MONTHYEARML24032A4762024-02-0101 February 2024 Final Report of a Part 21 Evaluation Associated with Starter Contactors for the BFN Unit 1 High Pressure Coolant Injection Suppression Pool Inboard Suction Valve ML24023A2802024-01-23023 January 2024 Final Report of a Deviation or Failure to Comply Associated with a Relay in the Reactor Core Isolation Cooling Condensate Pump CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions ML24016A3042024-01-16016 January 2024 Final Report of a Part 21 Evaluation Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump CNL-23-071, Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-472024-01-11011 January 2024 Response to Request for Additional Information Regarding Browns Ferry Nuclear Plant, Units 1, 2, and 3, Inservice Inspection and Augmented Program Interval Revised Request for Alternative 0-ISI-47 ML24022A1732024-01-0303 January 2024 Receipt and Availability of the Subsequent License Renewal Application ML23319A1992024-01-0303 January 2024 Issuance of Amendment Nos. 333, 356, and 316 Regarding the Technical Specification Surveillance Requirements 3.4.3.2 and 3.5.1.11 Regarding Safety Relief Valves ML23355A2062023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23348A3942023-12-14014 December 2023 Interim Part 21 Report of a Potential Deviation or Failure to Comply Associated with Starter Contactors for the High Pressure Coolant Injection Suppression Pool Inboard Suction Valve IR 05000259/20230102023-12-11011 December 2023 Commercial Grade Dedication Inspection Report 05000259/2023010 and 05000260/2023010 and 05000296/2023010 ML23335A0722023-12-0101 December 2023 Interim Report of a Deviation or Failure to Comply Associated with a Relay in the Unit 2 Reactor Core Isolation Cooling Condensate Pump ML23334A2492023-11-30030 November 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-070, Submittal of Fifth 10-Year Interval Inservice Testing Program Plan2023-11-29029 November 2023 Submittal of Fifth 10-Year Interval Inservice Testing Program Plan ML23331A2532023-11-27027 November 2023 Summary Report for 10 CFR 50.9 Evaluations, Technical Specifications Bases Changes, Technical Requirement Manual Changes, and NRC Commitment Revisions CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23325A1102023-11-21021 November 2023 Anchor Darling Double Disc Gate Valve Commitment Revision ML23320A2542023-11-16016 November 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump IR 05000259/20230032023-11-13013 November 2023 Integrated Inspection Report 05000259/2023003, 05000260/2023003 and 05000296/2023003 IR 05000259/20230402023-11-0202 November 2023 Supplemental Inspection Supplemental Report 05000259 2023040 and Follow-Up Assessment Letter ML23292A2532023-10-18018 October 2023 BFN 2024-301, Corporate Notification Letter (210-day Ltr) ML23282A0022023-10-0606 October 2023 Interim Part 21 Report of a Deviation or Failure to Comply Associated with Check Valve 0-CKV-023-0565 for D1 Residual Heat Removal Service Water Pump ML23278A0122023-10-0505 October 2023 Updated Final Safety Analysis Report, Amendment 30 ML23271A1702023-09-28028 September 2023 Site Emergency Plan Implementing Procedure Revision ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23257A1232023-09-22022 September 2023 Administrative Changes to Technical Specification Pages Issued for License Amendment Nos. 332, 355, and 315 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23263B1042023-09-20020 September 2023 Special Report 260/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML23205A2132023-09-0808 September 2023 Issuance of Amendment Nos. 332, 355, and 315 Regarding the Revision of Technical Specifications to Adopt TSTF-566-A and TSTF-580-A, Rev. 1 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000259/20230052023-08-29029 August 2023 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2023005, 05000260/2023005 and 05000296/2023005 ML23233A0432023-08-18018 August 2023 Enforcement Action EA-22-122 Inspection Readiness Notification ML23219A1542023-08-17017 August 2023 Request to Use Later Edition of ASME Code for Operation and Maintenance and Alternative Requests BFN-IST-01 Through 05 for the Fifth 10-Year Interval Inservice Testing Program ML23228A1642023-08-16016 August 2023 Site Emergency Plan Implementing Procedure Revision ML23228A0202023-08-15015 August 2023 (BFN) Unit 1 - Special Report 259/2023-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation IR 05000259/20230022023-08-10010 August 2023 Integrated Inspection Report 05000259/2023002, 05000260/2023002, 05000296/2023002 and 07200052/2023001 ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills ML23171A8862023-07-24024 July 2023 Issuance of Amend. Nos. 331, 354, and 314; 365 and 359 Regarding Adoption of TSTF-541-A, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23201A2182023-07-20020 July 2023 Registration of Use of Cask to Store Spent Fuel (MPC-298 and -299) ML23159A2552023-07-20020 July 2023 Proposed Alternative to the Requirements of the ASME Code Regarding Volumetric Inspection of Standby Liquid Control Nozzles ML23199A3072023-07-18018 July 2023 Site Emergency Plan Implementing Procedure Revision CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions IR 05000259/20233012023-07-18018 July 2023 NRC Operator License Examination Report Nos. 05000259/2023301, 05000260/2023301, and 05000296/2023301 2024-02-01
[Table view] Category:Licensee 30-Day Written Event Report
MONTHYEARML17200A0842017-07-19019 July 2017 Special Report 259/2017-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML16340A2072016-12-0505 December 2016 Transmittal of 10 CFR 50.46 30-Day Report ML16197A2872016-07-18018 July 2016 Voluntary Reporting of High Groundwater Tritium Levels ML15022A0142015-01-16016 January 2015 Special Report 260/2015-001 for Inoperable Post Accident Monitoring (PAM) Instrumentation ML14364A0252014-12-23023 December 2014 Offsite Dose Calculation Manual (ODCM) Special Report ML14175B3902014-06-20020 June 2014 CFR 50.46 30-Day Report Regarding Changes and Errors to the Calculated Peak Cladding Temperature for Emergency Core Cooling System Evaluation Model ML13010A0162013-01-0404 January 2013 CFR 50.46 30-Day Report ML12153A0532012-05-30030 May 2012 CFR 50.46 30-Day Report for Browns Ferry Nuclear Plant, Unit 3 ML1004801402010-02-12012 February 2010 Day Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes ML1004700522010-02-0808 February 2010 Submittal of 30-Day Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes 2017-07-19
[Table view] |
Text
Tennessee Valley Authority, 1101 Market Street, Chattanooga, Tennessee 37402-2801 February 8, 2010 10 CFR 50.46 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Browns Ferry Nuclear Plant, Units 2 and 3 Facility Operating License Nos. DPR-52 and DPR-68 NRC Docket Nos. 50-260 and 50-296
Subject:
30-Day Report of Emergency Core Cooling System (ECCS) Evaluation Model Changes The Tennessee Valley Authority (TVA) is submitting this report in accordance with 10 CFR 50.46(a)(3)(ii), due to changes in the model used to determine compliance with ECCS requirements.
During the NRC acceptance review of the Browns Ferry Nuclear Plant (BFN) Unit 1 license amendment request supporting the transition to ATRIUM-10 fuel (TS-467), NRC requested that TVA address the single failure of one or all Automatic Depressurization System (ADS) valves in the loss-of-coolant accident (LOCA) analysis.
The current AREVA NP LOCA analysis addresses BFN Units 1, 2, and 3 and is applicable to Units 2 and 3 and in the future for Unit 1 after the transition to AREVA NP fuel. The fuel in Unit 1 is currently provided by Global Nuclear Fuels. In response to the NRC question, AREVA NP has performed a LOCA analyses for TVA assuming a single failure of ADS automatic actuation caused by a station battery failure. This assessment addresses the use of ATRIUM-10 fuel for BFN Units 2 and 3 operations at the current licensed thermal power (CLTP) of 3458 megawatts thermal and the various break types (recirculation line suction and discharge, feedwater, and low pressure core spray line) used in the LOCA analyses. Credit for high pressure coolant injection at its Technical Specification flow was assumed rather than the more conservative value in the analysis of record, and manual opening of 4 ADS valves was assumed at 10 minutes.
For licensing basis peak clad temperature (PCT), the assessment showed that the worst break was found to be a recirculation discharge line break with an area of 0.25 ft2 . The resulting PCT was 2057 degrees Fahrenheit (OF). This estimated PCT change is 550 F
-APCn rD Printedon recycledpaper
U.S. Nuclear Regulatory Commission Page 2 February 8, 2010 relative to the current licensing basis PCT of 2002TF. Since the change exceeds 50'F, this is being reported within 30 days as required by 10 CFR 50.46(a)(3)(ii). Other 10 CFR 50.46 requirements (e.g., maximum cladding oxidation, maximum hydrogen generation) are maintained within limits.
TVA will provide an addendum report to the current AREVA NP analysis of record in April 2010. This addendum will contain the evaluation of this single failure. This report will address both extended power uprate and CLTP power levels.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact F. R. Godwin, Site Licensing and Industry Affairs Manager, at (256) 729-2636.
Respectfuly R. M. Krich Vice President Nuclear Licensing cc: