MONTHYEARML0934504852009-11-30030 November 2009 Request for Amendment to TS Table 3.3.5-1,Engineered Safety Features Actuation System Instrumentation, and Figure 3.5.5-1, Minimum Required Refueling Water Tank (RWT) Volume & Supporting Changes Project stage: Request ML1011604712010-04-26026 April 2010 Draft Request for Additional Information TS Changes on Minimum RWT Volume Setpoints Project stage: Draft RAI ML1011604562010-04-26026 April 2010 E-mail, Request for Additional Information TS Changes on Minimum RWT Volume Setpoints Project stage: RAI ML1021500362010-07-22022 July 2010 Response to Request for Additional Information Relating to License Amendment Request to Change the Technical Specifications to Support Crediting an Existing Manual Operator Action to Isolate the Refueling Water Tank Project stage: Response to RAI ML1021500372010-07-22022 July 2010 Engineering Study 13-MS-B094, Revision 0 Project stage: Other ML1027103012010-11-24024 November 2010 Issuance of Amendment Nos. 182, 182, and 182, Revise TS Table 3.3.5-1, Engineered Safety Features Actuation System, and Figure 3.5-1, Minimum Refueling Water Tank Volume Project stage: Approval 2010-11-24
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24297A6212024-10-22022 October 2024 Request for Additional Information Relief Request (RR) No. 72: Re-Submittal of RR-39/ASME Code X1 IWC-3420, IWA-3300 ML24267A2172024-09-23023 September 2024 (E-Mail) Palo Verde Nuclear Generating Station Units 1, 2, and 3 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24257A1012024-09-11011 September 2024 Request for Additional Information License Renewal Commitment for AMP of Alloy 600 Components ML24248A2632024-09-0404 September 2024 Acceptance Review of Palo Verde Nuclear Generating Station, Units 1, 2, and 3, Relief Request (RR) No. 71: Re?Submittal of RR?30 ML24242A2812024-08-26026 August 2024 RR72 Acceptance 08/27/24 - La Jr ML24221A2382024-08-0606 August 2024 Change in Estimated Review Schedule and Level of Effort for Palo Verde Units 1, 2, and 3 ML24143A1112024-05-20020 May 2024 Draft 2nd Round Request for RAIs Concerning LAR to Modify LCO for TS 3.5.2, LCO for TS 3.6.5, and Surveillance Requirements 3.5.1.2 and 3.5.2.2 for TS 3.5.1 and TS 3.5.2 ML24138A1112024-05-16016 May 2024 Draft 2nd Round Request for Additional Information (Rais) Concerning License Amendment Request (LAR) to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2 ML24123A2002024-05-0101 May 2024 (E-Mail) Draft 2nd Round Request for Additional Information Concerning License Amendment Request to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2, LCO for TS 3.6.5, 3.5.1.2 and 3.5.2.2 for TS 3.5.1, a ML24120A2612024-05-0101 May 2024 Email Acceptance Review of Requested Licensing Action License Renewal Commitment 23A, Alloy 600 Management Program Plan ML24114A2812024-04-19019 April 2024 Request for Additional Information (RAI-10150-R1) ML24103A1222024-04-11011 April 2024 – Acceptance of Requested Licensing Action Re_ License Amendment Request to Revise Technical Specifications 3 ML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23243B0082023-08-31031 August 2023 NRR E-mail Capture - Action: Opportunity to Review and Comment on a New NRC Information Collection, 10 CFR Part 50.55a, Codes and Standards (3150-XXXX) ML23233A0132023-08-18018 August 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23220A0512023-08-0303 August 2023 NRR E-mail Capture - Re Palo Verde 1, 2, and 3 - SUNSI Review of UFSAR, Rev. 22 ML23202A0162023-07-20020 July 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23143A1332023-05-23023 May 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR Revising TS 3.3.11 to Adopt TSTF-266-A, Rev. 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls ML23130A0132023-05-10010 May 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for Authorized Use of Mururoa Supplied Air Suits (Models V4F1 and MTH2) Pursuant to 10 CFR 20.1703 and 10 CFR 20.1705 ML23017A0932023-01-17017 January 2023 NRR E-mail Capture - Palo Verde - Acceptance of License Amendment Request Regarding Adoption of TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable (L-2022-LLA-0181) ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 – Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22167A1872022-06-16016 June 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Revised Acceptance Review of LAR to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues ML22136A0922022-05-16016 May 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Adopt TSTF-487-A, Revision 1, Relocate DNB Parameters to the COLR ML22075A1902022-03-16016 March 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22034A0132022-02-0202 February 2022 NRR E-mail Capture - Palo Verde, Unit 2 - Verbal Approval of RR-69 to Extend Containment Tendon Inspection from 2/8/22 to 6/8/22 ML22032A0312022-01-31031 January 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for an Exemption Regarding Elimination of Dafas Using RIPE Process ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21333A1982021-11-19019 November 2021 NRC Review of PVNGS Training Needs Analysis and Training Required by Condition I of the Confirmatory Order EA-20-054 ML21306A1882021-10-18018 October 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Second Pre-submittal Meeting for the Proposed Exemption to Eliminate Dafas Using RIPE Process ML21272A0592021-09-28028 September 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - SUNSI Review of UFSAR, Rev. 21 ML21264A1352021-09-17017 September 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Acceptance Review of LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21237A0762021-08-25025 August 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of RR-67, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML21228A0082021-08-16016 August 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of an LAR for Administrative Changes to Technical Specifications ML21228A1042021-08-12012 August 2021 RR-67, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (EPID L-2021-LLR-0050) (Email) ML21237A5172021-08-10010 August 2021 Email to PV Licensee and Palo Verde Nuclear Generating Station, Units 1, 2 and 3 - Notification of Inspection of the Licensees Implementation Industry Initiative Associated with the Open Phase Condition (NRC Bulletin 2012-01) and Request Fo ML21160A1442021-06-0909 June 2021 NRR E-mail Capture - Palo Verde 1 and, 2 - Acceptance Review for Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21146A3342021-05-14014 May 2021 ISFSI - Final Package for an Order Associated with Indirect Transfers of Control of Licenses from Pnm to Avangrid ML21132A2372021-05-12012 May 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3, and ISFSI - Final Package for an Order Associated with Indirect Transfers of Control of Licenses from Pnm to Avangrid ML21103A3632021-04-13013 April 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for Indirect Transfer of Control of Licenses Pursuant to 10 CFR 50.80 and 10 CFR 72.50 ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21053A0262021-02-22022 February 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Acceptance Review of LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc 2024-09-04
[Table view] |
Text
From: Hall, Randy Sent: Monday, April 26, 2010 1:55 PM To: Stroud, Rusty (Z00989)
Subject:
Draft RAI for Palo Verde Nuclear Generating Station, Units 1,2, and 3, LAR, TS Changes on Minimum RWT Volume and Setpoints(TAC Nos. ME2842, ME2843 and ME2844)
Attachments: RAI ME2842.doc April 26, 2010 Mr. Russell A. (Rusty) Stroud Licensing Section Leader Regulatory Affairs Palo Verde Nuclear Generating Station Arizona Public Service Company Rusty:
By letter dated November 30, 2009, Arizona Public Service Company (APS) submitted a license amendment request (LAR) for the Palo Verde Nuclear Generating Station, Units 1, 2, and 3.
The proposed amendment would revise Technical Specification (TS) Table 3.3.5-1, Engineered Safety Features Actuation System Instrumentation, to increase the Refueling Water Tank (RWT) low-level setpoint for the Recirculation Actuation Signal (RAS); and TS Figure 3.5.5-1, Minimum Required RWT Volume, to increase the minimum volume in the RWT; and would also change the plant licensing basis to allow credit for an existing manual operator action to isolate the RWT in order to preclude the potential for air entrainment from the RWT following an RAS.
The U.S. Nuclear Regulatory Commission staff has reviewed the LAR and has determined that the information specified in the attached draft Request for Additional Information (RAI) is needed for the staff to complete its evaluation.
In order for the staff to complete its review in time to meet your requested schedule for issuance of the amendment by November 30, 2010, we request that you submit your response to the enclosed RAI by June 25, 2010. Please contact me if APS would like to have a conference call to discuss this draft RAI.
Sincerely, Randy Hall, Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation USNRC (301) 415-4032 Randy.Hall@nrc.gov E-mail Properties
Mail Envelope Properties ()
Subject:
Draft RAI for Palo Verde Nuclear Generating Station, Units 1,2, and 3, LAR, TS Changes on Minimum RWT Volume and Setpoints(TAC Nos. ME2842, ME2843 and ME2844)
Sent Date: 4/26/2010 1:40:11 PM Received Date: 4/26/2010 1:55:00 PM From: Hall, Randy Created By: Randy.Hall@nrc.gov Recipients:
Russell.Stroud@aps.com (Stroud, Rusty (Z00989))
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 73271 4/26/2010 RAI ME2842.doc 66042 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: