MONTHYEARML0924401762009-09-29029 September 2009 Cover Letter Transmitting the Draft Safety Evaluation of Boiling Water Reactors Owners' Group Topical Report NEDC-33347, Revision 0, Containment Overpressure Credit for Net Positive Suction Head (Npsh). Project stage: Draft Approval 2009-09-29
[Table View] |
|
---|
Category:Letter
MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
September 29, 2009 Mr. Doug Coleman Chair, BWROG Energy Northwest Columbia Generating Station Mail Drop PE20 P.O. Box 968 Richland, WA 99352-0968
SUBJECT:
DRAFT SAFETY EVALUATION OF BOILING WATER REACTORS OWNERS=
GROUP (BWROG) TOPICAL REPORT NEDC-33347, REVISION 0, "CONTAINMENT OVERPRESSURE CREDIT FOR NET POSITIVE SUCTION HEAD (NPSH)" (TAC NO. MD8146)
Dear Mr. Coleman:
By letter dated February 15, 2008 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML080520268 ), the BWROG submitted topical report (TR)
NEDC-33347, Revision 0, "Containment Overpressure Credit for Net Positive Suction Head (NPSH)" to the U.S. Nuclear Regulatory Commission (NRC) staff for review. Enclosed for the BWROG review and comment is a copy of the NRC staff's draft safety evaluation (SE) for the TR.
Pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR), we have determined that the enclosed draft SE does contain proprietary information. We have marked with bold text inside single brackets, the information we determined to be proprietary. If you believe that any additional information in the enclosure is proprietary, please identify such information line-by-line and define the basis pursuant to the criteria of 10 CFR 2.390.
Twenty working days are provided for you to comment on any additional proprietary content, factual errors, or clarity concerns contained in the SE. The final SE will be issued after making any necessary changes and a redacted (non-proprietary) version will be made publicly available.
The NRC staff's disposition of your comments on the draft SE will be discussed in the final SE.
D. Coleman To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Michelle C. Honcharik at 301-415-1774.
Sincerely,
/RA/
Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 691
Enclosure:
Draft SE cc w/out encl: See next page
D. Coleman To facilitate the NRC staff's review of your comments, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes.
If you have any questions, please contact Michelle C. Honcharik at 301-415-1774.
Sincerely,
/RA/
Stacey L. Rosenberg, Chief Special Projects Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 691
Enclosure:
Draft SE cc w/out encl: See next page DISTRIBUTION:
PUBLIC (Cover memo)
NON-PUBLIC (Enclosed Draft SE)
PSPB Reading File RidsNrrDpr RidsNrrDprPspb RidsNrrPMMHoncharik RidsNrrLADBaxley RidsOgcMailCenter RidsAcrsAcnwMailCenter RidsNrrDssScvb (Robert Dennig)
Richard Lobel Ahsan Sallman Zena Abdullahi ADAMS ACCESSION NO.: Package: ML092450068, Memo: ML092440176, Enclosure (Proprietary Draft SE): ML092440170
- No major changes to SE input. NRR-043 OFFICE PSPB/PM PSPB/LA SCVB/BC* PSPB/BC NAME MHoncharik DBaxley RDennig SRosenberg (CHawes for)
DATE 9/2/09 9/3/09 8/14/2009 9/29/09 OFFICIAL RECORD COPY
BWR Owners= Group Project No. 691 Mr. Richard Libra Executive Vice Chair, BWR Owners= Group Mr. Craig J. Nichols, Program Manager Exelon Generation Co, LLC GE-Hitachi Nuclear Energy 200 Exelon Way PO Box 780 M/C F12 Mail Code KSA 2-N 3901 Castle Hayne Road Kennett Square, PA 19348 Wilmington, NC 28402 Rick.libra@exeloncorp.com craig.nichols@ge.com Mr. Richard Anderson Oscar Limpias BWROG, Executive Chair Entergy Nuclear Northeast FPL Energy (DAEC) 1340 Echelon Parkway.
Duane Arnold Energy Center Jackson, MS 39213-8202 3277 DAEC Road olimpia@entergy.com Palo, IA 52324 rich.anderson@fpl.com Joe Donahue Progress Energy Inc.
Mr. James F. Klapproth 410 S. Wilmington St.
GE-Hitachi Nuclear Energy PEB 6A M/C A50 Raleigh, NC 27601-1849 3901 Castle Hayne Road joe.w.donahue@pgnmail.com Wilmington, NC 28401 james.klapproth@ge.com Paul J. Davison Hope Creek Generating Station Mr. Joseph E. Conen, Vice Chair P.O. Box 236 Regulatory Response Group Hancocks Bridge, NJ 08038 BWR Owners= Group paul.davison@pseg.com DTE Energy-Fermi 2 200 TAC Mr. Ted Schiffley 6400 N. Dixie Highway Vice Chairman, BWROG Newport, MI 48166 Exelon Generation Co., LLC.
conenj@dteenergy.com Cornerstone II at Cantera 4300 Winfield Road Dennis Madison, Hatch Vice President Warrenville, IL 60555 Southern Nuclear Operating Co. frederick.schiffley@exeloncorp.com 11028 Hatch Parkway North Baxley, GA 31515-2010 Mr. Randy C. Bunt, Chair drmadiso@southernco.com Regulatory Response Group Southern Nuclear Operating Company Frederick Emerson 40 Inverness Center Parkway/Bin B057 BWROG, Project Manager Birmingham, AL 35242 Frederick.emerson@ge.com rcbunt@southernco.com 8/28/09