MONTHYEARBVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20240012024-06-28028 June 2024 NRC Inspection Report No. 05000271/2024001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24053A2572024-03-0101 March 2024 Withdrawal of Requested Licensing Action for a License Amendment Submitted for Approval of the License Termination Plan BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G IR 05000271/20230022024-02-20020 February 2024 NRC Inspection Report Nos. 05000271/2023002 and 07200059/2023001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 19, zoio Vice President, Operations Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 250 Governor Hunt Road Vernon, VT 05354
SUBJECT:
ENTERGY NUCLEAR VERMONT YANKEE LLC'S STATUS OF DECOMMISSIONING FUNDING ASSURANCE FOR VERMONT YANKEE NUCLEAR POWER STATION (TAC NO. ME0583)
Dear Sir or Madam:
The Nuclear Regulatory Commission (NRC) staff had previously reviewed the October 29, 2009, submittal, outlining Entergy's plan of action to cover shortfalls in decommissioning funding disclosed in the Vermont Yankee Nuclear Power Station Biennial Decommissioning Funding Report that was submitted on March 30, 2009. On December 28, 2009, the NRC accepted Entergy's plan of action with the provision that the NRC staff would seek verification that adequate financial assurance would be established as of December 31,2009.
Based on the information provided by Entergy on January 28, 2010, the NRC staff finds that Vermont Yankee Nuclear Power Station as of September 30, 2009, had a Decommissioning Trust Fund Balance of $419.8 million. Entergy established a Parent Company Guarantee in the amount of $40 million by December 31, 2009, to provide additional financial assurance. NRC staff has determined that the Trust Fund Balance, projected to the time of permanent cessation of operations in 2012, plus the verification of a Parent Company Guarantee will cover the projected shortfall.
Sincerely, p ~.
~ /<
James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-271 cc: Distribution via ListServ
February 19, 2010 Vice President, Operations Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 250 Governor Hunt Road Vernon, VT 05354
SUBJECT:
ENTERGY NUCLEAR VERMONT YANKEE LLC'S STATUS OF DECOMMISSIONING FUNDING ASSURANCE FOR VERMONT YANKEE NUCLEAR POWER STATION (TAC NO. ME0583)
Dear Sir or Madam:
The Nuclear Regulatory Commission (NRC) staff had previously reviewed the October 29, 2009, submittal, outlining Entergy's plan of action to cover shortfalls in decommissioning funding disclosed in the Vermont Yankee Nuclear Power Station Biennial Decommissioning Funding Report that was submitted on March 30, 2009. On December 28,2009, the NRC accepted Entergy's plan of action with the provision that the NRC staff would seek verification that adequate financial assurance would be established as of December 31,2009.
Based on the information provided by Entergy on January 28, 2010, the NRC staff finds that Vermont Yankee Nuclear Power Station as of September 30, 2009, had a Decommissioning Trust Fund Balance of $419.8 million. Entergy established a Parent Company Guarantee in the amount of $40 million by December 31,2009, to provide additional financial assurance. NRC staff has determined that the Trust Fund Balance, projected to the time of permanent cessation of operations in 2012, plus the verification of a Parent Company Guarantee will cover the projected shortfall.
Sincerely, IRA!
James Kim, Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-271 cc: Distribution via ListServ DISTRIBUTION:
PUBLIC RidsRgn1 MailCenter Resource RidsNrrPMPilgrim Resource LPL 1-1 R/F RidsNrrDorlLpl1-1 Resource RidsNrrLASLittle Resource MDusaniwskj RidsOgcRp Resource RidsAcrsAcnw_MailCenter Resource ADAMS Accession No.: ML100431486 OFFICE LPL1-1/PM LPL 1-1 ILA DPR/PFPB OGC/NLO LPL 1-1 IBC NAME JKim SLittie RCarlson SUttal RGuzman for (w/chanqes) NSalgado DATE 2/16/10 2/16/10 2/16/10 2/18/10 2/19/10 OFFICIAL RECORD COpy