ML101120176

From kanterella
Jump to navigation Jump to search
Meeting Slides, Duke Energy Carolinas, Major Project Plans for April 22, 2010 Meeting
ML101120176
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 04/22/2010
From:
Duke Energy Carolinas
To:
Office of Nuclear Reactor Regulation
Stang J, NRR/DORL, 415-1345
References
Download: ML101120176 (29)


Text

Major Project Plans April 22, 2010 Oconee Nuclear Station

Objectives

 Provide history and context regarding completed projects, risk improvements, and organization capabilities.

 Provide technical information, status, and projected risk improvements associated with Oconee projects of regulatory interest.

 Reaffirm Dukes commitment to Oconee projects of regulatory interest.

2

Agenda

 Background

 ONS Refurbishment

 Steam Generator and Reactor Head Replacements

 Active Projects

 Reactor Protective System / Engineered Safeguards Protective System

 Tornado

 Natural Phenomena Barrier System

 High Energy Line Break

 Fire Protection transition to NFPA-805

 Protected Service Water

 Main Steam Isolation Valves

 Commitments

 Closing Remarks 3

Background

ONS Refurbishment

 Digital Upgrades

 Integrated Control System (1998)

 Water Treatment System (2000)

 Automatic Feedwater Isolation (2002)

 Keowee Hydroelectric Stations Exciter and Governor (2004)

 Main Turbine Control System (2004)

 Control Rod Drive System (2008)

 Turbine Supervisory Instrumentation (2008)

 Main Generator Voltage Regulator (2008)

 Expandable Process Control System (2008)

 Main Feedwater Pump Control System (2010, 2011)

 Reactor Protective and Engineered Safeguards Protective Systems (2011 - 2013) 4

Background

ONS Refurbishment

 Emergency Core Cooling Systems / Emergency Operating Procedure Improvements

 High Pressure Injection Pump recirculation flow

 Low Pressure Injection cross-tie / flow restrictors

 Reactor Building Spray

 Other Upgrades - examples

 Emergency Feedwater Control Valve Instrument Air Upgrades

 Battery Replacements: Vital, Power, Standby Shutdown Facility, & Keowee

 Keowee Underground Cable Replacement

 Electrical Penetration Replacements

 600 V Electrical Distribution System Upgrades

 Security System Upgrades

 Reactor Building Sump Strainers (~100 ft2 to ~5000 ft2)

 GL 04-02 Closed for ONS

 Steam Generator / Rx Vessel Head Replacements

 Combined Cost: $1.3 Billion 5

Completed Projects Risk Improvement 2.0E+03 1E-03 Estimate Oconee CDF - Historical 1.8E+03 1.6E-04 1.6E+03 SSF &

TB Flood Mods Core Damage Frequency ( /yr. )

1.4E-04 1.4E+03 1.2E+03 Oconee 1.2E-04 IPE 1.0E+03 1.0E-04 Rev. 2 PRA Rev. 3 Ext. Flood:

8.0E-05 8.0E+02 PRA Fragility Analysis 6.0E-05 6.0E+02 4.0E+02 4.0E-05 2.0E-05 2.0E+02 1.0E-06 0.0E+00 Post-TMI 1986 1990 1997 2003 2006 6

Active Projects RPS/ES

 Regulatory Status

 License Amendment Request (LAR) submitted 1/31/2008

 Safety Evaluation Report (SER) issued 1/30/2010

 Inspection Planning for Site Acceptance Testing and installation

 Project Status

 Unit 1 installation Spring 2011

 Unit 2 installation Fall 2013

 Unit 3 installation Spring 2012

 Risk Benefit

 Not quantified - Addresses long term obsolescence

 Cost

 $ 225 M 7

Active Projects Tornado

 Regulatory Status

 Tornado LAR submitted 6/30/2008; Review in progress

 Fiber Re-enforced Polymer LAR submitted; 6/1/2006

 Approved for re-enforcing Block Walls only; 3/26/2008

 Re-submitted for Brick Walls 6/29/2009; NRC review in progress

 Project Status

 Natural Phenomena Barrier System (NPBS); construction in progress

 Protected Service Water System; design & construction in progress

 Main Steam Isolation Valves (w/ tornado protection); design in progress

 SSF Equipment Doors Upgrade; design in progress

 Risk Benefit

 Small (low E-06 / yr) - actual risk improvement

 Cost

 $ 155 M (NPBS only) 8

Active Projects Natural Phenomena Barrier System Project Status

Complete

Control Room North Wall

SSF / CT-5 Trench Intersection

SSF Generator Fuel Oil Vent

Ongoing

Borated Water Storage Tank (BWST) Foundations

Remaining

Fibrwrap Installations

BWST Superstructure and Steel Siding 9

Active Projects High Energy Line Break

 Regulatory Status

 LARs submitted; Unit 1 6/2008; Unit 2 12/2008; Unit 3 6/2009

 NRC review in progress

 Project Status

 Feedwater and Main Steam Pipe Weld Inspections; complete

 East Penetration Room Flood Modifications; complete

 Protected Service Water System; design and construction in progress

 Main Steam Isolation Valves; design in progress

 Letdown Cooler Isolation Valves Upgrade; scoped, slotted, awaiting LAR approval

 Control Complex Ventilation Isolation; scoped, slotted, awaiting LAR approval

 High Pressure Injection Suction Header Isolation Valves Upgrade; scoped, slotted, awaiting LAR approval

 Turbine Building column re-enforcements; scoped, slotted, awaiting LAR approval

 Condenser Circulating Water Stop Gate Upgrade; scoped, slotted, awaiting LAR approval

 Risk Benefit and Cost primarily attributed to PSW project 10

Active Projects NFPA--805 Transition NFPA

 Regulatory Status

 Letter of intent submitted February 2005

 Initial LAR submitted May 31, 2008

 Incomplete - preliminary Fire PRA & modifications not determined

 Followup LAR submitted October 31, 2008

 Based on RG 1.205, revision 0

 Revised LAR submitted April 14, 2010

 Incorporates Requests for Additional Information (RAIs)

 Will be template for RG 1.205, revision 1, submittals

 Project Status

 Protected Service Water System; design and construction in progress

 Turbine/Auxiliary Building Wall Fire Barrier Upgrade; scoped, slotted, awaiting LAR approval

 Purge Inlet Room/Auxiliary Building Fire barrier Upgrade; scoped, slotted, awaiting LAR approval

 Blockhouse Pressure Relief Shafts Upgrade; scoped, slotted, awaiting LAR approval

 General Area/Hazard Fire Detection improvements; scoped, slotted, awaiting LAR approval

 Breaker Coordination Study; scheduled to complete 8/2010

 Program Implementation Team; in place

 Risk Benefit

 Small - actual risk improvement from PSW project

 Cost

 $ 20 M (not including modifications) 11

Active Projects Main Steam Isolation Valves

 Regulatory Status

 Tornado and HELB LARs dependent on commitment to install

 Separate LAR will be required - targeted for 12/2011

 Project Status

 Initial Scope Approved

 MSIV procurement specification being developed

 Detailed Scope being developed

 Risk Benefit

 Very Small (<1E-06 / yr) - actual risk improvement

 Cost

 ~$ 400 M 12

Active Projects Protected Service Water

 Background

 Oconees Licensing Basis evolved over time; became complex and open to interpretation.

 Higher Risk Licensing Basis issues were on paths to resolution

 Emergency Feedwater

 Emergency Power

 Seismic

 Lower Risk Licensing Basis issues remained to be addressed

 Tornado

 High Energy Line Break (outside containment)

 Appendix R (Transition to NFPA-805) 13

Active Projects Protected Service Water Background, contd

 Standby Shutdown Facility (SSF)

 Designed to meet Appendix R, Turbine Building Flood (internal), and Sabotage.

 Maintains Units in Mode 3 from outside the Main Control Rooms

 Damage Control Measures used to cooldown and restore long term DHR

 Later credited for Station Blackout and Tornado

 Single train, with support system interdependencies

 Most Risk Significant set of systems at the Station

 SSF Risk Reduction Team focused on reliability / availability improvements 14

Active Projects Protected Service Water

 Background, contd

 Issaqueena Team Chartered

 Provide framework for resolution of Licensing Basis Issues

 Reduce Overall Station Risk

 Reduce Risk Worth of SSF

 Concept for PSW (Protected Service Water)

 Integral to licensing approach for Tornado, HELB, and Fire Protection

 Duplicates functions of SSF using equipment in the Auxiliary Building

 Supplies alternate power to SSF equipment

 Feasibility/Constructability Analyses

 Initial Scope/Licensing approach development

 Final Scope/commitment to construct

 Design/Licensing/Construction ; in progress.

 Licensing / Design Basis at risk; LARs not approved.

 Non-Seismic CDF Improvement: 20-25% risk reduction.

15

Protected Service Water Mechanical Scope Remove abandoned Diagram for PSW Keowee mechanical eqpt Mechanical Scope to make space for new Keowee PSW electrical eqpt.

Turbine Bldg New PSW Primary New Piping to U 3

( 2000 HP ) & Booster Condensate System

( 50 HP ) Pump for Test Line U1 & 2 U 2 CCW U 3 Ctrl Ctrl Rm Suction Rm New Piping to U 2 New Piping CCW for Pump Test / Min Flow Aux Bldg New Piping &

New Piping &

Isolation Vlvs Isolation Vlvs U1 U2 U3 RX Bldg Rx Bldg Rx Bldg 16

Protected Service Water Civil & Electrical Power Scope Keowee Diagram for PSW Install new circuit breakers for PSW Civil & Electrical Power Scope ACB - 9 ACB - 10 13 . 8 KV Power Feeder Circuit Existing Underground 15 KV Cable /Reels Keowee 13 . 8 KV PSW Power Feed 100 KV CT - 4 Xfmr Lee line to Blockhouse Central Pwr to U 1 /2 /3 PSW AB Turbine Loads & Backup Power to the following AB Eqpt  :

Bldg 1 ) U 1 / U 2 / U 3 HPI Pumps Power Feed 2 ) U 1 /U 2 / U 3 Vital I & C From Lee Battery Chargers . Line New PSW Xfmr Auxiliary & Switchgear Bldg Bckup Pwr to U 1 / 2 /3 Pzr Htrs Bldg U1 U2 U3 RX Bldg Rx Bldg Rx Bldg Backup Pwr for SSF Diesel Generator SSF CT-5 Xfmr 17

Protected Service Water Instrument & Control Scope Diagram for PSW Keowee Instrumentation & Control Scope Re - route Keowee Emergency Start Cables out of Turbine Bldg U1 & 2 Blockhouse MCR Ctrls for New PSW Turbine Bldg MCR Ctrls for New Pmp , Sw itchgear & U 1 / U2 PSW U 3 Specific Eqpt .

Specific Eqpt .

New PSW Xfm r

& Sw itchgear U1 & 2 U 2, 125 U 3 Ctrl Bldg U 1, 125 U 3 , 125 VDC Bus Ctrl Rm VDC Bus Rm VDC Bus Aux Bldg Re - route Vital I & C Prim ary & Backup Pow er Cables out of Turbine Bldg 18

Protected Service Water Project Status

 Complete

 Most of duct bank outside protected area

 PSW Building Foundation

 100kV Substation

 Unit 1 (Fall 2009) - all except HPI transfer switches and power panels

 Ongoing

 Equipment Manufacturing

 Duct Bank Construction

 PSW Building

 Unit 2 outage (Spring 2010) - will install portions of Main Control Board additions & some HPI mechanical scope

 Auxiliary Building piping, cable tray, and hangers

 Remaining

 Unit 1, 2 & 3 Refueling, Keowee, and Standby Shutdown Facility outages

 PSW Building and Equipment Installation

 PSW Duct Bank and Cable Installation

 Aux Service Water Demolition and Install PSW Pump

 SSF Alternate Power Supplies

 System Testing 19

Natural Phenomenon Barrier System Protected Service Water Projects

 Projects have been Managed Task with a contractor providing engineering and procurement specifications. Another contractor is the constructor and responsible for equipment / material procurement.

 Currently transitioning most remaining construction to Self Perform using supplemental personnel.

 Quality and Adherence to Standards is top priority and have not been compromised to achieve schedule. Numerous Stop Work and Stand-Downs to drive standards improvement.

 Initial schedule based on much higher production rates.

20

Natural Phenomenon Barrier System Protected Service Water Projects

 Improvement plans in place to reduce human performance issues and rework.

 oversight, risk awareness, human performance, procedure use and adherence, security, productivity, engineering quality and safety culture

 All critical equipment expedited.

 Outage work based on equipment availability.

 Work added well past outage schedule milestones.

21

Focus

 Maintaining healthy SCWE

 Continuous reinforcement that we will not compromise safety and quality standards even with aggressive scheduling

 Improving worker human performance and schedule predictability

 Ensuring quality manufacturing and on time delivery of materials and equipment

 Finalizing design

 Transferring construction work from contract constructor

 Strong oversight of remaining work to be completed by contract constructor 22

Work Windows

 Work Windows needed to complete the project:

 Spring 2010 - Unit 2 Outage

 Fall 2010 - Unit 3 Outage

 Spring 2011 - Unit 1 Outage

 Summer 2011 - Keowee Outage

 Fall 2011 - Unit 2 Outage; Outage SSF Outage

 Spring 2012 - Unit 3 Outage

 Station Aux Service Water Outage - Adjacent to last unit outage to transition to Protected Service Water.

 Schedule Commitments

 NPBS - 7/2011

 PSW - 7/2012 23

Tornado Commitments Current New Complete No. Commitment Due Date Due Date (Y/N) 1T U3 Control Room North Wall Modification. 5-2009 - Y 2T SSF Diesel Fuel Vent Modification. 12-2007 - Y SSF and CT-5 Trenches Intersection Modification SSF Trench at north 3T 6-2008 - Y end of SSF (TORMIS).

4T Natural Phenomena Barrier System Modifications. 12-2010 7-2011 N 5T Fiber Reinforced Polymer (FRP) LAR for strengthening selected 6T 11-2006 - Y masonry walls for tornado wind and P.

7T Tornado Mitigation Strategy LAR. 6-2008 - Y 8T PSW/HPI modifications. 12-2010 7-2012 N 9T Missile inventory program developed. 12-2007 Y Notify NRC management of significant changes in the scope and/or As necessary until As necessary until 10T N completion dates of the commitments. 12-2014 7-2016 11T U1:12-2012 U1:12-2014 12T Installation of MSIVs. U2:12-2014 U2:12-2015 N 13T U3:12-2013 U3: 7-2016 Fiber Reinforced Polymer (FRP) LAR for strengthening selected "brick" 14T 6-2009 - Y masonry walls for tornado wind and P.

24

HELB Commitments Current New Complete No. Commitment Due Date Due Date (Y/N)

Implement an inspection program for the Aux Bldg MS and FW girth 1H 11-2006 - Y and accessible attachment welds.

U1: 6-2008 Implement an inspection program for other Aux. Bldg high energy 2H U2: 12-2008 - Y piping critical crack locations at welds.

U3: 6-2009 Initial ASME Section XI ISI interval UT of the Aux. Bldg MS and FW 3H 7-2008 - Y girth welds and accessible attachment welds.

Initial ASME Section XI ISI interval UT of other Aux. Bldg high 3-2012 No change Y 4H energy piping critical crack locations at welds.

Implement an inspection program for accessible piping base metal 11-2006 - Y 5H downstream of the FW isolation valves located in the EPR.

Implement an inspection program for accessible piping base metal U1: 6-2008 6H of other Aux. Bldg high energy piping critical crack locations not at U2: 12-2008 - Y welds. U3: 6-2009 Initial ASME Section XI ISI interval UT inspection of piping base 7H 11-2006 - Y metal downstream of FW isolation valves located in the EPR.

Initial ASME Section XI ISI interval UT inspection for accessible 8H piping base metal of other Aux. Bldg high energy piping critical 3-2012 No change Y crack locations not at welds.

Implement an inspection program of accessible attachment welds at 9H 11-2006 - Y the terminal ends inside the FW guard pipe.

25

HELB Commitments Current New Complete No. Commitment Due Date Due Date (Y/N)

Initial visual inspections of accessible attachment welds at the terminal 10H 6-2007 - Y ends inside the FW guard pipe.

Inspect and repair the Unit 2 East Penetration Room electrical penetration termination enclosures to their correct configuration.

11H 11-2006 - Y Missing and/or damaged covers, gaskets, and fasteners will be repaired or replaced.

Inspect and repair the Unit 1 East Penetration Room electrical penetration termination enclosures to their correct configuration.

12H 12-2006 - Y Missing and/or damaged covers, gaskets, and fasteners will be repaired or replaced.

Inspect and repair the Unit 3 East Penetration Room electrical penetration termination enclosures to their correct configuration.

13H 11-2006 - Y Missing and/or damaged covers, gaskets, and fasteners will be repaired or replaced.

Create an inspection plan to select a portion of Units 1, 2 and 3 14H enclosures to open and inspect for signs of internal debris and 11-2006 - Y corrosion.

Revise station procedures and processes as needed to ensure 15H penetration termination enclosures are maintained in their correct 3-2007 - Y configurations.

Complete the design and installation of flood outlet devices for the Unit 16H 11-2006 - Y 1 East Penetration Room.

26

HELB Commitments Current New Complete No. Commitment Due Date Due Date (Y/N) 17H Complete the design and installation of flood outlet devices for the Unit 11-2006 - Y 2 East Penetration Room.

18H Complete the design and installation of flood outlet devices for the Unit 11-2006 - Y 3 East Penetration Room.

19H Complete the design and installation of flood impoundment and 12-2007 - Y exterior door flood improvement features for the Unit 1 East Penetration Room 20H Complete the design and installation of flood impoundment and 12-2007 - Y exterior door flood improvement features for the Unit 2 East Penetration Room.

21H Complete the design and installation of flood impoundment and 12-2007 - Y exterior door flood improvement features for the Unit 3 East Penetration Room.

22H U1: 6-2008 23H HELB LB and Mitigation Strategy LARs. U2: 12-2008 - Y 24H U3: 6-2009 Notify NRC management of significant changes in the scope and/or As necessary As necessary 25H N completion dates of the commitments. until 3-2012 until 7-2016 27

Other Projects

 Alloy 600 Remediation

 Buried Piping

 SSF Generator

 Keowee Major Maintenance

 License Renewal

 Replacement Rx Head NDE

 Feedwater Pump Turbine Controls

 24 Month Fuel Cycle

 Valve Controller Replacements (Pneumatic replaced with Digital)

 Keowee / Toxaway Relicensing 28

Action Items and Closing Remarks

 We have provided history and context regarding completed projects, risk improvements, and organization capabilities.

 Provided technical information, status, and projected risk improvements associated with current Oconee projects of regulatory interest.

 Reaffirmed Dukes commitment to Oconee projects of regulatory interest.

29