UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Ju1Y 16, 2010 Mr. Michael J. Annacone, Vice President Mr. Jon A. Franke, Vice President Brunswick Steam Electric Plant Crystal River Nuclear Plant (NA2C)
Carolina Power & Light Company Florida Power & Light Company Post Office Box 10429 ATIN: Supervisor, Licensing & Regulatory Southport, North Carolina 28461 Programs 15760 West Power Line Street Crystal River, Florida 34428-6708 Mr. Eric McCartney, Vice President H. B. Robinson Steam Electric Plant, Mr. Christopher L. Burton, Vice President Unit NO.2 Shearon Harris Nuclear Power Plant Carolina Power & Light Company Carolina Power & Light Company 3581 West Entrance Road Post Office Box 165, Mail Zone 1 Hartsville, South Carolina 29550-0790 New Hill, North Carolina 27562-0165
SUBJECT:
BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2; CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT; H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO.2; AND SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO.1 -
WITHDRAWAL OF AN AMENDMENT REQUEST FOR APPROVAL OF THE CYBER SECURITY PLAN (TAC NOS. ME2664, ME2665, ME2666, ME2746, AND ME2796)
Gentlemen:
By letters dated November 18, 19, and 23, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML093410254, ML093270227, ML093340350, and ML093290248), the Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc., and the Florida Power Corporation, now doing business as Progress Energy Florida, Inc. (the licensees), applied for license amendments for the Brunswick Steam Electric Plant, Units 1 and 2, the Crystal River 3 Nuclear Generating Plant, the H.B. Robinson Steam Electric Plant, Unit No.2, and the Shearon Harris Nuclear Power Plant, Unit 1 (Facility Operating License Nos. DPR-71, DPR-62, DPR-72, DPR-23, and NPF-63, respectively).
The license amendment requests (LARs) included the Cyber Security Plan, proposed changes to the (Renewed) Facility Operating License, and a proposed Cyber Security Plan Implementation Schedule for each facility. The proposed Cyber Security Plans were submitted in accordance with Title 10 of the Code of Federal Regulations, Section 73.54, "Protection of digital computer and communication systems and networks."
M. Annacone J. Franke E. McCartney C. Burton
- 2 Subsequently, by letter dated July 8, 2010 (ADAMS Accession No. ML101950042), the licensees superseded the above LARs and requested that the original LARs be withdrawn. The purpose of this withdrawal was to allow the licensees to submit a fleet Cyber Security Plan that conforms to the model Cyber Security Plan contained in Appendix A of Nuclear Energy Institute document NEI 08-09, "Cyber Security Plan for Nuclear Power Reactors," Revision 6, dated April 2010, with one deviation regarding the definition of a Cyber Attack as described in the licensees' letter.
This letter is to advise you that the applications dated November 18, 19, and 23, 2009, are being treated as withdrawn and superseded by the LAR contained in the licensees' July 8, 2010, letter. Notice of Consideration of Issuance of the proposed amendments had not been published in the Federal Register.
Please contact me at (301) 415-3178 if you have questions regarding this matter.
Marlayna Vaaler, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325, 50-324, 50-302,50-261, and 50-400 cc: Distribution via Listserv
ML101950042), the licensees superseded the above LARs and requested that the original LARs be withdrawn. The purpose of this withdrawal was to allow the licensees to submit a fleet Cyber Security Plan that conforms to the model Cyber Security Plan contained in Appendix A of Nuclear Energy Institute document NEI 08-09, "Cyber Security Plan for Nuclear Power Reactors," Revision 6, dated April 2010, with one deviation regarding the definition of a Cyber Attack as described in the licensees' letter.
This letter is to advise you that the applications dated November 18,19, and 23, 2009, are being treated as withdrawn and superseded by the LAR contained in the licensees' July 8, 2010, letter. Notice of Consideration of Issuance of the proposed amendments had not been published in the Federal Register.
Please contact me at (301) 415-3178 if you have questions regarding this matter.
Sincerely, IRA!
Marlayna Vaaler, Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-325, 50-324, 50-302, 50-261, and 50-400 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL2-2 Reading RidsAcrsAcnw_MaiICTR Resource RidsNrrDorlDprResource RidsOgcRp Resource RidsNrrPMRobinson Resource RidsNrrDorlLpl2-2 Resource C. Erlanger, NSIR P. Pederson, NSIR RidsNrrLACSola Resource RidsNrrPMShearonHarris Resource RidsRgn2MailCenter Resource BSingal, NRR TWengert, NRR RidsNrrPMCrystalRiver Resource RidsNrrPMBrunswick Resource RidsNrrDori Resource RidsOgcRp Resource ADAMS Accession Number* ML101940523 NRR-106 OFFICE LPL2-2/PM LPL2-2/LA LPL2-2/PM LPL2-2/PM LPL2-2/BC NAME MVaaler BClayton for CSoia TOrt MVaaler for FSaba DBroaddus DATE 7/14/2010 7/14/2010 7/16/10 7/14/2010 7/16/10