendment Revision R Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revisionl02 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 Revision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision,41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal toperation.,

-- The basic performance requirements are that a 30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated

/I operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

ý A-,

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82°F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to be OPERABLE in these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A.1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 'Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is 2! 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is < 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

  • 1- - Lv June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) i Revision 87 8/15/07 ii Revision 87 8/15/07 iii Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 - Revision 70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

I iý Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revisionl02 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 . t Revision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision 41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal operation. The basic-performance, requirements are that a 30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate

/

SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B38.7.8-i Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to-be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82 0 F at.722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to be OPERABLE'iin these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A. 1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 O BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is _>739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is < 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR '3ffi8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doe) rev 99 TS Bases LOES (entire doe) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doe) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section)

Revision 87 8/15/07 ii iii Revision 87 8/15/07 Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision '87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 Revision 70 S10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revision 102 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 Revision 0 i V.- 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision,41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/1 0/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

p SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal

-operation.J;he basic performance requirements are that a 30 day supply,.,.-

of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat~transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

-p..

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82 0 F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to 0 6-b&OPERABLE in these MODES. -'A:4-In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A.1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging Unit systems.

SURVEILLANCE -SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is < 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

4%

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

owx3z &AAA/U Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) i Revision 87 8/15/07 ii Revision 87 8/15/07 iii Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0. 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 Revision 70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revision102 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 S.... Revision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision 41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units I and 2 Page 3 Revision 100

I  !

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal operation. The basic performance requirements are that a 30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated

/I operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82 0 F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to t .::,,

be OPERABLE in these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A._1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained., The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is<* 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

\

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) i Revision 87 8/15/07 ii Revision 87 8/15/07 iii Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

'~.2 Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 z' B 3.5.4 Revision 70 10/5/04 ý.Th

-Zr B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revision102 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3:7.16 Revision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision,4l 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

3>

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWI?)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal operation. The basic performance requirements are that a 30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate

/

SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82 0 F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to be OPERABLE ih these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A. 1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is<* 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 317-8"3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107

(4%

June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

16 ' ý6 UAAW Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) ii Revision 87 8/15/07 iii Revision 87 8/15/07 Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B .3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4 Revision'.70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revisionl02 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05 B 3.7.16 *,R'&Vision 0 9/30/98 B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision,41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100

SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal

.operation. -The basic performance requirements are that a 30 day supply.ý.)-

of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated

/I operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82°F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY of the equipment serviced by the SNSWP and required to be'OPERABLE in these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A._1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is < 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

v"v SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No.' 107

4> 4-June 29, 2010 MEMORANDUM To: All McGuire Nuclear Station Technical Specification Bases (TSB) Manual Holders

Subject:

McGuire TSB Updates REMOVE INSERT TSB Manual TS Bases LOES (entire doc) rev 99 TS Bases LOES (entire doc) rev 100 TSB 3.7.8. (entire doc) rev 0 TSB 3.7.8 (entire doc) rev 107 Revision numbers may skip numbers due to Regulatory Compliance Filing System.

Please call me if you have questions.

Bonnie Beaver Regulatory Compliance 875-4180

McGuire Nuclear Station Technical Specification Bases LOES TS Bases are revised by section Page Number Revision Revision Date BASES (Revised per section) i Revision 87 8/15/07 ii Revision 87 8/15/07 iii Revision 87 8/15/07 B 2.1.1 Revision 51 1/14/04 B 2.1.2 Revision 102 8/17/09 B 3.0 Revision 81 3/29/07 B 3.1.1 Revision 73 3/6/06 B 3.1.2 Revision 10 9/22/00 B 3.1.3 Revision 10 9/22/00 B 3.1.4 Revision 0 9/30/98 B 3.1.5 Revision 19 1/10/02 B 3.1.6 Revision 0 9/30/98 B 3.1.7 Revision 58 06/23/04 B 3.1.8 Revision 0 9/30/98 B 3.2.1 Revision 74 5/3/06 B 3.2.2 Revision 10 9/22/00 B 3.2.3 Revision 34 10/1/02 B 3.2.4 Revision 10 9/22/00 B 3.3.1 Revision 99 3/9/09 B 3.3.2 Revision 99 3/9/09 B 3.3.3 Revision 100 4/13/09 B 3.3.4 Revision 57 4/29/04 B 3.3.5 Revision 11 9/18/00 B 3.3.6 Not Used - Revision 87 6/29/06 B 3.4.1 Revision 51 1/14/04 B 3.4.2 Revision 0 9/30/98 B 3.4.3 Revision 44 7/3/03 B 3.4.4 Revision 86 6/25/07 B 3.4.5 Revision 86 6/25/07 McGuire Units 1 and 2 Page I Revision 100

Page Number Amendment Revision Date B 3.4.6 Revision 86 6/25/07 B 3.4.7 Revision 86 6/25/07 B 3.4.8 Revision 41 7/29/03 B 3.4.9 Revision 0 9/30/98 B 3.4.10 Revision 102 8/17/09 B 3.4.11 Revision 102 8/17/09 B 3.4.12 Revision 102 8/17/09 B 3.4.13 Revision 86 6/25/07 B 3.4.14 Revision 102 8/17/09 B 3.4.15 Revision 82 9/30/06 B 3.4.16 Revision 57 4/29/04 B 3.4.17 Revision 0 9/30/98 B 3.4.18 Revision 86 6/25/07 B 3.5.1 Revision 70 10/5/05 B 3.5.2 Revision 102 8/17/09 B 3.5.3 Revision 57 4/29/04 B 3.5.4: Revision 70 10/5/04 B 3.5.5 Revision 0 9/30/98 B 3.6.1 Revision 53 2/17/04 B 3.6.2 Revision 98 3/24/09 B 3.6.3 Revision 87 6/29/06 B 3.6.4 Revision 0 9/30/98 B 3.6.5 Revision 0 9/30/98 B 3.6.5-2 Revision 6 10/6/99 B 3.6.6 Revision 102 8/17/09 B 3.6.7 Not Used - Revision 63 4/4/05 B 3.6.8 Revision 63 4/4/05 B 3.6.9 Revision 63 4/4/05 B 3.6.10 Revision 43 5/28/03 B 3.6.11 Revision 78 9/25/06 B 3.6.12 Revision 53 2/17/04 B 3.6.13 Revision 96 9/26/08 B 3.6.14 Revision 64 4/23/05 B 3.6.15 Revision 0 9/30/98 McGuire Units 1 and 2 Page 2 Revision 100

Page Number Amendment Revision Date B 3.6.16 Revision 40 5/8/03 B 3.7.1 Revision 102 8/17/09 B 3.7.2 Revision 105 2/22/10 B 3.7.3 Revision 102 8/17/09 B 3.7.4 Revision 57 4/29/04 B 3.7.5 Revision 102 8/17/09 B 3.7.6 Revision 0 9/30/98 B 3.7.7 Revision 101 9/17/09 B 3.7.8 Revision 107 6/23/10 B 3.7.9 Revision 97 1/30/09 B 3.7.10 Revision 75 6/12/06 B 3.7.11 Revision 65 6/2/05 B 3.7.12 Revision 28 5/17/02 B 3.7.13 Revision 85 2/26/07 B 3.7.14 Revision 66 6/30/05 B 3.7.15 Revision 66 6/30/05.

$24 B 3.7.16 Revision 0 9/30/98" B 3.8.1 Revision 106 10/16/08 B 3.8.2 Revision 92 1/28/08 B 3.8.3 Revision 103 12/15/08 B 3.8.4 Revision 100 4/13/09 B 3.8.5 Revision 41 7/29/03 B 3.8.6 Revision 0 9/30/98 B 3.8.7 Revision 20 1/10/02 B 3.8.8 Revision 41 7/29/03 B 3.8.9 Revision 24 2/4/02 B 3.8.10 Revision 41 7/29/03 B 3.9.1 Revision 68 9/1/05 B 3.9.2 Revision 41 7/29/03 B 3.9.3 Revision 91 11/7/07 B 3.9.4 Revision 84 2/20/07 B 3.9.5 Revision 59 7/29/04 B 3.9.6 Revision 41 7/29/03 B 3.9.7 Revision 88 9/5/07 McGuire Units 1 and 2 Page 3 Revision 100'

I1ý SNSWP B 3.7.8 B 3.7 PLANT SYSTEMS B 3.7.8 Standby Nuclear Service Water Pond (SNSWP)

BASES BACKGROUND The SNSWP functions as the ultimate heat sink and performs two principal safety functions: (1) dissipation of residual heat after reactor shutdown and (2) dissipation of residual heat after an accident. This is done by utilizing the Nuclear Service Water System (NSWS) and the Component Cooling Water (CCW) System.

The ultimate heat sink (UHS) is comprised of cooling water from the SNSWP, necessary retaining structures, and the canals or conduits connecting the water sources with, but not including, the cooling water system intake structures as discussed in the UFSAR, Section 9.2 (Ref. 1).

For McGuire, the SNSWP is the only cooling water source qualified as the ultimate heat sink.

The SNSWP can be aligned to dissipate sensible heat during normal operation. The basic performance requirements are that a 30 day supply of water be available, and that the design basis temperatures of safety related equipment not be exceeded.

Additional information on the design and operation of the system, along with a list of components served, can be found in Reference 1.

APPLICABLE The SNSWP provides the Ultimate Heat Sink safety function to dissipate

/

SAFETY ANALYSES residual heat from the reactor core following all accidents and anticipated operational occurrences in which the unit is cooled down and placed on residual heat removal (RHR) operation. Its maximum post accident heat load occurs approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after a design basis loss of coolant accident (LOCA). Prior to this time, the unit switches from injection to recirculation and the containment cooling systems and RHR are required to remove the core decay heat.

The operating limits are based on conservative heat transfer analyses for the worst case LOCA. Reference 1 provides the details of the assumptions used in the analysis, which include worst expected meteorological conditions, conservative uncertainties when calculating McGuire Units 1 and 2 B 3.7.8-1 Revision No. 107

SNSWP B 3.7.8 BASES APPLICABLE SAFETY ANALYSES (continued) decay heat, and worst case single active failure. The SNSWP is designed in accordance with Regulatory Guide 1.27 (Ref. 2), which requires a 30 day supply of cooling water in the SNSWP.

The SNSWP satisfies Criterion 3 of 10 CFR 50.36 (Ref. 3).

LCO The SNSWP is required to be OPERABLE and is considered OPERABLE if it contains a sufficient volume of water at or below the maximum temperature that would allow the NSWS to operate for at least 30 days following the design basis LOCA without the loss of net positive suction head (NPSH), and without exceeding the maximum design temperature of the equipment served by the NSWS. To meet this condition, the SNSWP temperature should not exceed 82°F at 722 ft mean sea level and the level should not fall below 739.5 ft mean sea level during normal unit operation.

APPLICABILITY In MODES 1, 2, 3, and 4, the SNSWP is required to support the OPERABILITY'of the equipment serviced by the SNSWP and required to

-be OPERABLE in these MODES.

In MODE 5 or 6, the requirements of the SNSWP are determined by the systems it supports.

ACTIONS A.1 If the SNSWP is inoperable the unit must be placed in a MODE in which the LCO does not apply. To achieve this status, the unit must be placed in at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

The allowed Completion Times are reasonable, based on operating experience, to reach the required unit conditions from full power conditions in an orderly manner and without challenging unit systems.

SURVEILLANCE SR 3.7.8.1 REQUIREMENTS This SR verifies that adequate long term (30 day) cooling can be maintained. The specified level also ensures that sufficient NPSH is McGuire Units 1 and 2 B 3.7.8-2 Revision No. 107

SNSWP B 3.7.8 BASES SURVEILLANCE REQUIREMENTS (continued) available to operate the NSWS pumps. The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the SNSWP water level is > 739.5 ft mean sea level.

SR 3.7.8.2 This SR verifies that the NSWS is available to cool the CCW System to at least its maximum design temperature with the maximum accident or normal design heat loads for 30 days following a Design Basis Accident.

The 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> Frequency is based on operating experience related to trending of the parameter variations during the applicable MODES. This SR verifies that the average water temperature of the SNSWP is<* 82 0 F at an elevation of 722 ft. The SR is modified by a Note that states the Surveillance is only required to be performed during the months of July, August, and September. During other months, the ambient temperature is below the surveillance limit.

SR 3.7.8.3 This SR verifies dam integrity by inspection to detect degradation, erosion, or excessive seepage. Operating experience has shown that these components usually pass the Surveillance when performed at the 12 month Frequency. Therefore, the Frequency is acceptable from a reliability standpoint.

REFERENCES 1. UFSAR, Section 9.2.

2. Regulatory Guide 1.27.
3. 10 CFR 50.36, Technical Specifications, (c)(2)(ii).

McGuire Units 1 and 2 B 3.7.8-3 Revision No. 107