MONTHYEARML1018706002010-07-0101 July 2010 American Society of Mechanical Engineers Request for Relief PV-02, Revision 1 Project stage: Request ML1019502252010-07-15015 July 2010 Request for Additional Information Regarding Relief Request PV-02, Revision 1 Project stage: RAI ML1019000692010-07-15015 July 2010 Acceptance Review Regarding the Proposed Relief Request PV-02, Revision 1 Project stage: Acceptance Review ML1021603402010-07-30030 July 2010 Response to Request for Additional Information Regarding Relief Request PV-02, Revision 1 Project stage: Response to RAI ML1023601912010-08-30030 August 2010 Safety Evaluation of Relief Request PV-02, Revision 1 for the Second 10-Year Interval of the Inservice Testing Program (Tac No. ME4204) Project stage: Approval 2010-07-15
[Table View] |
|
---|
Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024 Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09
[Table view] |
Text
Tennessee Valley Authority 1101 Market Street, LP 3R Chattanooga, Tennessee 37402-2801 R. M. Krich Vice President Nuclear Licensing July 1, 2010 10 CFR 50.4 10 CFR 50.55a ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 1 Facility Operating License No. NPF-90 NRC Docket No. 50-390
Subject:
American Society of Mechanical Engineers Request for Relief PV-02, Revision 1
Reference:
Letter from NRC to TVA, "Watts Bar Nuclear Plant, Unit 1 - Requests for Relief for the Second 10-Year Pump and Valve Inservice Testing Program (TAC Nos. MD2527, MD2528, MD2529, and MC2530)," dated March 9, 2007 In accordance with 10 CFR 50.55a, "Codes and Standards," the Tennessee Valley Authority (TVA) requests NRC approval of Request for Relief PV-02, Revision 1. The original version of PV-02 was authorized by the NRC in the safety evaluation issued March 9, 2007 (Reference).
The Code of Record for the current second 10-year interval is American Society of Mechanical Engineers/American National Standards Institute, "Code for Operation and Maintenance (O&M) of Nuclear Power Plants," 2001 Edition through 2003 Addenda.
The revision to PV-02 requests authorization to include relief from the "preservice" testing requirements of ISTB-5210(a) in addition to relief from the "inservice" testing requirements as authorized in the original version of PV-02. The "Basis for Relief' is unchanged from the original relief request because the basis is applicable to both preservice and inservice testing.
4/--7 0I'r printed on recycled paper
U.S. Nuclear Regulatory Commission Page 2 July 1, 2010 In addition to the "preservice" requirements, the revision to PV-02 also corrects the O&M Code reference from section ISTB-5121(b) to section ISTB-5221(b). ISTB-5121 (b) is in the O&M Code section for "Centrifugal Pumps (excluding vertical line-shaft pumps)," whereas the correct reference should be ISTB-5221 (b) which is for "Vertical Line-Shaft Pumps." The Essential Raw Cooling Water (ERCW) Screen Wash Pumps, for which we are requesting this revised relief, are vertical line-shaft pumps.
The sections are essentially the same with only minor changes associated with the pump type. Identification of this correction has been entered in TVA's Corrective Action Program.
The request for relief is provided in the enclosure. The revised portions are shown in bold italic text.
TVA requests approval of this request for relief by September 1, 2010, in order to permit elimination of preservice testing during the replacement of the ERCW Screen Wash Pump, 1-PMP-67-431, currently scheduled for the week of September 14, 2010.
This relief request was discussed with representatives of NRC on June 22, 2010.
There are no commitments associated with this submittal. If you have any questions about this change, please contact Kevin Casey at (423) 751-8523.
Respectfully, R. M. Krich Enclosure cc: (Enclosure):
NRC Regional Administrator - Region II NRC Resident Inspector - Watts Bar Nuclear Plant
Enclosure Tennessee Valley Authority Watts Bar Nuclear Plant, Unit I Second 10-Year Interval REQUEST FOR RELIEF PV-02, REVISION I Systems/Components For Which Relief Is Requested Code Class 3 Essential Raw Cooling Water Screen Wash Pumps:
- 1 -PMP-67-431-A (reference drawing 1-47W845-1)
, 1-PMP-67-440-B (reference drawing 1-47W845-1)
- 2-PMP-67-437-A (reference drawing 1-47W845-1)
- 2-PMP-67-447-B (reference drawing 1-47W845-1)
Applicable Code Edition and Addenda
For the current, second 10-year inservice testing (IST) interval, the applicable Code edition is the American Society of Mechanical Engineers (ASME), "Code for Operation and Maintenance of Nuclear Power Plants" (ASME OM Code), 2001 Edition through 2003 Addenda. The second interval began on May 27, 2007 and will end on May 26, 2016, which will return the Watts Bar Nuclear Plant (WBN) IST intervals to the original 10-year schedule, as the first interval was extended to 11 years.
Applicable Code Requirement
ASME OM Code, 2001 Edition through 2003 Addenda, ISTB-5210, "PreserviceTesting,"
(a), "In systems where resistancecan be varied,flow rate and differentialpressureshall be measured at a minimum of five points. If practicable,these points shall be from pump minimum flow to at least pump design flow. A pump curve shall be establishedbased upon the measuredpoints. At least one point shall be designatedas the reference point(s). Data taken at the reference point will be used to compare the results of inservice tests. A pump curve need not be established for pumps in systems where the resistancecannot be varied."
ASME OM Code, ISTB-5221(b), "The resistance of the system shall be varied until the flow rate equals the reference point. The differential pressure shall be determined and compared to its reference value. Alternatively, the flow rate shall be varied until the differential pressure equals the reference point and the flow rate determined and compared to the reference flow rate value."
E-1
Code Requirement From Which Relief Is Requested Relief is being requested from:
- 1. Measuring flow rate and differential pressure at five points during Preservice Testing and establishment of a pump curve, and
- 2. Measuring the pump flow rate during Preservice or Inservice Testing of the Screen Wash Pumps.
Basis for Relief No in-line instrumentation exists to measure flow and the physical configuration of the pump and piping does not allow the use of portable flow measuring equipment such as ultrasonics. Piping from the discharge of the, screen wash pumps is open-ended to the spray nozzles at the traveling screen and is relatively short with multiple elbows, reducers, and valves in different planes. The physical configuration of this piping system is such that no portion of the piping meets the requirements for adequate installation of a permanent flow measuring device.
Therefore, measured flow readings from an installed device may not be repeatable nor representative of actual pump flow. Significant system modifications, such as piping rerouting and support redesign, would be required to obtain a configuration that would provide reliable flow readings.
Flow is not the critical parameter for these pumps. The nature of their operation is to ensure that sufficient pressure is maintained at the spray nozzles during flushing operations of the traveling water screens to ensure that sufficient force is exerted on the debris accumulated on the screen to remove it. This can be verified by verifying the effectiveness of the flushing operation.
Maintenance history was reviewed for spray nozzle plugging and it was determined that nozzle plugging is infrequent. The spray nozzles are inspected by operations personnel during spray operation with corrective maintenance initiated as required.
Alternative Examinations Testing will be performed by setting the system resistance to the same point for each test with the throttle valves full open. Flow will not be measured. The remaining variable that could affect system resistance is the spray nozzles.' The condition of the spray nozzles will be inspected during each test performance with corrective actions initiated as necessary, thus providing assurance that the spray nozzle condition will not affect flow rate. With system resistance maintained constant for each test, pump degradation would be identified through changes in differential pressure. Differential pressure is calculated using inlet (based on lake level or suction pressure) and discharge pressure. The pump will be trended for degradation based on differential pressure at this point. Vibration readings will also be taken at this reference point. The pumps will be tested in this manner for the Preservice,and the quarterly Group A and the biennial Comprehensive inservice tests.
E-2
Instrument accuracyand acceptance criteriafor pump differential pressureand vibration will meet the requirementsof Table ISTB-3500-1 and Table ISTB-5200-1, respectively, for the appropriatetest type.
Preservicetest data for differentialpressure and vibration data will be evaluated to verify it representsacceptablepump operationand will be used as reference values for subsequent quarterly Group A and Comprehensive tests.
Justification for the Granting of Relief Based upon the above discussion, the alternative test provides an acceptable level of quality and safety. Authorization to implement the proposed alternative is requested in accordance with 10 CFR 50.55a(3)(i).
Revision 0 of this Request for Relief was authorized by letter from Margaret H. Chernoff, Acting Branch Chief Plant Licensing Branch, to Karl W. Singer dated March 9, 2007. The attached Safety Evaluation transmitted by this letter authorized the use of Relief Requests PV-01, PV-02, PV-03, and PV-04 for the Second Inservice Interval at WBN.
Implementation Schedule This proposed alternative is requested for the Second Inservice Interval.