UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 March 25, 2010 Mr. Paul A. Harden Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 - CLOSEOUT OF BULLETIN 2007-01 "SECURITY OFFICER ATTENTIVENESS" (TAC NOS.
MD7568 AND MD7569)
Dear Mr. Harden:
By letter dated December 12, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML073400150), the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2007-01, "Security Officer Attentiveness."
By letter dated February 11, 2008 (ADAMS Accession No. ML080440432), FirstEnergy Nuclear Operating Company (licensee) provided a response for Beaver Valley Power Station, Unit Nos.
1 and 2 (BVPS-1 and 2) to Bulletin 2007-01. After reviewing the licensee's response, the NRC staff identified a need for additional information. By letter dated July 10, 2008 (ADAMS Accession No. ML081780361), the NRC staff issued a request for additional information (RAI).
The licensee provided a response to the RAI on August 15, 2008 (ADAMS Accession No. ML082340846), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at BVPS-1 and 2. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that the responses to Bulletin 2007-01 and related RAI are adequate for BVPS-1 and 2. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review,Bulletin 2007-01 will be closed and no further action is required.
If you have any questions regarding this letter, please contact me at (301) 415-1016.
Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Distribution via Listserv Sincerely,
ML080440432), FirstEnergy Nuclear Operating Company (licensee) provided a response for Beaver Valley Power Station, Unit Nos.
1 and 2 (BVPS-1 and 2) to Bulletin 2007-01. After reviewing the licensee's response, the NRC staff identified a need for additional information. By letter dated July 10, 2008 (ADAMS Accession No. ML081780361), the NRC staff issued a request for additional information (RAI).
The licensee provided a response to the RAI on August 15, 2008 (ADAMS Accession No. ML082340846), which included detailed descriptions of the administrative and managerial controls to deter and address inattentiveness and complicity among licensee security personnel at BVPS-1 and 2. Due to the sensitivity of the subject matter, some responses may contain Security-Related Information and may not be publicly available.
The NRC staff has reviewed the submitted information and has concluded that the responses to Bulletin 2007-01 and related RAI are adequate for BVPS-1 and 2. The bases for the NRC's conclusion have been documented in a memorandum, "Security Bulletin 2007-01, Security Officer Attentiveness: Summary Report" (ADAMS Accession No. ML093440311). Based on this review,Bulletin 2007-01 will be closed and no further action is required.
If you have any questions regarding this letter, please contact me at (301) 415-1016.
Sincerely, Ira/
Nadiyah S. Morgan, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPLI-1 Reading RidsAcrsAcnw MailCTR RidsNrrDorlLpll-1 RidsOgcRp Resource RidsRgn1 MailCenter RidsNrrPMBeaverValley RidsNrrLASLittie SStuchell, DPR/PGCB Accession No*.. ML100610598 OFFICE LPLI-1/PM LPL 1-2/LA LPLI-1/BC LPLI-1/PM NAME NMorQan ABaxter NSalQado NMorgan DATE 3/25/10 3/22/2010 3/25/10 3/25/10