Letter Sequence Acceptance Review |
|---|
|
|
MONTHYEAR1CAN011003, Response to Request for Additional Information Request for Alternative - Implementation of a Risk-Informed Inservice Inspection Program Based on ASME Code Case N-7162010-01-20020 January 2010 Response to Request for Additional Information Request for Alternative - Implementation of a Risk-Informed Inservice Inspection Program Based on ASME Code Case N-716 Project stage: Response to RAI 0CAN011004, Units 1 & 2, Request for Exemption from Physical Supplemental Information2010-01-28028 January 2010 Units 1 & 2, Request for Exemption from Physical Supplemental Information Project stage: Supplement ML1012506042010-05-0505 May 2010 E-mail Arkansas Nuclear One, Unit 2 - Acceptance Review Email, License Amendment Request, Technical Specification Changes and Analyses Relating to Use of Alternative Source Term Project stage: Acceptance Review ML1014502942010-05-25025 May 2010 Request for Additional Information License Amendment Request for Technical Specification Changes and Analyses Regarding Use of Alternate Source Project stage: RAI 2CAN061004, License Amendment Request Technical Specification Changes and Analyses Relating to Use of Alternative Source Term - Supplemental Information2010-06-23023 June 2010 License Amendment Request Technical Specification Changes and Analyses Relating to Use of Alternative Source Term - Supplemental Information Project stage: Supplement ML1019604922010-07-15015 July 2010 Email, Request for Additional Information License Amendment Request to Implement an Alternative Source Term Project stage: RAI ML1018103372010-07-29029 July 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1018102182010-07-29029 July 2010 Request for Withholding Information from Public Disclosure, 6/3/2010 Affidavit Executed by J. Gresham, Westinghouse Calculation Note CN-OA-08-15, Revision 0, TAC No. ME3678 Project stage: Withholding Request Acceptance ML1018102242010-07-29029 July 2010 Request for Withholding Information from Public Disclosure, 6/3/2010 Affidavit Executed by J. Gresham, Westinghouse Calculation Note CN-OA-08-16, Revision 0, TAC No. ME3678 Project stage: Withholding Request Acceptance ML1018102262010-07-29029 July 2010 Request for Withholding Information from Public Disclosure - 6/3/2010 Affidavit Executed by J. Gresham, Westinghouse Calculation Note CN-OA-08-17, Revision 0 Project stage: Withholding Request Acceptance ML1018102332010-07-29029 July 2010 Request for Withholding Information from Public Disclosure - 6/3/2010 Affidavit Executed by J. Gresham, Westinghouse Calculation Note CN-OA-08-57, Revision 0 Project stage: Withholding Request Acceptance ML1018103312010-07-29029 July 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1018103452010-07-29029 July 2010 Request for Withholding Information from Public Disclosure - 6/3/2010 Affidavit Executed by J. Gresham, Westinghouse Calculation Note CN-OA-08-18, Revision 0 Project stage: Withholding Request Acceptance 2CAN081001, Request for Additional Information, Technical Specification Changes and Analyses Relating to Use of Alternative Source Term2010-08-0909 August 2010 Request for Additional Information, Technical Specification Changes and Analyses Relating to Use of Alternative Source Term Project stage: Request ML1023104312010-08-19019 August 2010 Email, Request for Additional Information, Round 3, License Amendment Request for Technical Specification Changes and Analyses Regarding Use of Alternate Source Term Project stage: RAI 2CAN081007, Request for Additional Information Implementation of a Risk-Informed Inservice Inspection Program Based on ASME Code Case N-7162010-08-24024 August 2010 Request for Additional Information Implementation of a Risk-Informed Inservice Inspection Program Based on ASME Code Case N-716 Project stage: Request 2CAN091002, Request for Additional Information Technical Specification Changes and Analyses Relating to Use of Alternative Source Term2010-09-16016 September 2010 Request for Additional Information Technical Specification Changes and Analyses Relating to Use of Alternative Source Term Project stage: Request ML1109801972011-04-26026 April 2011 Issuance of Amendment No. 293, Technical Specification Changes and Analyses Regarding Use of Alternate Source Term Project stage: Approval ML1115108242011-05-0202 May 2011 Email Correction to the Safety Evaluation (SE) on the Alternate Source Term License Amendment Request, (SE Issued on April 26, 2011) Project stage: Request ML1115110012011-08-0909 August 2011 Correction to Safety Evaluation for Amendment No. 293 Related to Use of Alternate Source Term Project stage: Approval 2010-07-29
[Table View] |
Text
From:
Kalyanam, Kaly Sent:
Wednesday, May 05, 2010 3:44 PM To:
CLARK, ROBERT W; BICE, DAVID B Cc:
Lingam, Siva; Feintuch, Karl; Burkhardt, Janet; Lent, Susan
Subject:
Acceptance Review Results and Request for Supplemental Information to Entergy Operations Inc.
Licensee: Entergy Operations Inc.
Plant: Arkansas Nuclear One, Unit 2 Docket No.: 50-368
Subject:
Transmission of the Acceptance Review Result to Licensee and Request for Supplemental Information TAC No.: ME3678 Dave/Bob:
By letter dated March 31, 2010, Entergy Operations, Inc. (Entergy) submitted a License Amendment Request for Arkansas Nuclear One, Unit 2, regarding Technical Specification Changes and Analyses Relating to Use of Alternative Source Term.
In support of AST implementation and also in accordance with the provisions of 10 CFR 50.90, Entergy included the request for an amendment to the Technical Specifications (TS) for ANO-2.
The proposed amendment will modify TS requirements related to the use of an AST associated with accident offsite and control room dose consequences.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it generally does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. However, before we can begin our detailed review, we request that Entergy provide, within the next 45 days, additional supplementary information, in the form of the design analyses used to determine the dose consequences for each of the design basis accidents that were analyzed.
If, after the detailed review of your application, additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1480.
N. Kalyanam Project Manager (Arkansas Nuclear One)
Nuclear Regulatory Commission
Division of Operating Reactor Licensing Tel. No. 301 415-1480 Fax No. 301 415-2102 Email: kaly.kalyanam@nrc.gov E-mail Properties Mail Envelope Properties (94A2A4408AC65F42AC084527534CF41608A0EA160D)
Subject:
Acceptance Review Results and Request for Supplemental Information to Entergy Operations Inc.
Sent Date: 5/5/2010 3:43:58 PM Received Date: 5/5/2010 3:43:58 PM From: Kalyanam, Kaly Created By: Kaly.Kalyanam@nrc.gov Recipients:
RCLARK@entergy.com (CLARK, ROBERT W)
Tracking Status: None DBICE@entergy.com (BICE, DAVID B)
Tracking Status: None Siva.Lingam@nrc.gov (Lingam, Siva)
Tracking Status: None Karl.Feintuch@nrc.gov (Feintuch, Karl)
Tracking Status: None Janet.Burkhardt@nrc.gov (Burkhardt, Janet)
Tracking Status: None Susan.Lent@nrc.gov (Lent, Susan)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 12472 5/5/2010 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: