Brunswick Nuclear Plant Human Performance NRC Region II Visit January 14, 2010
Agenda l Human Performance (HU) Excellence Plan w Development w Inputs w Focus Areas l Focus Area Key Actions l Results l Summary 2
01/13/10
HU Excellence Plan Development l
Benchmarked Industry l
Established a Living Plan with action assignments tracked by the Corrective Action Program l
Established Metrics to monitor effectiveness l
Action assignments tracked in the Corrective Action Program l
Plan reviewed by Fleet and INPO l
Aligned Station through high visibility and consistent communication of the plan 3
01/13/10
HU Excellence Plan Inputs l
Common Cause Analysis - 2008 w Risk Identification/Mitigation w Engineering Technical rigor w Equipment Reliability l
Corrective Action Program Trend Reports l
Site Level Human Performance Events l
INPO Performance Indicators l
NRC Cross Cutting Matrix 4
01/13/10
HU Excellence Plan Focus Areas l
Focus Areas l
Behavior Change and Reinforcement l
Procedures l
Risk Identification and Mitigation l
Work Control l
Key Enabler l
Training 5
01/13/10
Behavior Change and Reinforcement Key Actions l
17 Key actions l
Increased First Line Supervisor oversight of field activities l
Conducted Leadership Assessment l
Conducted Accountability training to all site personnel l
Site Leadership completed a Leadership workbook l
Established Supervisor Steering committee l
Enhanced oversight and training of Supplemental Personnel 01/13/10 6
Behavior Change and Reinforcement Key Actions l
Implemented Dynamic Learning Activities l
Implemented new Observation program in September 2009 w Allowed better trending of data w Improved entry and monitoring process w Implemented at a fleet level w Implemented in-process Technical review observations w Improved Major Projects utilization of the observation program l
Developed, proceduralized and implemented consistent HU clock reset criteria 01/13/10 7
Behavior Change and Reinforcement Key Actions l
Communicated HU Excellence Plan site-wide l
Established HU Program Oversight w HU Program Manager position reporting to Director of Site Operation w Human Performance Core Team lead by HU Program Manager as the implementation arm of the HUSC w Human Performance Steering Committee (HUSC) as the senior site management team w Review Boards w Shared learning through site and fleet communications w Nuclear Safety Review Committee standing agenda item l
Established and communicated NGG Leadership Behaviors 8
01/13/10
Behavior Change and Reinforcement Key Remaining Actions l
Develop supervisor training guideline to support line employee transition to supervision l
Perform Self-Assessment of monthly observations in comparison to monthly Nuclear Condition Reports to evaluate effectiveness of identifying, coaching & correcting behaviors at a low threshold l
Conduct a Supervisory effectiveness Self-Assessment l
Implement a training strategy to improve performance of supplemental craft, supervision and supplemental project management oversight 01/13/10 9
Procedures Key Actions l
46 Key Actions l
Site personnel completed an Adverse Human Performance Trend, Procedure Use and Adherence /
Work Management Activities, workbook l
Implemented industry best practices Procedure Use and Adherence standards into a fleet NGG procedure l
Placekeeping requirements established for procedures and work orders l
Developed and implemented a plan (resources &
timeline) to accelerate upgrade to site procedures and work off PRR backlog 01/13/10 10
Procedures Key Actions l
Implemented a graded approach to planning to prompt more rigorous reviews for pre-defined work activities l
Developed and implemented process for early identification of work activities requiring increased rigor reviews to confirm procedure adequacy l
Established maintenance planning review committee l
Proceduralized requirements for quality critical work tasks 01/13/10 11
Procedures Key Remaining Actions l Revise procedure writers guide to incorporate HU & industry best practices (Human factors) l Formalize the use of checklists for procedure writers and procedure reviewers l Work the plan to accelerate upgrade to site procedures and reduce PRR backlog l Conduct training on the Engineering Product Quality procedure focusing on processes and tools to improve quality 01/13/10 12
Risk Identification and Mitigation Key Actions l
22 Key Actions l Risk significant activities identified, communicated, supervisor oversight established and specific mitigation measures put in place and discussed at the morning meetings l Developed and implemented procedure 0AP-060, Technical Risk/Rigor Risk Assessment l Implemented improvements to the Post Maintenance Testing process 01/13/10 13
Risk Identification and Mitigation Key Actions l Implemented modification quality improvements l Revised BNP Integrated Scheduling procedure to include specific behavior changes that are expected for elevated risk activities l Implemented method to improve identification and evaluation of organizational contributors to events during Priority 1 and 2A investigations 01/13/10 14
Risk Identification and Mitigation Key Remaining Actions l Perform Self-Assessment on a site elevated risk activity/task including site behaviors, procedure compliance, and barriers put-in-place l Conduct a self-assessment on the implementation of AP-60, Technical Risk/Rigor Risk Assessment 01/13/10 15
Work Management Key Actions l
8 Key Actions l
Strengthened requirements on written guidance required to manipulate equipment l
Implemented Industry best practice for Skill of the Craft/Minor Maintenance work l
Implemented OPS-NGGC-1308, Plant Status Control at BNP l
Signage posted in plant to heighten awareness of work classifications and plant status control 01/13/10 16
Work Management Key Actions l
Revised Work Management Process procedure to make it clear that changing status of Work Order tasks to finish and using lists to track items not completed is not allowed.
l Implemented Plant Labeling upgrade 01/13/10 17
Work Management Key Remaining Actions l Complete plant labeling upgrade l Perform a site survey to verify knowledge level pertaining to the Work Management Process procedure requirements 01/13/10 18
Results Human Performance Event Tree 01/13/10 19
Results l Station HU Events: ~72% reduction in rate of site level HU events l Plant Status Control (PSC): ~50% reduction in rate of PSC events l Clearance Tagging: ~52% reduction in rate of tagging errors/precursor events 20 01/13/10
Site Human Performance Events - 2009 Average Days 52.8 Days Since Last Event 47 December Events 0
Year to Date Events 6
December 2009 Performance 01/13/10 21
Status Control Events - 2009 Improving Performance Trend 01/13/10 22
Clearance Tagging Events - 2009 01/13/10 23
Results l Operations HU Clock resets: 38% reduction in reset rate l Maintenance HU Clock resets: 45%
reduction in reset rate l Engineering HU Clock resets: 28 % reduction in reset rate 24 01/13/10
Results l
68% reduction in Procedure Use and Adherence Nuclear Condition Reports (NCRs) l Improved identification of procedure quality issues due to increased focus on procedure use and adherence prior to causing an adverse condition/event w Procedure Backlog increase due to early identification of issues w Increased Observations showing individuals stopping when questions arise and getting the procedure/work order fixed w 35% Reduction in Procedure Adequacy NCRs 25 01/13/10
Self Evaluation Roll-up Human Performance Improving Performance Trend 26 01/13/10
Procedure Related Events 01/13/10 27
Observations - 2009 Observed Stopping When Unsure 01/13/10 28
Critical Observations Improvement Opportunities 01/13/10 29
Summary l
We have identified, recognized, and have taken actions to address Human Performance l
We have a comprehensive HU Excellence Plan l
We have implemented timely and aggressive corrective actions l
Metrics demonstrate actions taken are improving performance l
Performance Improvement is institutionalized l
Sustainability w Focus is on Leadership, Behaviors, and key Process Changes 30 01/13/10