MONTHYEARNRC-09-0064, Submittal of the Inservice Testing Program Relief Requests for Pumps and Valves - Third Ten-Year Interval2009-11-0303 November 2009 Submittal of the Inservice Testing Program Relief Requests for Pumps and Valves - Third Ten-Year Interval Project stage: Request ML0934900022009-12-14014 December 2009 E-mail to A. Hassoun and R. W. Johnson - Submittal of the Inservice Testing Program Relief Requests for Pumps and Valves - Third Ten-year Interval (TAC Nos. ME2548 - ME2559) Project stage: Approval ML1017603332010-01-0707 January 2010 Submittal of IST Relief for Pumps and Valves - Third Ten-Year Interval Project stage: Other ML1004918562010-02-0505 February 2010 Relief Requests - IST Program - RAI - PRR-004, PRR-005, PRR-007, and PRR-010 - ME2552, ME2553, ME2554, ME2559 Project stage: RAI NRC-10-0023, Response to Request for Additional Information Regarding Relief Requests PRR-004, PRR-005, PRR-007 and PRR-010 for the Inservice Testing Program Third Ten-Year Interval2010-03-22022 March 2010 Response to Request for Additional Information Regarding Relief Requests PRR-004, PRR-005, PRR-007 and PRR-010 for the Inservice Testing Program Third Ten-Year Interval Project stage: Response to RAI ML1008304072010-03-23023 March 2010 Request for Additional Information - PRR-002 (ME2548), and PRR-003 (ME2549) - Application Dated 11/3/10 (ML093140302) Project stage: RAI ML1008201712010-03-24024 March 2010 Notice of Meeting with Progress Energy Carolinas Re Planned Amendment Requests Project stage: Meeting ML1009800042010-04-0707 April 2010 Pre-Application Meeting BSEP License Amendments Supporting Atrium 10XM Fuel Project stage: Meeting NRC-10-0033, Response to Request for Additional Information Regarding Relief Requests PRR-002 and PRR-003 for the Inservice Testing Program Third Ten-Year Interval2010-04-22022 April 2010 Response to Request for Additional Information Regarding Relief Requests PRR-002 and PRR-003 for the Inservice Testing Program Third Ten-Year Interval Project stage: Response to RAI ML1011305282010-04-22022 April 2010 Submittal of the Inservice Testing Program Relief Requests for Pumps and Valves - Third Ten-Year Interval - ME2552, ME2553 Project stage: Approval ML1016703512010-07-0606 July 2010 Evaluation of Relief Requests Nos. PRR-002, PRR-003, and PRR-006 for the Third 10-Year Interval Inservice Program Project stage: Approval ML1016703722010-07-0606 July 2010 Evaluation of Relief Requests Nos.: PRR-004, PRR-005, PRR-007, and PRR-010 for the Third 10-Year Interval Inservice Program Project stage: Approval BSEP 10-0083, Additional Information Supporting Requests for License Amendments - Addition of Analytical Methodology Topical Report to Technical Specification 5.6.5, Core Operating Limits Report2010-07-22022 July 2010 Additional Information Supporting Requests for License Amendments - Addition of Analytical Methodology Topical Report to Technical Specification 5.6.5, Core Operating Limits Report Project stage: Other ML13007A3732013-01-0808 January 2013 MELLLA Implementation Pre-Application Meeting January 08, 2013 Project stage: Meeting NRC-16-0028, Submittal of Revised Relief Request No. PRR-007 for the Inservice Testing Program Third 10-Year Interval2016-04-0505 April 2016 Submittal of Revised Relief Request No. PRR-007 for the Inservice Testing Program Third 10-Year Interval Project stage: Request 2010-03-24
[Table View] |
Similar Documents at Fermi |
|---|
|
Text
From:
Chawla, Mahesh Sent:
Tuesday, March 23, 2010 5:02 PM To:
Alan I Hassoun Cc:
Billerbeck, John; Giessner, John; Morris, R. Michael; Jones, Robert; Lerch, Robert
Subject:
FERMI 2 - REQUEST FOR ADDITIONAL INFORMATION - PRR-002 (ME2548),
AND PRR-003 (ME2549) - Application dated 11/3/10 (ML093140302)
In reference to your above application, please arrange a teleconference to discuss the following information with the NRC staff.
For Relief Request PRR-002 (Parallel Testing of Core Spray Pumps):
- 1. Will Group A type testing be performed at nominally full flow conditions of greater than or equal to 6,600 gpm per division?
- 2. Why are the monitoring, analysis, and evaluation requirements of ISTB-6000 limited to Alert and Action Range low criteria only (i.e., Alert and Action Range high criteria are not included)?
- 3. The relief request states that when a reference curve may have been affected by repair, replacement, or routine servicing of a pump, a new reference curve will be determined, or an existing reference curve will be reconfirmed. Is relief therefore being sought from ISTB-3310?
- 4. Will the vibration acceptance criteria of Table ISTB-5121-1 still apply and be applied to each pump individually. Will a single value be used over the whole range of the pump curve?
- 5. The relief request states that the first Comprehensive Pump Test (CPT) will be performed on each of the Core Spray pumps no later than February 17, 2013. When will the second CPT be performed?
For Relief Request PRR-003 (EECW Pump Testing with Pump Curves):
- 1. Will testing will be done at substantial flowrates of greater than or equal to 1,550 gpm?
- 2. Will the vibration acceptance criteria of Table ISTB-5121-1 still apply? Will a single value be used over the whole range of the pump curve?
- 3. Does this relief request apply also to the Comprehensive Pump Test (CPT) required by OM Code, or just the Group A test?
Mahesh Chawla Phone: 301-415-8371 Fax: 301-415-1222 mahesh.chawla@nrc.gov E-mail Properties
Mail Envelope Properties ()
Subject:
FERMI 2 - REQUEST FOR ADDITIONAL INFORMATION - PRR-002 (ME2548), AND PRR-003 (ME2549) - Application dated 11/3/10 (ML093140302)
Sent Date: 3/23/2010 4:47:01 PM Received Date: 3/23/2010 5:01:00 PM From: Chawla, Mahesh Created By: Mahesh.Chawla@nrc.gov Recipients:
hassouna@dteenergy.com (Alan I Hassoun)
Tracking Status: None John.Billerbeck@nrc.gov (Billerbeck, John)
Tracking Status: None John.Giessner@nrc.gov (Giessner, John)
Tracking Status: None R.Michael.Morris@nrc.gov (Morris, R. Michael)
Tracking Status: None Robert.Jones@nrc.gov (Jones, Robert)
Tracking Status: None Robert.Lerch@nrc.gov (Lerch, Robert)
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 15405 3/23/2010 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: