Other: ML073511698, ML081790538, ML091800430, ML093000354, ML101800052, ML110350515, NRC 2009-0113, Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC Nos. MC4705/4706), NRC 2011-0010, Plan for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors
|
MONTHYEARML0515203322005-06-0303 June 2005 6/3/05, Point Beach - RAI Potential Impact of Debris Blockage on Emergency Sump Recirculation Pressurized-Water Reactors Project stage: RAI ML0603704912006-02-0909 February 2006 RAI - Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized-Water Reactors Project stage: RAI ML0732303452007-11-16016 November 2007 Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0735116982007-12-20020 December 2007 GSI-191/GL 2004-02 Extension Request Approval (Tac No. MC4705/4706) Project stage: Other NRC 2008-0027, Response to Request for Additional Information License Amendment Request 260 One-Time Extension of Completion Time for Technical Specification 3.7.5. Auxiliary Feedwater System2008-05-15015 May 2008 Response to Request for Additional Information License Amendment Request 260 One-Time Extension of Completion Time for Technical Specification 3.7.5. Auxiliary Feedwater System Project stage: Response to RAI ML0816203372008-06-0909 June 2008 Supplemental Response to Generic Letter 2004-02, Potential Lmpact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0817905382008-07-0101 July 2008 Generic Safety Issue 191/Generic Letter 2004-02, Additional Extension Request Approval Project stage: Other ML0822503302008-10-0606 October 2008 Teleconference Summary Regarding Point Beach Nuclear Plant Supplement to the Auxiliary Feedeater Amendment Project stage: Request ML0833001732009-01-0707 January 2009 GSI-191/GL 2004-02 Request for Additional Information Project stage: RAI NRC 2009-0033, Response to Request for Additional Information GSI-191/GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors2009-04-0707 April 2009 Response to Request for Additional Information GSI-191/GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Response to RAI ML0909805232009-04-0707 April 2009 Response to Request for Additional Information GSI-191/GL 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Response to RAI ML0916603262009-06-12012 June 2009 Request for Extension of Unit 1 and 2 Completion Dates for Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC MC4705/4706) Project stage: Request NRC 2009-0053, Request for Extension of Unit 1 and 2 Completion Dates for Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC MC4705/4706)2009-06-12012 June 2009 Request for Extension of Unit 1 and 2 Completion Dates for Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC MC4705/4706) Project stage: Request NRC 2009-0059, Response to Request for Additional Information GSI-I91/GL 2004-02 Potential Lmpact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors2009-06-29029 June 2009 Response to Request for Additional Information GSI-I91/GL 2004-02 Potential Lmpact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Response to RAI ML0918004302009-06-30030 June 2009 GSI-191/GL 2004-02 Additional Extension Request Approval Project stage: Other ML0921506362009-07-31031 July 2009 Response to Request for Additional Information GSI-191/GL 2004-02 (TACs MC4705/4706) Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Response to RAI NRC 2009-0077, Response to Request for Additional Information GSI-191/GL 2004-02 (TACs MC4705/4706) Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors2009-07-31031 July 2009 Response to Request for Additional Information GSI-191/GL 2004-02 (TACs MC4705/4706) Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors Project stage: Response to RAI ML0930003542009-10-27027 October 2009 Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC Nos. MC4705/4706) Project stage: Other NRC 2009-0113, Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC Nos. MC4705/4706)2009-10-27027 October 2009 Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC Nos. MC4705/4706) Project stage: Other ML1005704542010-03-0303 March 2010 Notice of Meeting with FPL Energy Point Beach, LLC Regarding Discussion of Licensee Responses to Generic Letter 2004-02 for Point Beach Nuclear Plant, Units 1 and 2 Project stage: Meeting ML1005703212010-03-0303 March 2010 Request for Additional Information Generic Letter 2004-02 Round 2 Project stage: RAI NRC 2010-0046, Supplemental Response for Extension Request for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation Durian Design Basis Accidents at Pressurized-Water Reactors2010-06-11011 June 2010 Supplemental Response for Extension Request for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation Durian Design Basis Accidents at Pressurized-Water Reactors Project stage: Supplement ML1018000522010-06-30030 June 2010 Generic Letter Project stage: Other ML1016002922010-07-0808 July 2010 Summary of Meeting with NextEra Point Beach, Llc. Response to GL 2004-02 Project stage: Meeting NRC 2011-0010, Plan for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors2011-02-0404 February 2011 Plan for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other ML1103505152011-02-0404 February 2011 Plan for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Other L-2012-098, Units, 1 and 2, Turkey Point, Units 3 and 4, Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol2012-03-0303 March 2012 Units, 1 and 2, Turkey Point, Units 3 and 4, Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol Project stage: Request ML12213A0612012-08-0101 August 2012 8/16/12 Forthcoming Conference Call with NextEra Energy and Florida Power & Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Protocol Project stage: Draft Approval ML12222A0392012-08-0909 August 2012 8/16/2012 Cancellation Notice of Forthcoming Conference Call with NextEra Energy and Florida Power and Light Concerning Generic Letter 2004-02 and Request for NRC Staff Review of Draft Proposed Guideline for Strainer Fiber Bypass Test Proto Project stage: Draft Approval ML12121A3842012-08-31031 August 2012 Acknowledgment Letter Regarding Draft Propose Guideline for Strainer Fiber Bypass Test Protocol Associated with Generic Letter 2004 Project stage: Draft Other 2009-06-12
[Table View] |
Text
June 11,2010 NEXTera TM ENERGY1 POINT BEACH 7
NRC 201 0-0046 GL 2004-02 U. S. Nuclear Regulatory Commission ATN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Sup~lemental Response for Extension Request for Completion of Actions for Generic Letter 2004-02 Potential Impact for Debris Blockage in Emergencv Recirculation Durinn Design Basis Accidents at Pressurized-Water Reactors (TAC No. MC4705lMC4706)
References:
( 1 NRC letter to NextEra Energy Point Beach, LLC, dated June 30, 2009, Point Beach Nuclear Plant, Units 1 and 2, GSI-19IIGL 2004-02, Additional Extension Request Approval (TAC Nos. MC4705 and MC4706)
(ML091800430)
(2) NextEra Energy Point Beach, LLC letter to NRC, dated February 19, 201 0, Request for Extension of Completion Date for Generic Letter 2004-02, Potential Impact for Debris Blockage in Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors (TAC No. MC4705lMC4706) (MLI 00500632)
(3)
NRC Memorandum dated May 17, 2010, Staff Requirements - Briefing on Resolution of Generic Safety Issue (GSI) - 191, Assessment of Debris Accumulation in Pressurized Water (PWR) Sump Performance (MI 0041 5)
Via Reference (I), the Commission granted a request submitted by NextEra Energy Point Beach, LLC (NextEra) for an extension to achieve compliance with the provisions of GL 2004-02. The extension was approved until June 30, 201 0, for Point Beach Nuclear Plant (PBNP) Unit I, and to June 30, 201 1 for Unit 2, respectively.
In Reference (2), NextEra requested an additional extension to achieve compliance with the provisions of GSI-191IGL 2004-02 at PBNP by June 30,2013, for Unit 1, and by December 31, 2012, for Unit 2. The purpose of this letter is to replace the extension requested by Reference (2) by this letter.
Recent NRC and industry discussions have revealed there are a number of issues that have not yet been resolved for GSI-I 91 (GL 200402) and that a clear and acceptable path needs to be defined to resolve the issues. On May 17, 201 0, the Commission directed the NRC staff (Reference 3) to submit information on potential approaches that might be implemented to bring GSI-I 91 (GL 2004-02) to closure pending further direction from the Commission.
NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241
Document Control Desk Page 2 The request stated that discussion of the options should include such factors as the Commission's ALARA policy concerning radiation dose, worker hazardous material exposure and risk-informed versus deterministic treatment of remaining elements, such as determining the zone of influence, application of General Design Criterion 4, consideration of in-vessel effects of different types of fuel, etc.
Due to the uncertainties currently surrounding resolution of GSI-I 91 (GL 2004-02), milestones contained in the Reference (2) extension request require revision. During a teleconference held on June 7, 2010, between NextEra and the NRC, NextEra stated that an updated path moving forward, including a plan with milestones, would be submitted to the NRC within 60 days following Commission direction to the NRC staff based on their review of the information submitted by the NRC staff to address the NRC Memorandum dated May 17,201 0 (MI 0041 5).
Following the NextEra submittal, the NRC would take an additional 30 days to review and respond to this approach. During the teleconference, the NRC stated that this was an acceptable approach.
Accordingly, NextEra makes the following commitment:
Within 60 days following establishment of sufficient Commission direction to resolve the remaining GSI-191 issues, PBNP will submit to the NRC a plan with milestones to achieve final resolution.
Therefore, NextEra requests an extension for PBNP Unit I for 90 days beyond receipt of the above noted Commission direction.
The extension to achieve compliance with the provisions of GL 2004-02 that was approved by the NRC in Reference (I) for PBNP Unit 2 to June 30,201 1, remains unchanged and an additional extension is not requested at this time.
If you have questions or require additional information, please contact Ms. Fritzie Flentje at 9201755-7656.
In accordance with the provisions of 10 CFR 50.91, a copy of this submittal has been provided to the designated Wisconsin Official.
Very truly yours, NextEra nergy Point Beach, LLC arry Meyer Site Vice President cc:
USNRC Resident Inspector, Point Beach Nuclear Plant USNRC Project Manager, Point Beach Nuclear Plant Administrator, USNRC Region Ill PSCW