UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 March 25, 2010 Mr. John 1. Carlin, Vice President RE. Ginna Nuclear Power Plant RE. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519 SUB~IECT:
R E. GINNA NUCLEAR POWER PLANT - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NO. MD7603)
Dear Mr. Carlin:
On December 12, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007 01, "Security Officer Attentiveness" (Agencywide Documents Access and Management System (ADAMS) Accession No. IVIL073400150).
RE. Ginna Nuclear Power Plant, LLC (the licensee) provided a response, dated February 11, 2008 (ADAMS Accession No. ML080500151), to Bulletin 2007-01. Once the licensee response was reviewed for RE. Ginna Nuclear Power Plant (Ginna), the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on July 9, 2008 (ADAMS Accession No. ML081830460). The licensee provided a response to the RAI on August 13, 2008 (ADAMS Accession No. ML082321125), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Ginna. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for Ginna. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1364.
Sincerely,
~~ V P~"-cet Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244 cc: Distribution via Listserv
ML080500151), to Bulletin 2007-01. Once the licensee response was reviewed for RE. Ginna Nuclear Power Plant (Ginna), the NRC staff identified a need for additional information. To gather that information, the NRC staff issued a Request for Additional Information (RAI) to the licensee on July 9,2008 (ADAMS Accession No. ML081830460). The licensee provided a response to the RAI on August 13, 2008 (ADAMS Accession No. ML082321125), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at Ginna. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that your response to Bulletin 2007-01 and the subsequent RAI is adequate for Ginna. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review, your response to the Bulletin 2007-01 is considered closed and no further action is requested of you at this time.
If you have any questions regarding this letter, please feel free to contact me at (301) 415-1364.
Sincerely, Ira!
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-244 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLI-1 Reading RidsAcrsAcnw MailCTR Resource RidsNrrDorlLpll-1 Resource RidsOgcRp Resource RidsRgn1 MailCenter Resource RidsNrrPMREGinna Resource RidsNrrLASLittle AMarkley, DPR/PGCB SStuchell, DPR/PGCB ADAMS Accession No'., ML100740667 OFFICE LPLI-1/PM LPLI-2/LA LPLI-1/BC LPLI-1/PM NAME DPickett ABaxter NSalqado DPickett DATE 3/23/10 3/22/10 3/25/10 3/25/10