Senior Reactor and Reactor Operator Initial Examinations - J. A. FitzPatrick Nuclear Power Plant
ML092520570
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/09/2009
From: Hansell S
Operations Branch I
To: Peter Dietrich
Entergy Nuclear Northeast
Shared Package
ML092470037 List:
References
Download: ML092520570 (5)


Text

September 9, 2009 Mr. Peter T. Dietrich Site Vice President Entergy Nuclear Northeast James A. FitzPatrick Nuclear Power Plant Post Office Box 110 Lycoming, NY 13093

SUBJECT:

SENIOR REACTOR AND REACTOR OPERATOR INITIAL EXAMINATIONS -

J. A. FITZPATRICK NUCLEAR POWER PLANT

Dear Mr. Dietrich:

In a telephone conversation on August 20, 2009 between Mr. John G. Caruso, Senior Operations Engineer/Chief Examiner and Mr. Joseph Barnes, Training Manager, arrangements were made for the administration of licensing examinations at J.A. FitzPatrick Nuclear Power Plant during the week of May 3, 2010.

As agreed during the telephone conversation, the staff of the U.S. Nuclear Regulatory Commission (NRC) will prepare the examinations based on the guidelines in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1.

Your staff will be given the opportunity to review the examinations during the week of April 5, 2010.

The reference materials identified in Attachment 3 to ES-201 will be due by September 4, 2009.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked.

In order to conduct the requested written and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-401, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressure, temperatures, and levels) generated during dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

P. Dietrich 2 This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018. The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C. 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosures will be available electronically for public inspection in the NRC=s Public Document Room or from the Publicly Available Records (PARS) component of the NRC=s Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC=s public Web site at http://www.nrc.gov/reading-rm/adams.html.

Thank you for your cooperation in this matter. Mr. Barnes has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact John Caruso at (610) 337-5389, or me at (610) 337-5046.

Sincerely,

/RA/

Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No: 50-333 License No: DPR-59

P. Dietrich 2 This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018. The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C. 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosures will be available electronically for public inspection in the NRC=s Public Document Room or from the Publicly Available Records (PARS) component of the NRC=s Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC=s public Web site at http://www.nrc.gov/reading-rm/adams.html.

Thank you for your cooperation in this matter. Mr. Barnes has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact John Caruso at (610) 337-5389, or me at (610) 337-5046 Sincerely,

/RA/

Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No. 50-220 License No. DPR-63 SUNSI Review Complete: JGC (Reviewer=s Initials)

ADAMS PKG: ML092470037 ADAMS ACC# ML092520570 DOCUMENT NAME: G:\DRS\Operations Branch\CARUSO\Exam 10-Fitz May 10 (U01786)\120dayexamltr.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CBixler/CJB JCaruso/JGC SHansell/SLH DATE 09/09/09 09/09/09 09/09/09 OFFICIAL RECORD COPY

P. Dietrich 3 cc w/encl:

Senior Vice President and COO, Entergy Nuclear Operations Vice President, Oversight, Entergy Nuclear Operations Senior Manager, Nuclear Safety and Licensing, Entergy Nuclear Operations Assistant General Counsel, Entergy Nuclear Operations E. Dorman, Acting Manager, Licensing, Entergy Nuclear Operations P. Eddy, New York State Department of Public Service P. Church, Oswego County Administrator Supervisor, Town of Scriba C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law S. Lousteau, Treasury Department, Entergy Services J. Spath, Program Director, New York State Energy Research and Development Authority F. Murray, President & CEO New York State Energy Research and Development Authority J. Barnes, Manager, Training and Development

P. Dietrich 4 Distribution: (via E-mail)

S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP M. Gray, DRP B. Bickett, DRP J. Heinly, DRP S. McCarver, DRP L. Trocine, RI OEDO R. Nelson, NRR M. Kowal, NRR A. Muniz, PM NRR J. Hughey, NRR G. Hunegs, DRP, Senior Resident Inspector S. Rutenkroger, DRP, Resident Inspector K. Kolek, Resident OA D. Bearde, DRP Region I Docket Room (with concurrences)

D. Roberts, DRS P. Wilson, DRS S. Hansell, DRS Distribution:

C. Bixler, DRS (Exam Master File) w/concurrences DRS File