MONTHYEARML0922503792009-08-0505 August 2009 RPM 2.3.4, Revision 002-03, Inspection and Maintenance Process for Respiratory Protection Equipment Project stage: Request ML0924503332009-08-28028 August 2009 Submittal of Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection. Project stage: Response to RAI NL-09-1265, Response to RAI Related to License Amendment Request to Revise TS Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10,Steam Generator Tube Inspection Report for Permanent Alternate Repair Criteria2009-08-28028 August 2009 Response to RAI Related to License Amendment Request to Revise TS Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10,Steam Generator Tube Inspection Report for Permanent Alternate Repair Criteria Project stage: Response to RAI NL-09-1317, Supplemental Information for License Amendment Request to Revise Technical Specification Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection Report for Permanent Alternate Repair Criteria2009-08-28028 August 2009 Supplemental Information for License Amendment Request to Revise Technical Specification Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection Report for Permanent Alternate Repair Criteria Project stage: Supplement NL-09-1411, License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection Report for Interim Alternate Repair Criteria2009-09-11011 September 2009 License Amendment Request to Revise Technical Specification (TS) Sections 5.5.9, Steam Generator (SG) Program and TS 5.6.10, Steam Generator Tube Inspection Report for Interim Alternate Repair Criteria Project stage: Request ML0936200852009-11-23023 November 2009 License Amendment Request to Revise Technical Specification (TS) 6.8.4.g, Steam Generator (SG) Program, and TS 6.9.1.7, Steam Generator Tube Inspection Report for One-Time Alternate Repair Criteria (H*) Project stage: Request ML1011904172010-04-22022 April 2010 Westinghouse Electric Co., LLC, LTR-SGMP-10-50 NP-Attachment Assessment of the Effect of the Location of the Bottom of the Expansion Transition on H Project stage: Request ML1011804732010-04-28028 April 2010 Response to Query on MPS3 Tube Inspection Results Project stage: Request ML1007703582010-05-0303 May 2010 Issuance of Amendment Changes to the Steam Generator Inspection Scope and Repair Requirements Project stage: Approval ML1015405582010-06-11011 June 2010 Request for Withholding Information from Public Disclosure for Millstone Power Station, Unit 3 Project stage: Withholding Request Acceptance ML1021607492010-09-22022 September 2010 Request for Withholding Information from Public Disclosure for Millstone Power Station, Unit No. 3 Project stage: Withholding Request Acceptance ML1028504382010-09-30030 September 2010 Attachments 2, 3, 5, 7, 8 & 9, to 10-579A, Westinghouse Electric Co. LLC, WCAP-17071-NP, H*: Alternate Repair Criteria for the Tubesheet Expansion Region in Steam Generators with Hydraulically Expanded Tubes (Model F), Revision 2, Dated Sep Project stage: Other ML1027308602010-09-30030 September 2010 Extension Request for Resubmittal of Westinghouse Documentation Supporting License Amendment 249, Changes to the Steam Generator Inspection Scope & Repair Requirements Project stage: Request ML1028504352010-10-0707 October 2010 Resubmittal of Westinghouse Documentation Supporting License Amendment 249, Changes to the Steam Generator Inspection Scope and Repair Requirements Project stage: Other ML1103906642011-02-28028 February 2011 Request for Withholding Information from Public Disclosure for Millstone Power Station, Unit No. 3 Project stage: Withholding Request Acceptance 2010-04-22
[Table View] |
Text
From:
William D Bartron [william.d.bartron@dom.com]
Sent:
Wednesday, April 28, 2010 3:12 PM To:
Sanders, Carleen Cc:
MaryLou L Calderone; Michael V Stark
Subject:
Response to Query on MPS3 Tube Inspection Results
- Carleen, Regarding the seven tubes from the MPS3 Steam Generator A that we have committed to remove from service during the next scheduled inspection, the most recent inspection results from 3R12 for these seven tubes showed no indications of any kind. Accordingly, no specific reference to these tubes were reported in the 180-day report for 3R12 as that report discussed tubes with indications.
Bill CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.
E-mail Properties Mail Envelope Properties (90D7BEDC8151CB4A98D4952A4C3B3A9743EDCB58)
Subject:
Response to Query on MPS3 Tube Inspection Results Sent Date: 4/28/2010 3:12:10 PM Received Date: 4/28/2010 3:12:10 PM From: William D Bartron Created By: william.d.bartron@dom.com Recipients:
Carleen.Sanders@nrc.gov (Sanders, Carleen)
Tracking Status: None marylou.l.calderone@dom.com (MaryLou L Calderone)
Tracking Status: None michael.v.stark@dom.com (Michael V Stark)
Tracking Status: None Post Office:
DOM-MBX06.mbu.ad.dominionnet.com Files Size Date & Time MESSAGE 13381 4/28/2010 Options Expiration Date: