UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 March 24, 2010 Mr. Paul Freeman Site Vice President clo Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO.1 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NO. MD7651)
Dear Mr. Freeman:
On December 12, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
NextEra Energy Seabrook. LLC (the licensee) provided a response, dated February 11, 2008 (ADAMS Accession No. ML080450322), to Bulletin 2007-01. Once the licensee response was reviewed for Seabrook Station, Unit No.1 (Seabrook), the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on July 1, 2008 (ADAMS Accession No. ML081780102). The licensee provided a response to the RAI on August 15, 2008 (ADAMS Accession No. ML082320057), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Seabrook. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for Seabrook. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-2443.
Dennis Egan, P.E.
Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv
March 24, 2010 Mr. Paul Freeman Site Vice President c/o Mr. Michael O'Keefe NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874
SUBJECT:
SEABROOK STATION, UNIT NO.1 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATIENTIVENESS" (TAC NO. MD7651)
Dear Mr. Freeman:
On December 12,2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150).
NextEra Energy Seabrook. LLC (the licensee) provided a response, dated February 11, 2008 (ADAMS Accession No. ML080450322), to Bulletin 2007-01. Once the licensee response was reviewed for Seabrook Station, Unit NO.1 (Seabrook), the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on July 1, 2008 (ADAMS Accession No. ML081780102). The licensee provided a response to the RAI on August 15, 2008 (ADAMS Accession No. ML082320057), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Seabrook. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for Seabrook. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-2443.
Sincerely, Ira!
Dennis Egan, P.E.
Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLI-2Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpll-2 Resource RidsOgcRp Resource RidsNrrPMSeabrook Resource RidsNrrLABaxter Resource RidsRgn1 MailCenter Resource AMarkley, DPR/PGCB SStuchell, DPR/PGCB ADAMS Accession No' ML100770458 OFFICE LPLI-2/PM LPL 1-2/LA LPLI-21BC LPLI-2/PM NAME DEgan ABaxter HChernoff DEgan DATE 3/23/10 3/24/10 3/24/10 3/24/10 OFFICIAL RECORD COpy