FACILITY NAME:
McGuire Nulear Plant Section 11 REPORTNUMBER: ____ ~O~5~OO~O~3~69~1~37~O~~~O~09~-~30~1~ ____ _
FINAL SIM/IN-PLANT JPMS CONTENTS:
o Final SIM/ln-Plant JPMs o 'As given' with changes made during administration annotated Location of Electronic Files:
SubmittedBy:~' ~~~
FACILITY NAME:
McGuire Nulear Plant Section 11 REPORTNUMBER: ____ ~O~5~OO~O~3~69~/~37~O~~~O~09~-~30~1~ ____ _
FINAL SIM/IN-PLANT JPMS CONTENTS:
o Final SIM/ln-Plant JPMs o 'As given' with changes made during administration annotated Location of Electronic Files:
SubmittedBy:~' b:#:==::::::;k--t------ Verified B y--l---"---L..---"'-_~~L>...c:::~~
Appendix C Job Performance Measurl3 Worksheet Form ES-C-1 SIM JPM A 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 SIM JPM A 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C Facility:
Task
Title:
McGuire Job Performance Measure Worksheet Task No.:
Emergency Borate the Reactor JPM No.:
Coolant System Using the PD Pump KIA
Reference:
004, A4.18, 4.3/4.1 Form ES-C-1 2009 Systems - Control Room JPM A (Alternate Path)
Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The PD Pump is running and both Boric Acid Transfer Pumps running with 30 gpm or greater emergency boration flow indicated.
Required Materials:
None 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Facility:
Task
Title:
McGuire Job Performance Measure Worksheet Task No.:
Emergency Borate the Reactor JPM No.:
Coolant System Using the PD Pump KIA
Reference:
004, A4.18, 4.3/4.1 Form ES-C-1 2009 Systems - Control Room JPM A (Alternate Path)
Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The PD Pump is running and both Boric Acid Transfer Pumps running with 30 gpm or greater emergency boration flow indicated.
Required Materials:
None 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 General
References:
EP/1/A/5000/FR-S.1, Response To Nuclear Power Generation/ATWS EP/1A/5000/G-1, Generic Enclosure -17, PD Pump Start Handouts:
Time Critical Task:
Validation Time:
EP/1/A/5000/FR-S.1, Response To Nuclear Power Generation/ATWS marked up for place-keeping through Step 4.
NO 20 minutes 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 General
References:
EP/1/A/5000/FR-S.1, Response To Nuclear Power Generation/ATWS EP/1A/5000/G-1, Generic Enclosure -17, PD Pump Start Handouts:
Time Critical Task:
Validation Time:
EP/1/A/5000/FR-S.1, Response To Nuclear Power Generation/ATWS marked up for place-keeping through Step 4.
NO 20 minutes 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC # 39, 100% Power, MOL. Go to RUN.
- 2.
Insert:
- a.
- b.
MALF-IPE001A MALF-IPE001 B MALF-I PE002A MALF-IPE002B Failure of Auto Reactor Trips - Train A Failure of Auto Reactor Trips - Train B Failure of Manual Reactor Trips - Train A Failure of Manual Reactor Trips - Train B Form ES-C-1
- c.
MALF-NV029B NV pump trips on over current set to trigger 1 delay of 15 seconds
- d.
MALF-EP003C Zone 1 B Lockout set to trigger 1.
- e.
MALF-EP006B MALF-EP006D Failure of 1 TB to auto swap Failure of 1TD to auto swap
- f.
LOA-NV046 Pump Rack out 1A NV pump; Place red tag sticker on 1A NV
- 3.
Actuate Trigger 1.
- 4.
Manually exercise AlB Reactor Trip Switches.
- 5.
Perform steps 1 through 4 of EP/1/A/5000/FR-S.1.
- 6.
Trip the reactor 1 minute after starting the JPM by deleting:
MALF-IPE001A, Failure of Auto Reactor Trips - Train A MALF-IPE001 B, Failure of Auto Reactor Trips - Train B
- 7.
Ensure Letdown isolated.
- 8.
Allow plant time to stabilize and then Freeze Simulator.
- 1. Reset Simulator to Temporary Snap IC-122 (December, 2008).
- 2. Momentarily place Simulator in Run to acknowledge alarms.
- 3. Leave Simulator in FREEZE until operator is ready to begin.
NOTE:
During the performance of this JPM, the simulator operator will need to control CA flow to avoid NCS Cooldown and SI actuation.
2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC # 39,100% Power, MOL. Go to RUN.
- 2.
Insert:
- a.
- b.
MALF-IPE001A MALF-IPE001 B MALF-IPE002A MALF-IPE002B Failure of Auto Reactor Trips - Train A Failure of Auto Reactor Trips - Train B Failure of Manual Reactor Trips - Train A Failure of Manual Reactor Trips - Train B Form ES-C-1
- c.
MALF-NV029B NV pump trips on over current set to trigger 1 delay of 15 seconds
- d.
MALF-EP003C Zone 1 B Lockout set to trigger 1.
- e.
MALF-EP006B MALF-EP006D Failure of 1TB to auto swap Failure of 1TD to auto swap
- f.
LOA-NV046 Pump Rack out 1A NV pump; Place red tag sticker on 1A NV
- 3.
Actuate Trigger 1.
- 4.
Manually exercise AlB Reactor Trip Switches.
- 5.
Perform steps 1 through 4 of EP/1/Al5000/FR-S.1.
- 6.
Trip the reactor 1 minute after starting the JPM by deleting:
MALF-IPE001A, Failure of Auto Reactor Trips - Train A MALF-IPE001 B, Failure of Auto Reactor Trips - Train B
- 7.
Ensure Letdown isolated.
- 8.
Allow plant time to stabilize and then Freeze Simulator.
- 1. Reset Simulator to Temporary Snap IC-122 (December, 2008).
- 2. Momentarily place Simulator in Run to acknowledge alarms.
- 3. Leave Simulator in FREEZE until operator is ready to begin.
NOTE:
During the performance of this JPM, the simulator operator will need to control CA flow to avoid NCS Cooldown and SI actuation.
2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C Page 5 of 15 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1 IAl5000/FR-S. 1, Response To Nuclear Power Generation/ATWS marked up for place-keeping through step 4.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Step 5) Initiate emergency The operator recognizes boration of the NC System:
that there are no NV Pumps operating and proceeds to (Step 5.a) Ensure one NV Step 5.a RNO (Alternate Pump-ON.
Path).
2 (Step 5.a RNO) Place PD The operator seeks to find pump in service PER EP/1/A/5000/G-1 (Generic EP/1/A/5000/G-1 (Generic Enclosures), Enclosure 17.
Enclosures), Enclosure 17 (PD Pump Startup).
3 (Enclosure 17, Step 1)
The operator observes that Check power available to the Green status light is LIT, PD pump - AVAILABLE.
and determines that power is available to the PD Pump.
2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Page 5 of 15 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1 IAl5000/FR-S. 1, Response To Nuclear Power GenerationlATWS marked up for place-keeping through step 4.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Step 5) Initiate emergency The operator recognizes boration of the NC System:
that there are no NV Pumps operating and proceeds to (Step 5.a) Ensure one NV Step 5.a RNO (Alternate Pump-ON.
Path).
2 (Step 5.a RNO) Place PD The operator seeks to find pump in service PER EP/1/ A/5000/G-1 (Generic EP/1/ A/5000/G-1 (Generic Enclosures), Enclosure 17.
Enclosures), Enclosure 17 (PD Pump Startup).
3 (Enclosure 17, Step 1)
The operator observes that Check power available to the Green status light is LIT, PD pump - AVAILABLE.
and determines that power is available to the PD Pump.
2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 4
5 Page 6 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Steps 2.a-d) Reset the The operator observes that following:
the SI reset lights are LIT.
SII The operator observes that Sequencers the A Train Sequencer reset Phase B Isolation light is LIT.
If at any time a B/O signal The operator depresses the occurs then start SII B Train Sequencer reset equipment previously on.
pushbutton and observes that the Sequencer reset light is LIT.
The operator observes that the Phase B Isolation reset lights are LIT.
(Step 3) Close the following:
The operator observes the Close 1 RN-279B (AB Vent 1 RN-279B Green status Sys Return Isol).
light LIT, Red status light OFF.
Close 1 RN-299A (AB Vent The operator depresses the 1 RN-299A CLOSE Sys Return Isol).
pushbutton and observes Green status light LIT, Red status light OFF.
Close 1 RV-79A (U1 VU The operator depresses AHUS RV Cont Outside and holds the 1 RV-79A Supply Hdr Isol).
CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses Close 1RV-101A (U1 VU and holds the 1RV-101A AHUS RV Cont Inside CLOSE pushbutton and Return Hdr Isol).
observes Green status light LIT, Red status light OFF.
Close 1 RV-32A (U1 VL/VT The operator depresses the 1 RV-32A CLOSE AHUS RV Cont Outside pushbutton and observes Supply Hdr Isol).
Green status light LIT, Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 4
5 Page 6 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Steps 2.a-d) Reset the The operator observes that following:
the SI reset lights are LIT.
SII The operator observes that Sequencers the A Train Sequencer reset Phase B Isolation light is LIT.
If at any time a B/O signal The operator depresses the occurs then start SII B Train Sequencer reset equipment previously on.
pushbutton and observes that the Sequencer reset light is LIT.
The operator observes that the Phase B Isolation reset lights are LIT.
(Step 3) Close the following:
The operator observes the Close 1 RN-279B (AB Vent 1 RN-279B Green status Sys Return Isol).
light LIT, Red status light OFF.
Close 1 RN-299A (AB Vent The operator depresses the 1 RN-299A CLOSE Sys Return Isol).
pushbutton and observes Green status light LIT, Red status light OFF.
Close 1 RV-79A (U1 VU The operator depresses AHUS RV Cont Outside and holds the 1 RV-79A Supply Hdr Isol).
CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses Close 1 RV-101A (U1 VU and holds the 1RV-101A AHUS RV Cont Inside CLOSE pushbutton and Return Hdr Isol).
observes Green status light LIT, Red status light OFF.
Close 1 RV-32A (U1 VLIVT The operator depresses the 1 RV-32A CLOSE AHUS RV Cont Outside pushbutton and observes Supply Hdr Isol).
Green status light LIT, Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 5
(Cont'd) 6 Page 7 of 15 PERFORMANCE INFORMATION ELEMENTS Close 1 RV-76A (U1 VLIVT AHUS RV Cont Inside Return Hdr Isol).
Close 1 RV-80B (U 1 VU AHUS RV Cont Inside Supply Hdr Isol).
Close 1 RV-102B (U1 VU AHUS RV Cont Outside Return Hdr Isol).
Close 1 RV-33B (U1 VLIVT AHUS RV Cont Inside Supply Hdr Isol).
Close 1 RV-77B (U 1 VLIVT AHUS RV Cont Outside Return Hdr Isol).
(Step 4) Check any NC pump -ON STANDARD The operator depresses the 1 RV-76A CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RV-80B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RV -1 02B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 RV-33B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 RV-77B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator observes the NC Pump Safety breakers Green status light LIT, Red status lights OFF, determines that no NC pumps are on and proceeds to the 4 RNO.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 5
(Cont'd) 6 Page 7 of 15 PERFORMANCE INFORMATION ELEMENTS Close 1 RV-76A (U1 VLIVT AHUS RV Cont Inside Return Hdr Isol).
Close 1 RV-80B (U1 VU AHUS RV Cont Inside Supply Hdr Isol).
Close 1 RV-102B (U1 VU AHUS RV Cont Outside Return Hdr Isol).
Close 1 RV-33B (U1 VLIVT AHUS RV Cont Inside Supply Hdr Isol).
Close 1 RV-77B (U1 VLIVT AHUS RV Cont Outside Return Hdr Isol).
(Step 4) Check any NC pump -ON STANDARD The operator depresses the 1 RV-76A CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RV-80B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RV-1 02B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 RV-33B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 RV-77B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
Note eses.
are
~.tbeoPeratQt':: :.
ne. lWaitfor,. th,i'! L; **,.
valve to cornplet~IY cych:i/':
i~ef6re; takingacti~~~~tl1.'
the next v~lve~.} i':;;;* :1;:,.u,'
The operator observes the NC Pump Safety breakers Green status light LIT, Red status lights OFF, determines that no NC pumps are on and proceeds to the Ste 4 RNO.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS
- 7 8
9 10 Page 8 of 15 PERFORMANCE INFORMATION ELEMENTS (Step 4 RNO) Close the following:
1 RN-252B (RB Non Ess Sup Cont Outside 1501) 1 RN-277B (RB Non Ess Ret Cont Outside 1501)
(Step 5) Place the following RF pumps in "MAN" and ensure they are off:
A Jockey pump B Jockey pump (Step 6) Dispatch operator to close 2RL-267 (Unit 2 6900V Swgr Room AHU Supply From RN Inlet Isol)
(service bldg, 739+5, U-31, NE corner of service bldg over pit, near KR storage tank).
(Caution prior to Step 7)
Both trains RN valves must be aligned in Step 7 unless specified otherwise, even if power is lost.
STANDARD The operator depresses and holds the 1 RN-252B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RN-277B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the A RF Jockey Pump MAN pushbutton and observes the Green status light is LIT, Red status light OFF.
The operator depresses the B RF Jockey Pump MAN pushbutton and observes the Green status light is LIT, Red status light OFF.
The operator contacts an NEO and directs that 2RL-267 be closed.
The operator reads Caution and proceeds to Note prior to Step 7.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS
- 7 8
9 10 Page 8 of 15 PERFORMANCE INFORMATION ELEMENTS (Step 4 RNO) Close the following:
1 RN-252B (RB Non Ess Sup Cont Outside 1501) 1 RN-277B (RB Non Ess Ret Cont Outside 1501)
(Step 5) Place the following RF pumps in "MAN" and ensure they are off:
A Jockey pump B Jockey pump (Step 6) Dispatch operator to close 2RL-267 (Unit 2 6900V Swgr Room AHU Supply From RN Inlet Isol)
(service bldg, 739+5, U-31, NE corner of service bldg over pit, near KR storage tank).
(Caution prior to Step 7)
Both trains RN valves must be aligned in Step 7 unless specified otherwise, even if power is lost.
STANDARD The operator depresses and holds the 1 RN-252B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses and holds the 1 RN-277B CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the A RF Jockey Pump MAN pushbutton and observes the Green status light is LIT, Red status light OFF.
The operator depresses the B RF Jockey Pump MAN pushbutton and observes the Green status light is LIT, Red status light OFF.
The operator contacts an NEO and directs that 2RL-267 be closed.
The operator reads Caution and proceeds to Note prior to Step 7.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 11 12 13 Page 9 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Note prior to Step 7) If The operator reads Note OAC is unavailable to check and proceeds to Step 7.
any deenergized valve.
positions, RNO contains required actions if position unknown.
(Steps 7/7.a) Align RN to The operator observes that "AB Non Essential Header" the 1 A RN Pump Red as follows:
Breaker status light is LIT.
Ensure 1 A RN pump - ON.
(Step 7.b) Check at least one of the following valves -
closed:
The operator observes that 1 RN-41 B (Train B To Non the Green status light is LIT, Ess Hdr Isol) and the Red status light is OFF.
OR 1 RN-43A (Train B To Non The operator observes that the Red status light is LIT, Ess Hdr Isol).
and the Green status light is OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 11 12 13 Page 9 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Note prior to Step 7) If The operator reads Note OAC is unavailable to check and proceeds to Step 7.
any deenergized valve.
positions, RNO contains required actions if position unknown.
(Steps 7/7.a) Align RN to The operator observes that "AB Non Essential Header" the 1 A RN Pump Red as follows:
Breaker status light is LIT.
Ensure 1 A RN pump - ON.
(Step 7.b) Check at least one of the following valves -
closed:
The operator observes that 1 RN-41 B (Train B To Non the Green status light is LIT, Ess Hdr Isol) and the Red status light is OFF.
OR 1 RN-43A (Train B To Non The operator observes that the Red status light is LIT, Ess Hdr Isol).
and the Green status light is OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 14 15 16 Page 10 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 7.c.1-4) Open the following valves:
Open 1 RN-40A (Train A to The operator observes the Non Ess Hdr Isol) 1 RN-40A Red status light LIT, Green status light OFF.
Open 1 RN-42A (AS Non The operator observes the Ess Supply Isol) 1 RN-42A Red status light LIT, Green status light OFF.
The operator depresses the Open 1 RN-63S (AS Non 1 RN-63S OPEN pushbutton Ess Return Isol) and observes Red status light LIT, Green status light OFF.
1 RN-64A (AS Non Ess The operator depresses the 1 RN-64A OPEN pushbutton Return Isol) and observes Red status light LIT, Green status light OFF.
(Step 7.d) Check 1A RN The operator observes that pump flow as follows:
the 1 A RN Pump suction valves are OPEN (Red If RN pump suction aligned status lights LIT, Green to Low Level Intake, then status lights OFF).
check 1 A RN pump flow -
less than 16,000 gpm.
The operator observes 1 A OR RN flow (1 RNP-5040) to be
==5500 gpm.
If RN pump suction aligned to SNSWP.....
(Step 7.e) GO TO Step 8.
The operator proceeds to Step 8.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 14 15 16 Page 10 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 7.c.1-4) Open the following valves:
Open 1 RN-40A (Train A to The operator observes the Non Ess Hdr Isol) 1 RN-40A Red status light LIT, Green status light OFF.
Open 1 RN-42A (AS Non The operator observes the Ess Supply Isol) 1 RN-42A Red status light LIT, Green status light OFF.
The operator depresses the Open 1 RN-63S (AS Non 1 RN-63S OPEN pushbutton Ess Return Isol) and observes Red status light LIT, Green status light OFF.
1 RN-64A (AS Non Ess The operator depresses the 1 RN-64A OPEN pushbutton Return Isol) and observes Red status light LIT, Green status light OFF.
(Step 7.d) Check 1A RN The operator observes that pump flow as follows:
the 1 A RN Pump suction valves are OPEN (Red If RN pump suction aligned status lights LIT, Green to Low Level Intake, then status lights OFF).
check 1 A RN pump flow -
less than 16,000 gpm.
The operator observes 1 A OR RN flow (1 RNP-5040) to be
==5500 gpm.
If RN pump suction aligned to SNSWP.....
(Step 7.e) GO TO Step 8.
The operator proceeds to Step 8.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 17 18 19 20
- 21 Page 11 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 8) Check if NV S/I The operator observes the flow path is open as follows:
Green status light LIT for both valves, determines that 1 NI-9A (NC Cold Leg Inj neither valve is OPEN, and From NV) - OPEN proceeds to the Step 8 RNO.
OR 1 NI-10B (NC Cold Leg Inj From NV) - OPEN (Step 8 RNO a-b) Perform The operator observes that the following:
both NV Pump Green status IF 1A AND 1B NV pumps lights are lit, Red status OFF, THEN open 1 NV-241 lights are OFF.
(Seallnj Flow Control)
The operator adjusts the 1 NV-241 controller output to GO TO step 10.
100% (Both Red and Black Needles to 100%).
The operator proceeds to Step 10.
(Step 10) Place "PO pump The operator observes the speed control" in "MAN" and PO Pump Speed Controller set for minimum speed.
in MANUAL (Green and Yellow lights LIT) and observes controller output for minimum speed (0%
output).
(Step 11) Open 1 NV-1047A The operator depresses the (PO PUMP Recirculation) 1 NV-1047A OPEN pushbutton and observes Red status light LIT, Green status light OFF.
(Step 12) Start the PO The operator depresses the Pump.
PO Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 17 18 19 20
- 21 Page 11 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 8) Check if NV SII The operator observes the flow path is open as follows:
Green status light LIT for both valves, determines that 1 NI-9A (NC Cold Leg Inj neither valve is OPEN, and From NV) - OPEN proceeds to the Step 8 RNO.
OR 1 NI-10B (NC Cold Leg Inj From NV) - OPEN (Step 8 RNO a-b) Perform The operator observes that the following:
both NV Pump Green status IF 1A AND 1B NV pumps lights are lit, Red status OFF, THEN open 1 NV-241 lights are OFF.
(Seallnj Flow Control)
The operator adjusts the 1 NV-241 controller output to GO TO step 10.
100% (Both Red and Black Needles to 100%).
The operator proceeds to Step 10.
(Step 10) Place "PD pump The operator observes the speed control" in "MAN" and PD Pump Speed Controller set for minimum speed.
in MANUAL (Green and Yellow lights LIT) and observes controller output for minimum speed (0%
output).
(Step 11) Open 1 NV-1047A The operator depresses the (PD PUMP Recirculation) 1 NV-1047A OPEN pushbutton and observes Red status light LIT, Green status light OFF.
(Step 12) Start the PD The operator depresses the Pump.
PD Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS 22 23 24 25 Page 12 of 15 PERFORMANCE INFORMATION ELEMENTS (Step 13) Ensure 1 NV-1047A (PD Pump Recirculation) closes after 2 minutes.
(Step 14) WHEN 1 NV-1047A (PD Pump Recirculation) is closed, THEN raise "PD PUMP SPEED CNTRl" to establish charging flow.
(Note prior to Step 15)
Cooling water for areas in next step was isolated by Step 6.
(Step 15) Notify station management to monitor temperature in both units 6900v switchgear room, turbine bldg, and service bldg areas.
STANDARD After two minutes, the operator observes that the 1 NV-1 047 Green status light is LIT, Red status light is OFF.
The operator depresses the PD PUMP SPEED CNTRl increase pushbutton (Red),
and observes Charging flow is increasing.
The operator reads Note and proceeds to Step 15.
The operator notifies the CRSRO.
The operator returns to EP/1IAl5000/FR-S. 1, Step 5.b.
- 26 (EP/11A15000/FR-S.1/Step The operator depresses the 5.b/.b1) Align boration 1 NV-265B OPEN flowpath:
pushbutton and observes Red status light LIT, Green Open 1 NV-265B (Boric Acid status light OFF.
To NV Pumps).
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS 22 23 24 25 Page 12 of 15 PERFORMANCE INFORMATION ELEMENTS (Step 13) Ensure 1 NV-1047A (PO Pump Recirculation) closes after 2 minutes.
(Step 14) WHEN 1 NV-1047A (PO Pump Recirculation) is closed, THEN raise "PO PUMP SPEED CNTRL" to establish charging flow.
(Note prior to Step 15)
Cooling water for areas in next step was isolated by Step 6.
(Step 15) Notify station management to monitor temperature in both units 6900v switchgear room, turbine bldg, and service bldg areas.
STANDARD After two minutes, the operator observes that the 1 NV-1 047 Green status light is LIT, Red status light is OFF.
The operator depresses the PO PUMP SPEED CNTRL increase pushbutton (Red),
and observes Charging flow is increasing.
The operator reads Note and proceeds to Step 15.
The operator notifies the CRSRO.
~,.,
y,,,,,,,
).,.'
L;*::'iJ~;;~~:**:
~~t~~:.~~~: ;".
,,~'::- :.'\\
Sta1lion Mahag~m,~gt been. notified.
- li:~;>>*
. '1' The operator returns to EP/1IA/5000/FR-S.1, Step 5.b.
- 26 (EP/1/A/5000/FR-S.1/Step The operator depresses the 5.b/.b1) Align boration 1 NV-265B OPEN flowpath:
pushbutton and observes Red status light LIT, Green Open 1 NV-265B (Boric Acid status light OFF.
To NV Pumps).
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C STEPS
- 27 28 29 30 31 Page 13 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 5.b.2) Start both boric The operator places the A acid transfer pumps.
Boric Acid Transfer Pump control switch to START and observes the Red status light LIT, Green status light OFF.
The operator observes the B Boric Acid Transfer Pump Red status light LIT, Green status light OFF.
(Step 5.b.3) Check The operator observes emergency boration flow -
boration flow on 1 NVP-5440 GREATER THAN 30 GPM to be 60-80 gpm.
(Step 5.c) Check if NV flowpath aligned to NC System The operator observes 1 NV-244A (Charging Line 1 NV-244A Red status light Cont Isol Otsd) - OPEN LIT, Green status light OFF.
1 NV-245B (Charging Line The operator observes Cont Isol Otsd) - OPEN 1 NV-245B Red status light LIT, Green status light OFF.
(Step 5.d) Ensure charging The operator depresses the flow is greater than RAISE (Red) pushbutton on emergency boration flow.
the PD Pump controller to increase charging flow to greater than boration flow.
(Step 5.e) Check Pzr The operator observes that pressure - LESS THAN Pzr Pressure is less than 2335 PSIG 2335 psig on 1NCP-5161 (or equivalent).
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C STEPS
- 27 28 29 30 31 Page 13 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 5.b.2) Start both boric The operator places the A acid transfer pumps.
Boric Acid Transfer Pump control switch to START and observes the Red status light LIT, Green status light OFF.
The operator observes the B Boric Acid Transfer Pump Red status light LIT, Green status light OFF.
(Step 5.b.3) Check The operator observes emergency boration flow -
boration flow on 1 NVP-5440 GREATER THAN 30 GPM to be 60-80 gpm.
(Step 5.c) Check if NV flowpath aligned to NC System The operator observes 1 NV-244A (Charging Line 1 NV-244A Red status light Cont Isol Otsd) - OPEN LIT, Green status light OFF.
1 NV-245B (Charging Line The operator observes Cont Isol Otsd) - OPEN 1 NV-245B Red status light LIT, Green status light OFF.
(Step 5.d) Ensure charging The operator depresses the flow is greater than RAISE (Red) pushbutton on emergency boration flow.
the PD Pump controller to increase charging flow to greater than boration flow.
(Step 5.e) Check Pzr The operator observes that pressure - LESS THAN Pzr Pressure is less than 2335 PSIG 2335 psig on 1NCP-5161 (or equivalent).
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C Page 14 of 15 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM A Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM A NUREG 1021, Revision 9 Appendix C Page 14 of 15 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM A Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM A NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 was at 100% power with "A" NV pump tagged for maintenance.
A lockout occurred on Zone "1 B". Due to a relaying failure, busses 1TB and 1TD failed to swap to their alternate power source. The "1 B" Diesel Generator started and loaded 1 ETB.
The reactor coolant pumps tripped on under frequency.
An automatic reactor trip FAILED to occur. EP/1/A/5000/FR-S.1 (Response To Nuclear Power Generator/ATWS) has been implemented and completed through Step 4.
Letdown has been isolated per AP/1/A/5500/12 Loss of Letdown, Charging or Seal Injection.
The reactor has just been tripped locally.
The CRSRO has directed you to emergency borate the NC System in accordance with Step 5 of EP/1/A/5000/FR-S.1, Response To Nuclear Generator/ATWS.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 was at 100% power with "A" NV pump tagged for maintenance.
A lockout occurred on Zone "1 B". Due to a relaying failure, busses 1TB and 1TD failed to swap to their alternate power source. The "1 B" Diesel Generator started and loaded 1 ETB.
The reactor coolant pumps tripped on under frequency.
An automatic reactor trip FAILED to occur. EP/1/A/5000/FR-S.1 (Response To Nuclear Power Generator/ATWS) has been implemented and completed through Step 4.
Letdown has been isolated per AP/1/A/5500/12 Loss of Letdown, Charging or Seal Injection.
The reactor has just been tripped locally.
The CRSRO has directed you to emergency borate the NC System in accordance with Step 5 of EP/1IA/5000/FR-S.1,
Response To Nuclear Generator/ATWS.
NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 SIM JPM B 2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 SIM JPM B 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 Facility:
McGuire Task No.:
215Z13001 Task
Title:
Align the ND, NI, and NV Systems to Cold Leg Recirculation JPM No.:
2009 Systems - Control Room JPM B (Alternate Path)
KIA
Reference:
006, A4.02, 3.9/3.8 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
Upon receiving the "FWST Level Lo" annunciator, the operator transitions to EP/1/A/5000/ES-1.3 (Transfer to Cold Leg Recirc) per foldout page of E-1or Step 15.b RNO. The "A" train of ND and both trains of NI and NV are then aligned to Cold Leg Recirc. All critical tasks evaluated as satisfactory.
Required Materials:
None General
References:
EP/1/A/5000/E-1, Loss of Reactor or Secondary Coolant EP/1/A/5000/ES-1.3, Transfer to Cold Leg Recirc 2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 Facility:
McGuire Task No.:
215Z13001 Task
Title:
Align the NO, NI, and NV Systems to Cold Leg Recirculation JPM No.:
2009 Systems - Control Room JPM B (Alternate Path)
KIA
Reference:
006, A4.02, 3.9/3.8 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
Upon receiving the "FWST Level Lo" annunciator, the operator transitions to EP 111 A/5000/ES-1.3 (Transfer to Cold Leg Reci rc) per foldout page of E-1or Step 15.b RNO. The "A" train of NO and both trains of NI and NV are then aligned to Cold Leg Recirc. All critical tasks evaluated as satisfactory.
Required Materials:
None General
References:
EP/1/A/5000/E-1, Loss of Reactor or Secondary Coolant EP/1/A/5000/ES-1.3, Transfer to Cold Leg Recirc 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Handouts:
Time Critical Task:
Validation Time:
Job Performance Measure Worksheet Form ES-C-1 EP/1/A/5000/E-1, Loss of Reactor or Secondary Coolant marked up for place-keeping through Step 14.
NO 15 minutes 2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C Handouts:
Time Critical Task:
Validation Time:
Job Performance Measure Worksheet Form ES-C-1 EP/1 I A/5000/E-1, Loss of Reactor or Secondary Coolant marked up for place-keeping through Step 14.
NO 15 minutes 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset Simulator to IC-39 100% MOL
- 2.
Insert Malfunction - NC008B, Cold Leg LOCA Loop B
- 3.
Setup Malfunction - N1002E, NI System Valve 1NI-184B Failure, Value = 0
- 4.
Implement EP/E-O, FRP-P.1, FRP-Z.1, transition to EP/E-1 and perform steps 1 through 14. Allow FWST to drain to 200 inches.
- 5.
Freeze the Simulator
- 1.
Reset to IC-123 (December, 2008)
- 2.
Go to SILENCE on ESF Monitor Light Panel.
- 3.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 4.
Leave Simulator in FREEZE until operator is ready to begin.
Note: Time to Reach 180 Inches in FWST is =::45 sec.
2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset Simulator to IC-39 100% MOL
- 2.
Insert Malfunction - NC008B, Cold Leg LOCA Loop B
- 3.
Setup Malfunction - N1002E, NI System Valve 1 NI-184B Failure, Value = 0
- 4.
Implement EP/E-O, FRP-P.1, FRP-Z.1, transition to EP/E-1 and perform steps 1 through 14. Allow FWST to drain to 200 inches.
- 5.
Freeze the Simulator
- 1.
Reset to IC-123 (December, 2008)
- 2.
Go to SILENCE on ESF Monitor Light Panel.
- 3.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 4.
Leave Simulator in FREEZE until operator is ready to begin.
Note: Time to Reach 180 Inches in FWST is =45 sec.
2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Page S of 14 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1/Al5000/E-1 marked up for place-keeping through step 14.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
NOTE: Operator uses control board indications to check equipment status. Operator transitions to ES-1.3 when "FWST LEVEL La" annunciator is received (expected to come in while performing JPM Steps 1-4. When the alarm comes in, N/A any JPM Steps not performed and proceed to JPM Step 5.
1 2
3 (Step 1S) Check transfer to Cold Leg Recirc criteria:
(Step 1S.a) FWST level -
LESS THAN 180 INCHES
("FWST LEVEL LO" ALARM)
(Step 1S.a RNO) RETURN TO Step 13.
(Step 13) Initiate evaluation of plant status:
(Step 13.a) Check Cold Leg Recirc capability from at least one train as follows:
Train A:
1A NO pump - AVAILABLE 1NI-18SA (1A NO Pump Suction From Cont Sump Isol) - POWER AVAILABLE OR Train B:
1 B NO pump - AVAILABLE 1NI-184B (1B NO Pump Suction From Cont Sump Isol1-POWER AVAILABLE 2009 Systems - Control Room JPM B The operator checks FWST level indications (1 FWP-SOOO, S001 and S002) at approximately 200 inches and proceeds to RNO.
The operator returns to Step 13.
The operator observes 1 A NO Pump Red status light LIT, Green status light OFF.
1NI-18SA Green light lit, Red Light Dark The operator observes 1 B NO Pump Red status light LIT, Green status light OFF.
1NI-18SA Green light lit, Red Light Dark The operator determines that both pumps and valves are available.
NUREG 1021, Revision 9 Appendix C Page 5 of 14 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1/Al5000/E-1 marked up for place-keeping through step 14.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
NOTE: Operator uses control board indications to check equipment status. Operator transitions to ES-1.3 when "FWST LEVEL LO" annunciator is received (expected to come in while performing JPM Steps 1-4. When the alarm comes in, N/A any JPM Steps not performed and proceed to JPM Step 5.
1 2
3 (Step 15) Check transfer to Cold Leg Recirc criteria:
(Step 15.a) FWST level -
LESS THAN 180 INCHES
("FWST LEVEL LO" ALARM)
(Step 15.a RNO) RETURN TO Step 13.
(Step 13) Initiate evaluation of plant status:
(Step 13.a) Check Cold Leg Recirc capability from at least one train as follows:
Train A:
1A NO pump - AVAILABLE 1NI-185A (1A NO Pump Suction From Cont Sump Isol) - POWER AVAILABLE OR Train B:
1 B NO pump - AVAILABLE 1NI-184B (1B NO Pump Suction From Cont Sump Isol) - POWER AVAILABLE 2009 Systems - Control Room JPM B The operator checks FWST level indications (1 FWP-5000, 5001 and 5002) at approximately 200 inches and proceeds to RNO.
The operator returns to Step 13.
The operator observes 1 A NO Pump Red status light LIT, Green status light OFF.
1NI-185A Green light lit, Red Light Dark The operator observes 1 B NO Pump Red status light LIT, Green status light OFF.
1NI-185A Green light lit, Red Light Dark The operator determines that both pumps and valves are available.
NUREG 1021, Revision 9
Appendix C STEPS 4
Page 6 of 14 PERFORMANCE INFORMATION ELEMENTS (Step 13./b.1) Check for potential leak in aux bldg as follows: Check aux bldg radiation:
All area monitor EMF's -
NORMAL EMF-41 (Aux Bldg Ventilation) - NORMAL STANDARD The operator observes EMF's for Trip1ITrip2 lights are NOT LIT.
The operator observes associated EMF Annunciators are DARK.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT NOTE: Based on the setup, the operator should be transitioned to ES-1.3 by this point.
5 6
(ES-1.3/Step 1) Have ST A monitor foldout page (Step 2) Perform this EP without delay.
CSF procedures should not be implemented until directed by this procedure.
Double 3-way communication is not required.
2009 Systems - Control Room JPM B The operator looks for ST A.
The operator reads Step and proceeds to Step 3.
NUREG 1021, Revision 9 Appendix C STEPS 4
Page 6 of 14 PERFORMANCE INFORMATION ELEMENTS (Step 13./b.1) Check for potential leak in aux bldg as follows: Check aux bldg radiation:
All area monitor EMF's -
NORMAL EMF-41 (Aux Bldg Ventilation) - NORMAL STANDARD The operator observes EMF's for Trip1ITrip2 lights are NOT LIT.
The operator observes associated EMF Annunciators are DARK.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT NOTE: Based on the setup, the operator should be transitioned to ES-1.3 by this point.
5 6
(ES-1.3/Step 1) Have ST A monitor foldout page (Step 2) Perform this EP without delay.
CSF procedures should not be implemented until directed by this procedure.
Double 3-way communication is not required.
2009 Systems - Control Room JPM B The operator looks for ST A.
The operator reads Step and proceeds to Step 3.
",qle:
.;~~.
,,\\~,;;
"/' ';"i;"".~~
T~i dir'e~t~~.~~t&~.dor~~"*
withoutd~ijy~ a the....
relax~tion*bf.th
'~.~~:.
pushbuttq,.'
- he~kffONI:l.Y*:'
th~J ff'l~tvalva$; $tt\\~~V
~Q"lq~* and <,:c:)n,timle.o~;C\\*
With'thE! proQedYt.~~; ",.....,'
- ~.
!.~. :>",.'.
- ~
- ~:>:':.
~. :>. :~~/'
...: "." \\~D'.
~i'! ~I
,j:.:);~~~,
~..:. 'i:
- i
- f
()p~ning5eit~et£,1 Nt,
or 1NI-333B'satisfies (Step 7.f) Open the
,~i'ical part6fthis st following:
1 NI-332A (NV & NI Pumps The operator presses the 1 NI-332A OPEN Suction X-Over) pushbutton, observes Red status light LIT.
1 NI-333B (NV & NI Pumps The operator presses the Suction X-Over) 1 NI-333B OPEN pushbutton, observes Red status light LIT.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C STEPS
- 25
- 26
- 27 Page 11 of 14 PERFORMANCE INFORMATION ELEMENTS (Step 7.g) Align ND discharge to suction of NI and NV pumps as follows:
Open 1 ND-S8A (Train A ND To NV & NI Pumps).
Open 1 NI-136B (B NI Pump Suction From ND).
(Step 7.h) Isolate FWST from NV and NI pumps:
(Step 7.h.1) Enable power disconnect and close 1 NI-100B (FWST To NI Pumps).
(Step 7.h.2) Close the following:
STANDARD The operator presses the 1 ND-S8A OPEN pushbutton, observes Red status light LIT.
The operator presses the 1 NI-136B OPEN pushbutton, observes Green status light LIT.
The operator rotates the 1 NI-1 OOB power disconnect switch clockwise to ENABLE and presses CLOSE pushbutton.
The operator observes Green status light is LIT.
1 NV-221A (NV Pumps Suct The operator presses the From FWST) 1 NV-221 A CLOSE pushbutton, observes Green status light LIT.
1 NV-222B (NV Pumps Suct From FWST)
The operator presses the 1 NV-222B CLOSE pushbutton, observes Green status light LIT.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C STEPS
- 25
- 26
- 27 Page 11 of 14 PERFORMANCE INFORMATION ELEMENTS (Step 7.g) Align ND discharge to suction of NI and NV pumps as follows:
Open 1 ND-S8A (Train A ND To NV & NI Pumps).
Open 1 NI-136B (B NI Pump Suction From ND).
(Step 7.h) Isolate FWST from NV and NI pumps:
(Step 7.h.1) Enable power disconnect and close 1 NI-100B (FWST To NI Pumps).
(Step 7.h.2) Close the following:
STANDARD The operator presses the 1 ND-S8A OPEN pushbutton, observes Red status light LIT.
The operator presses the 1 NI-136B OPEN pushbutton, observes Green status light LIT.
The operator rotates the 1 NI-1 OOB power disconnect switch clockwise to ENABLE and presses CLOSE pushbutton.
The operator observes Green status light is LIT.
1 NV-221 A (NV Pumps Suct The operator presses the From FWST) 1 NV-221 A CLOSE pushbutton, observes Green status light LIT.
1 NV-222B (NV Pumps Suct From FWST)
The operator presses the 1 NV-222B CLOSE pushbutton, observes Green status light LIT.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Page 12 of 14 PERFORMANCE INFORMATION STEPS ELEMENTS 28 (Step 8) Check if NS should be aligned for recirc as follows...
STANDARD Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
2009 Systems - Control Room JPM B S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C Page 12 of 14 PERFORMANCE INFORMATION STEPS ELEMENTS 28 (Step 8) Check if NS should be aligned for recirc as follows...
STANDARD Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
2009 Systems - Control Room JPM B S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9
Appendix C Page 13 of 14 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM B Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM B NUREG 1021, Revision 9 Appendix C Page 13 of 14 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM B Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM B NUREG 1021, Revision 9
Appendix C Initial Conditions:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET You are the Unit 1 Balance of Plant (BOP) Operator.
Unit 1 has experienced a large break LOCA inside containment.
EP/1/A15000/E-0 has been completed.
EP/1/A15000/FR-P.1 (Response to Imminent Pressurized Thermal Shock) and EP/1/A15000/FR-Z.1 (Response to High Containment Pressure) have Deen implemented to address existing CSF orange paths.
EP/1/A15000/E-1 (Loss of Reactor or Secondary Coolant) is currently in effect and has been completed through Step # 14.
The CRSRO has directed you to continue in EP/1/A15000/E-1 (Loss *of Reactor or Secondary Coolant), beginning with Step #15, and perform ES-1.3, Transfer to Cold Leg Recirc when required.
NUREG 1021, Revision 9 Appendix C Initial Conditions:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET You are the Unit 1 Balance of Plant (BOP) Operator.
Unit 1 has experienced a large break LOCA inside containment.
EP/1/A/5000/E-0 has been completed.
EP/1/A/5000/FR-P.1 (Response to Imminent Pressurized Thermal Shock) and EP/1/A/5000/FR-Z.1 (Response to High Containment Pressure) have been implemented to address existing CSF orange paths.
EP/1/A/5000/E-1 (Loss of Reactor or Secondary Coolant) is currently in effect and has been completed through Step # 14.
The CRSRO has directed you to continue in EP/1/A/5000/E-1 (Loss of Reactor or Secondary Coolant), beginning with Step #15, and perform ES-1.3, Transfer to Cold Leg Recirc when required.
NUREG 1021, Revision 9
Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM C 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM C 2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Place L TOP in Service JPM No.:
2009 Systems - Control Room JPM C KIA
Reference:
010, A4.03, 4.0/3.8 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
Manually decrease NC System Pressure to 320-330 psig and place L TOP in service. All critical tasks evaluated as satisfactory.
Required Materials:
None General
References:
OP/1/A/6100/SD-4, Cooldown to 240 Degrees F OP/11 A/61 00/SO-1 0, Controlling Procedure for L TOP Operation OP/1/A/61001022, Unit 1 Data Book 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Place L TOP in Service JPM No.:
2009 Systems - Control Room JPM C KIA
Reference:
010, A4.03, 4.0/3.8 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
Manually decrease NC System Pressure to 320-330 psig and place L TOP in service. All critical tasks evaluated as satisfactory.
Required Materials:
None General
References:
OP/1/A/6100/SD-4, Cooldown to 240 Degrees F OP/1/A/6100/S0-10, Controlling Procedure for LTOP Operation OP/1/A/6100/022, Unit 1 Data Book 2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Handouts:
Time Critical Task:
Validation Time:
Page 3 of 11 PERFORMANCE INFORMATION Form ES-C-1 OP/1/A/6100/S0-10, Controlling Procedure for LTOP Operation,.1, Placing LTOP System in Service per OP/1/A/6100/SD-4 (Cooldown to 240 degrees F) marked up for place-keeping through step 3.13.1.
NO 15 minutes 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Handouts:
Time Critical Task:
Validation Time:
Page 3 of 11 PERFORMANCE INFORMATION Form ES-C-1 OP/1/A/6100/S0-10, Controlling Procedure for LTOP Operation,.1, Placing LTOP System in Service per OP/1/A/6100/SD-4 (Cooldown to 240 degrees F) marked up for place-keeping through step 3.13.1.
NO 15 minutes 2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Page 4 of 11 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES Form ES-C-1
- 1.
Reset simulator to IC-41, Mode 4, 325 PSIG, 299 Deg Trn B ND is service.
- 2.
Place in RUN
- 3.
Secure 1 C and 1 D NCP's
- 4.
Place L TOP PORV switches is OFF
- 5.
Insert LOA NC043 and LOA NC044
- 6.
Adjust NC System Pressure to 340 psig.
- 7.
Adjust NC System Temperature to 306°F.
- 8.
Ensure. that Simulator reflects that Enclosure 4.1 of OP/1/A/6100/SO-10 is completed through Step 3.13.1
- 9.
Freeze the Simulator
- 1.
Reset to IC-124 (December, 2008)
- 2.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 3.
Ensure that the "AFD" Computer screen displays the "C/D Tab" panel and that the "OATC" screen displays the "NCL TOP" panel.
- 4.
Leave Simulator in FREEZE until operator is ready to begin.
NOTE:
During the performance of this JPM, the simulator operator will need to control CF flow to the SGs.
2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Page 4 of 11 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES Form ES-C-1
- 1.
Reset simulator to IC-41, Mode 4, 325 PSIG, 299 Deg Trn B NO is service.
- 2.
Place in RUN
- 3.
Secure 1C and 10 NCP's
- 4.
Place L TOP PORV switches is OFF
- 5.
Insert LOA NC043 and LOA NC044
- 6.
Adjust NC System Pressure to 340 psig.
- 7.
Adjust NC System Temperature to 306°F.
- 8.
Ensure that Simulator reflects that Enclosure 4.1 of OP/1/A/6100/S0-10 is completed through Step 3.13.1
- 9.
Freeze the Simulator
- 1.
Reset to IC-124 (December, 2008)
- 2.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 3.
Ensure that the "AFD" Computer screen displays the "C/O Tab" panel and that the
- 4.
NOTE:
"OATC" screen displays the "NCL TOP" panel.
Leave Simulator in FREEZE until operator is ready to begin.
During the performance of this JPM, the simulator operator will need to control CF flow to the SGs.
2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Page 5 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout OP/1/Al6100/S0-10, with Enclosure 4.1 marked up for place-keeping through step 3.13.1.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Step 3.13.2) Ensure in The operator calls up both service:
pOints on OAC.
M1A1359 (NC NR Pressure for 1 NC-32B actuation).
M1A1365 (NC NR Pressure for 1 NC-34A actuation).
2 (Step 3.13.3) Monitor:
The operator monitors both M1A1359 (NC NR Pressure pOints and observes NC NR for 1 NC-32B actuation).
Pressure to be 340 psig.
M1A1365 (NC NR Pressure for 1 NC-34A actuation).
- 3 (Step 3.13.4) Decrease NC The operator adjusts Spray System Pressure to Valve(s) in the OPEN 320 - 330 PSIG direction using the Red Pushbutton, and lowers NC System Pressure to < 330 psig.
When NC System Pressure
< 330 psig, the operator adjusts Spray Valve(s) in the CLOSED direction in order to maintain pressure 320-330 psig.
2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Page 5 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout OP/1/Al61OO/SO-10, with Enclosure 4.1 marked up for place-keeping through step 3.13.1.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Step 3.13.2) Ensure in The operator calls up both service:
points on OAC.
M1A1359 (NC NR Pressure for 1 NC-32B actuation).
M1A1365 (NC NR Pressure for 1 NC-34A actuation).
2 (Step 3.13.3) Monitor:
The operator monitors both M1A1359 (NC NR Pressure points and observes NC NR for 1 NC-32B actuation).
Pressure to be 340 psig.
M1A1365 (NC NR Pressure for 1 NC-34A actuation).
- 3 (Step 3.13.4) Decrease NC The operator adjusts Spray System Pressure to Valve(s} in the OPEN 320 - 330 PSIG direction using the Red Pushbutton, and lowers NC System Pressure to < 330 psig.
When NC System Pressure
< 330 psig, the operator adjusts Spray Valve(s} in the CLOSED direction in order to maintain pressure 320-330 psig.
2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C STEPS 4
5 6
7 Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 3.13.5) Ensure the following for A Cold Leg Accumulator:
Pressure greater than 200 The operator observes 1 NIP-5050 and 1 NIP-5040, psig.
and determines A CLA pressure to be==625 psig.
Level less than 38.7%
The operator observes (7342 gallons maximum).
1NIP-5051 and 1NIP-5041, and determines A CLA Level to be==25%.
(Step 3.13.6) Ensure the following for B Cold Leg Accumulator:
Pressure greater than 200 The operator observes 1 NIP-5070 and 1 NIP-5060 psig.
and determines B CLA pressure to be==620 psig.
Level less than 38.7%
The operator observes (7342 gallons maximum).
1 NIP-5071 and 1 NIP-5061 and determines B CLA Level to be==24%.
(Step 3.13.7) Ensure open:
The operator observes Red 1NC-31B (pzr PORV Isol).
status light LIT, Green status light OFF for 1 NC-33B.
1 NC-33A (pzr PORV Isol).
The operator observes Red status light LIT, Green status light OFF for 1 NC-33A.
(Note prior to Step 3.13.8)
The operator reads the For NC Loop in which an Note, and proceeds to Step NC Pump is operating, NR 3.13.8.
pressure may indicate up to 20 psig higher than NR pressure for NC Loop in which an NC Pump is NOT operating.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C STEPS 4
S 6
7 Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 3.13.S) Ensure the following for A Cold Leg Accumulator:
Pressure greater than 200 The operator observes 1 NIP-SOSO and 1 NIP-S040, psig.
and determines A CLA pressure to be==62S psig.
Level less than 38.7%
The operator observes (7342 gallons maximum).
1 NIP-SOS1 and 1 NIP-S041, and determines A CLA Level to be==2S%.
(Step 3.13.6) Ensure the following for 8 Cold Leg Accumulator:
Pressure greater than 200 The operator observes 1 NIP-S070 and 1 NIP-S060 psig.
and determines 8 CLA pressure to be==620 psig.
Level less than 38.7%
The operator observes (7342 gallons maximum).
1 NIP-S071 and 1 NIP-S061 and determines 8 CLA Level to be==24%.
(Step 3.13.7) Ensure open:
The operator observes Red 1 NC-31 8 (pzr PORV Isol).
status light LIT, Green status light OFF for 1 NC-338.
1 NC-33A (pzr PORV Isol).
The operator observes Red status light LIT, Green status light OFF for 1 NC-33A.
(Note prior to Step 3.13.8)
The operator reads the For NC Loop in which an Note, and proceeds to Step NC Pump is operating, NR 3.13.8.
pressure may indicate up to 20 psig higher than NR pressure for NC Loop in which an NC Pump is NOT operating.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Page 7 of 11 Form ES-C-1 PERFORMANCE INFORMATION STEPS
- 8 9
10 11 ELEMENTS 3.1 M1A1359 indicates 320-330 psig, perform the following:
(Step 3.13.8.1) Select "LOW PRESS" on "PORV Overpress Protection Select 1 NC-32B."
(Step 3.13.8.2) lit 1 AD-6, F10 (PORV NC-32B Emerg CLA N2 Enabled) re open 1 NI-431 B (Emerg N2 from CLA to 1 NC-32B &
36B).
3.13.8.
Place I Sticker on control switch for 1 NI-431 B stating: "Do NOT operate, N2 aligned to 1 NC-32B for L TOP."
2009 Systems - Control Room JPM C STANDARD The operator observes M1A1359 is between 320-330 psig, and selects LOW PRESS on PORV Overpress Protection Select 1 NC-32B.
The operator observes that 1AD-6, F-10 is LIT.
The operator observes that Red status light is LIT, Green status light OFF for 1 NI-431 B.
The operator acknowledges and proceeds to Step 3.13.8.5.
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C Page 7 of 11 Form ES-C-1 PERFORMANCE INFORMATION STEPS
- 8 9
10 11 ELEMENTS (Step 3.13.8) When M1A1359 indicates 320-330 psig, perform the following:
(Step 3.13.8.1) Select "LOW PRESS" on "PORV Overpress Protection Select 1 NC-32B."
(Step 3.13.8.2) Check lit 1 AD-6, F10 (PORV NC-32B Emerg CLA N2 Enabled) 3.13.8.3) Ensure open 1 NI-431 B (Emerg N2 from CLA to 1 NC-32B &
36B).
(Step 3.13.8.4) Place Info Sticker on control switch for 1 NI-431 B stating: "Do NOT operate, N2 aligned to 1 NC-32B for LTOP."
2009 Systems - Control Room JPM C STANDARD The operator observes M1A1359 is between 320-330 psig, and selects LOW PRESS on PORV Overpress Protection Select 1 NC-32B.
The operator observes that 1AD-6, F-10 is LIT.
The operator observes that Red status light is LIT, Green status light OFF for 1 NI-431 B.
The operator acknowledges and proceeds to Step 3.13.8.5.
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9
Appendix C Page 8 of 11 Form ES-C-1 PERFORMANCE INFORMATION STEPS 12 13*
14 15 16 ELEMENTS (Step 3.13.8.5) Ensure 1 NC-32B (pzr PORV) in "Auto."
(Step 3.13.9) When M1A1365 indicates 320-330 psig, perform the following:
(Step 3.13.9.1) Select "LOW PRESS" on "PORV Overpress Protection Select 1 NC-34A."
(Step 3.13.9.2) heck lit 1 AD-6, F9 (PORV NC-34A Emerg CLA N2 Enabled)
(Step 3.13.9.3) Ensure open 1 NI-430A (Emerg N2 from CLA to 1 NC-34A).
(Step 3.13.9.4) Place Info Sticker on control switch for 1 NI-430A stating: "Do NOT operate, N2 aligned to 1 NC-34A for L TOP."
2009 Systems - Control Room JPM C STANDARD The operator observes that Control Switch for 1 NC-32B is in AUTO.
The operator observes M 1 A 1365 is between 320-330 pSig, and selects LOW PRESS on PORV Overpress Protection Select 1 NC-34A.
The operator observes that 1AD-6, F-9 is LIT.
The operator observes that Red status light is LIT, Green status light OFF for 1NI-430A.
The operator acknowledges and proceeds to Step 3.13.9.5.
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C Page 8 of 11 Form ES-C-1 PERFORMANCE INFORMATION STEPS 12 13*
14 15 16 ELEMENTS (Step 3.13.8.5) Ensure 1 NC-32B (pzr PORV) in "Auto."
(Step 3.13.9) When M1A 1365 indicates 320-330 psig, perform the following:
(Step 3.13.9.1) Select "LOW PRESS" on "PORV Overpress Protection Select 1 NC-34A."
3.13.
1 AD-6, F9 (PORV NC-34A Emerg CLA N2 Enabled)
(Step 3.13.9.3) Ensure open 1 NI-430A (Emerg N2 from CLA to 1 NC-34A).
(Step 3.13.9.4) Place Info Sticker on control switch for 1 NI-430A stating: "Do NOT operate, N2 aligned to 1 NC-34A for LTOP."
2009 Systems - Control Room JPM C STANDARD The operator observes that Control Switch for 1 NC-32B is in AUTO.
The operator observes M 1 A 1365 is between 320-330 psig, and selects LOW PRESS on PORV Overpress Protection Select 1 NC-34A.
The operator observes that 1 AD-6, F-9 is LIT.
The operator observes that Red status light is LIT, Green status light OFF for 1NI-430A.
The operator acknowledges and proceeds to Step 3.13.9.5.
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9
Appendix C STEPS 17 Page 9 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 3.13.9.5) Ensure The operator observes that 1 NC-34A (pzr PORV) in Control Switch for 1 NC-34A "Auto."
is in AUTO.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C STEPS 17 Page 9 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 3.13.9.5) Ensure The operator observes that 1 NC-34A (pzr PORV) in Control Switch for 1 NC-34A "Auto."
is in AUTO.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM C NUREG 1021, Revision 9
Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM C Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM C NUREG 1021, Revision 9 Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM C Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room J PM C NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A Unit 1 NC cooldown and depressurization is in progress in accordance with OP/1/A/6100/SD-4, "Cooldown to 240 Degrees F."
The 1 A and 1 B NCPs are operating.
NC System pressure is 340 psig and NC System temperature is 306-312°F.
NC Pressure control via normal spray and PZR heaters.
- .1 of OP/1/A/6100/SO-1 0, "Controlling Procedure for L TOP Operation," has been completed through Step 3.13.1.
The CRSRO has directed you to place the L TOP System in operation in accordance with Step 3.13.2 of Enclosure 4.1 of OP/1/A/6100/SO-1 0, "Controlling Procedure for LTOP Operation,"
and monitor for proper operation.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A Unit 1 NC cooldown and depressurization is in progress in accordance with OP/1/A/6100/SD-4, "Cooldown to 240 Degrees F."
The 1 A and 1 8 NCPs are operating.
NC System pressure is 340 psig and NC System temperature is 306-312°F.
NC Pressure control via normal spray and PZR heaters.
- .1 of OP/1/A/6100/S0-10, "Controlling Procedure for L TOP Operation," has been completed through Step 3.13.1.
The CRSRO has directed you to place the L TOP System in operation in accordance with Step 3.13.2 of Enclosure 4.1 of OP/1/A/6100/S0-10, "Controlling Procedure for LTOP Operation,"
and monitor for proper operation.
NUREG 1021, Revision 9
Appendix C Page 1 of 13 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM D 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C Page 1 of 13 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM D 2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 13 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Establish Feedwater Flow to the S/G's Following a Reactor Trip JPM No.:
2009 Systems - Control Room JPM 0 KIA
Reference:
059, A4.11, 3.1/3.3 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
1 A CF Pump is in service and capable of providing feedwater flow to all four S/G's.
Required Materials:
None General
References:
EP/1/A/5000/ES-0.1, Reactor Trip Response Handouts:
EP/1 1 A/5000/ES-0.1, Reactor Trip Response, Enclosure 4, Re-establishing CF Flow.
EP/1/A/5000/ES-0.1, Reactor Trip Response, Enclosure 4, Re-establishing CF Flow.
2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 13 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Establish Feedwater Flow to the S/G's Following a Reactor Trip JPM No.:
2009 Systems - Control Room JPM D KIA
Reference:
059, A4.11, 3.1/3.3 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
1 A CF Pump is in service and capable of providing feedwater flow to all four S/G's.
Required Materials:
None General
References:
EP/1/A/5000/ES-0.1, Reactor Trip Response EP/1/A/5000/ES-0.1, Reactor Trip Response, Enclosure 4, Re-establishing CF Flow.
Handouts:
EP/1/A/5000/ES-0.1, Reactor Trip Response, Enclosure 4, Re-establishing CF Flow.
2009 Systems - Control Room JPM D NUREG 1021, Revision 9
Appendix C Time Critical Task:
Validation Time:
NO 20 minutes Page 3 of 13 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM D Form ES-C-1 NUREG 1021, Revision 9 Appendix C Time Critical Task:
Validation Time:
NO 20 minutes Page 3 of 13 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM D Form ES-C-1 NUREG 1021, Revision 9
Appendix C Page 4 of 13 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC-12, 15%, BOL
- 2.
Insert MAL Insert MAL Insert MAL Insert MAL CA004A Failure of CA Pump A to Start CA004B Failure of CA Pump B to Start CA003A CA Turbine Fails to Start CA003B CA Turbine Fails to Start
- 3.
Manually trip the Reactor.
BOTH BOTH Form ES-C-1
- 4.
Allow simulator to run until negative power mismatch and negative temp. mismatch clear.
- 5.
Place TD CA Pump start switch to "START'
- 6.
Freeze the simulator.
Simulator runner should monitor balance of plant. Adjust charging and letdown as necessary to minimize alarms.
- 1.
Reset Simulator to Temporary Snap IC-125 (December, 2008).
- 2.
Momentarily place Simulator in Run to acknowledge alarms.
NOTE: 1 NV-238 was placed in manual during setup and will need to be adjusted and returned to Auto within approx 10 minutes of start of JPM.
2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C Page 4 of 13 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC-12, 15%, BOL
- 2.
Insert MAL Insert MAL Insert MAL Insert MAL CA004A Failure of CA Pump A to Start CA004B Failure of CA Pump B to Start CA003A CA Turbine Fails to Start CA003B CA Turbine Fails to Start
- 3.
Manually trip the Reactor.
BOTH BOTH Form ES-C-1
- 4.
Allow simulator to run until negative power mismatch and negative temp. mismatch clear.
- 5.
Place TO CA Pump start switch to "START"
- 6.
Freeze the simulator.
Simulator runner should monitor balance of plant. Adjust charging and letdown as necessary to minimize alarms.
- 1.
Reset Simulator to Temporary Snap IC-125 (December, 2008).
- 2.
Momentarily place Simulator in Run to acknowledge alarms.
NOTE: 1 NV-238 was placed in manual during setup and will need to be adjusted and returned to Auto within approx 10 minutes of start of JPM.
2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9
Appendix C Page 5 of 13 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form 'ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1/A15000/ES-O.1, Reactor Trip Response, Enclosure 4, Reestablishing CF Flow.
START TIME:
STEPS
- 1 ELEMENTS (Step 1) Ensure the following in manual and close manual loaders for all:
SIG CF control valves SIG CF control bypass..
valves 2009 Systems - Control Room JPM D STANDARD The operator places the SIG CF control valve controllers (4) in MANUAL by depressing the Amber pushbutton.
On each controller the operator depresses the CLOSE pushbutton (Green) and observes that the controller outputs move to O.
The operator observes the Amber light LIT for each of the SIG CF control bypass valve controllers (4).
On each controller the operator observes the Green light LIT and controller outputs at O.
SIU COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C Page 5 of 13 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form "ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1/Al5000/ES-O.1, Reactor Trip Response, Enclosure 4, Reestablishing CF Flow.
START TIME:
STEPS
- 1 ELEMENTS (Step 1) Ensure the following in manual and close manual loaders for all:
S/G CF control valves S/G CF control bypass valves 2009 Systems - Control Room JPM D STANDARD The operator places the S/G CF control valve controllers (4) in MANUAL by depressing the Amber pushbutton.
On each controller the operator depresses the CLOSE pushbutton (Green) and observes that the controller outputs move to O.
The operator observes the Amber light LIT for each of the S/G CF control bypass valve controllers (4).
On each controller the operator observes the Green light LIT and controller outputs at O.
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9
Appendix C STEPS
- 2 Page 6 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2) Close the following CF Control isolation valves:
1CF-31 (A SIG CF Cntrl The operator depresses the Inlet Isol) 1 CF-31 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1CF-33 (A SIG CF Cntrl The operator depresses the Outlet Isol) 1 CF-33 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-22 (8 SIG CF Cntrl The operator depresses the 1 CF-22 CLOSE pushbutton Inlet Isol) and observes Green status light LIT, Red status light OFF.
1 CF-24 (8 SIG CF Cntrl The operator depresses the Outlet Isol) 1 CF-24 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-19 (C SIG CF Cntrl The operator depresses the Inlet Isol) 1 CF-19 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-21 (C SIG CF Cntrl The operator depresses the Outlet Isol) 1CF-21 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C STEPS
- 2 Page 6 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2) Close the following CF Control isolation valves:
1CF-31 (A S/G CF Cntrl The operator depresses the Inlet Isol) 1CF-31 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-33 (A S/G CF Cntrl The operator depresses the Outlet Isol) 1 CF-33 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-22 (8 S/G CF Cntrl The operator depresses the 1 CF-22 CLOSE pushbutton Inlet Isol) and observes Green status light LIT, Red status light OFF.
1 CF-24 (8 S/G CF Cntrl The operator depresses the Outlet Isol) 1 CF-24 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-19 (C S/G CF Cntrl The operator depresses the Inlet Isol) 1 CF-19 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
1 CF-21 (C S/G CF Cntrl The operator depresses the Outlet Isol) 1 CF-21 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9
Appendix C STEPS 2
(Cont'd) 3 4
Page 7 of 13 PERFORMANCE INFORMATION ELEMENTS 1 CF-16 (D S/G CF Cntrl Inlet Isol) 1 CF-18 (D S/G CF Cntrl Outlet Isol)
STANDARD The operator depresses the 1 CF-16 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 CF-18 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
(Step 3) Check the following The operator observes that alarms - DARK:
both MCB Annunciator "INNER DOGHOUSE LEVEL HI" (1AD-5, G-6)
"OUTER DOGHOUSE LEVEL HI" (1AD-5, H-6)
(Step 4) Check all S/G N/R levels - HAVE REMAINED LESS THAN 83% (P-14 setpoint).
windows are DARK.
The operator observes all four SG NR levels and determines that all SG levels are less than 83%.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C STEPS 2
(Cont'd) 3 4
Page 7 of 13 PERFORMANCE INFORMATION ELEMENTS 1 CF-16 (D S/G CF Cntrl Inlet Isol) 1 CF-18 (D S/G CF Cntrl Outlet Isol)
STANDARD The operator depresses the 1 CF-16 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
The operator depresses the 1 CF-18 CLOSE pushbutton and observes Green status light LIT, Red status light OFF.
Note:~){;,ii~(~\\:;
};~
Clos:,~g eith~r the Inlet OR,~h,Outlet for each
~
.. S/G,CF.. Cntrl valve....
+fsa.tiEr' ""i{Hecritlcal e:~~~:~;i;.>.Pf this step. \\~:j;;
(Step 3) Check the following The operator observes that alarms - DARK:
both MCB Annunciator "INNER DOGHOUSE LEVEL HI" (1 AD-5, G-6)
"OUTER DOGHOUSE LEVEL HI" (1AD-5, H-6)
(Step 4) Check all S/G N/R levels - HAVE REMAINED LESS THAN 83% (P-14 setpoint).
windows are DARK.
The operator observes all four SG NR levels and determines that all SG levels are less than 83%.
Cue: It asked, S/G level,s have remai'ned <83%.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9
Appendix C STEPS 5
- 6 7
8 Page 8 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Note prior to Step 5) The The operator reads the following step must be Note and proceeds to Step completed even if a
- 5.
Feedwater Isolation signal has not occurred.
(Step 5) Depress and The operator depresses the release the Feedwater Train A FWI Reset Isolation reset pushbuttons.
pushbutton, and observes that the Reset light is LIT.
The operator depresses the Train B FWI Reset pushbutton, and observes that the Reset light is LIT.
(Step 6) Ensure the following are open on SIGs to be fed:
The operator observes the 1 CF-35AB (A SIG CF Cont 1 CF-35AB Red status light Outside Isol)
LIT, Green status light OFF.
1 CF-30AB (B SIG CF Cont The operator observes the Outside Isol) 1 CF-30AB Red status light LIT, Green status light OFF.
1 CF-28AB (C SIG CF Cont The operator observes the Outside Isol) 1 CF-28AB Red status light LIT, Green status light OFF.
1 CF-26AB (0 SIG CF Cont The operator observes the Outside Isol) 1 CF-26AB Red status light LIT, Green status light OFF.
(Step 7) Check both CF The operator observes that pumps - RESET the Reset light on "A" CF Pump is LIT, and the Trip light on "B" CF pump is LIT and proceeds to Step 7 RNO.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9 Appendix C STEPS 5
- 6 7
8 Page 8 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Note prior to Step 5) The The operator reads the following step must be Note and proceeds to Step completed even if a
- 5.
Feedwater Isolation signal has not occurred.
(Step 5) Depress and The operator depresses the release the Feedwater Train A FWI Reset Isolation reset pushbuttons.
pushbutton, and observes that the Reset light is LIT.
The operator depresses the Train B FWI Reset pushbutton, and observes that the Reset light is LIT.
(Step 6) Ensure the following are open on S/Gs to be fed:
The operator observes the 1 CF-35AB (A S/G CF Cont 1 CF-35AB Red status light Outside Isol)
LIT, Green status light OFF.
1 CF-30AB (B S/G CF Cont The operator observes the Outside Isol) 1 CF-30AB Red status light LIT, Green status light OFF.
1 CF-28AB (C S/G CF Cont The operator observes the Outside Isol) 1 CF-28AB Red status light LIT, Green status light OFF.
1 CF-26AB (0 S/G CF Cont The operator observes the Outside Isol) 1 CF-26AB Red status light LIT, Green status light OFF.
(Step 7) Check both CF The operator observes that pumps - RESET the Reset light on "A" CF Pump is LIT, and the Trip light on "B" CF pump is LIT and proceeds to Step 7 RNO.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9
Appendix C STEPS 9
10 11 12 13 14 Page 9 of 13 PERFORMANCE INFORMATION ELEMENTS (Step 7 RNO a) Perform the following: IF only one CF pump is tripped, THEN GO TO Step 10.
(Steps 10/1 O.a) Perform the following:
Check "RESET" light on "1 A OR 1B CF PUMP RECIRC VALVE CLOSURE CIRCUIT" - DARK (Step 10.a RNO) GO TO Step 11.
(Step 11) Ensure AS is supplied by either Unit 2 or the Aux Electric Boiler PER Step 24 in body of procedure.
(Step 12) Check 1 HM-95 (U 1 Aux Steam Supply to CF Pumps turbine Isol) -
OPEN (Step 13) Check CF flow -
HAS BEEN LOST FOR OVER ONE HOUR.
STANDARD The operator determines only "B" CF pump is tripped and proceeds to step 10.
The operator determines RESET light is LIT and proceeds to the Step 10.a RNO.
The operator proceeds to Step 11.
After the cue, the operator proceeds to Step 12.
The operator observes the 1 HM-95 Red status light LIT, Green status light OFF.
After the cue, the operator proceeds to Step 13 RNO.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C STEPS 9
10 11 12 13 14 Page 9 of 13 PERFORMANCE INFORMATION ELEMENTS (Step 7 RNO a) Perform the following: IF only one CF pump is tripped, THEN GO TO Step 10.
(Steps 10/1 O.a) Perform the following:
Check "RESET" light on "1 A OR 1 B CF PUMP RECIRC VALVE CLOSURE CIRCUIT" - DARK (Step 10.a RNO) GO TO Step 11.
(Step 11) Ensure AS is supplied by either Unit 2 or the Aux Electric Boiler PER Step 24 in body of procedure.
(Step 12) Check 1 HM-95 (U1 Aux Steam Supply to CF Pumps turbine Isol) -
OPEN (Step 13) Check CF flow -
HAS BEEN LOST FOR OVER ONE HOUR.
STANDARD The operator determines only "B" CF pump is tripped and proceeds to step 10.
The operator determines RESET light is LIT and proceeds to the Step 10.a RNO.
The operator proceeds to Step 11.
After the cue, the operator proceeds to Step 12.
The operator observes the 1 HM-95 Red status light LIT, Green status light OFF.
After the cue, the operator proceeds to Step 13 RNO.
Cue:' "... ******;,f CF fl.9W was lost.20 ndnutes ago~;/!:
fe' S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9
Appendix C STEPS ELEMENTS Page 10 of 13 PERFORMANCE INFORMATION STANDARD 15 (Step 13 RNO) GO TO Step The operator proceeds to
- 16
- 15.
Step 15.
(Step 15) On CF pump to be placed in service, raise speed demand "DEM" to establish "CF HEADER PRESSURE" 50-100 psig above S/G pressure.
The operator observes CF Header Pressure (1 CFP-5140) to be =800 psig, and Steam Header Pressure (1 SMP-5200) to be =1100 psig, and determines the current differential pressure to be =300 psig.
The operator selects "1 A" CF pump and depresses the "INC" and/or "DEC" push buttons as needed to establish CF header pressure 75 psig greater than S/G pressure.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C STEPS 15
- 16 Page 10 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 13 RNO) GO TO Step The operator proceeds to
- 15.
Step 15.
(Step 15) On CF pump to The operator observes CF be placed in service, raise Header Pressure (1 CFP-speed demand "OEM" to 5140) to be ::::::800 psig, and establish "CF HEADER Steam Header Pressure PRESSURE" 50-100 psig (1 SMP-5200) to be ::::::1100 above S/G pressure.
psig, and determines the current differential pressure to be ::::::300 pSig.
Not(t:,
Th~~operator m#~':4lSe,the OAe,(Unit 1 Ovehi:lew>"..
Screen orequival~httt6i mQnitorthe AP.
The operator selects "1 A" CF pump and depresses the "INC" and/or "DEC" pushbuttons as needed to establish CF header pressure 75 psig greater than S/G pressure.
Note,:,';'
\\i,.'
~. :~>.:.. ;.;
The.Operat()~can exceed..,
100:'psid d,utihg'attempts to obtain)iO~'1 00 psid.
Tij~ sta,l;!dard iS~Q.b!
betvl~,n 50 - 100 pSld.'....,
when'leaving this step~/ ;:.:.
.. :,....**. j>J,;;:.,:.. :
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9
Appendix C STEPS
- 17 18 Page 11 of 13 PERFORMANCE INFORMATION ELEMENTS (Step 16) Establish desired feed flow to S/Gs by performing the following:
Slowly throttle open S/G CF control bypass valves Raise CF pump speed demand "DEM" to raise discharge pressure as required.
(Step 17) WHEN the following conditions are established, THEN S/G CF control bypass valves may be placed in auto as desired:
DIP between "CF HEADER PRESSURE" and S/G pressure between 50 and 100 pSig.
S/G levels at 39%.
STANDARD The operator depresses the OPEN pushbutton (Red) and observes each S/G CF control bypass valve controller output rising.
The operator depresses the DEM pushbutton on the 1 A CF pump speed controller until discharge pressure is adequate to provide flow.
The operator continues to feed the S/Gs.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C STEPS
- 17 18 Page 11 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 16) Establish desired The operator depresses the feed flow to S/Gs by OPEN pushbutton (Red) performing the following:
and observes each S/G CF control bypass valve Slowly throttle open S/G CF controller output rising.
control bypass valves Raise CF pump speed The operator depresses the demand "OEM" to raise OEM pushbutton on the 1 A discharge pressure as CF pump speed controller required.
until discharge pressure is adequate to provide flow.
(Step 17) WHEN the The operator continues to following conditions are established, THEN S/G CF feed the S/Gs.
control bypass valves may be placed in auto as Cue:.
desired:
Another operator will DIP between "CF HEADER monilor S/G levels and.
PRESSURE" and S/G pressure between 50 and complete this enclosure.
100 psig.
S/G levels at 39%.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT i,
2009 Systems - Control Room JPM 0 NUREG 1021, Revision 9
Appendix C Page 12 of 13 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM D Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM D NUREG 1021, Revision 9 Appendix C Page 12 of 13 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM D Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM D NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A U-1 Reactor Trip has occurred from 100% Power EP/1/A/5000/ES-0.1, Reactor Trip Response, is in progress and completed through subsequent step 11.
Total feed flow to S/G's is < 450 GPM and CA Pumps 1A and 1 B are not running. U-1 TO CA pump has tripped and is unavailable CF Isolation has not occurred.
The CRSRO directs you to place the 1 A CF Pump in service, and establish CF to the S/G's in accordance with Enclosure 4 of EP/1/A/5000/ES-0.1.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A U-1 Reactor Trip has occurred from 100% Power EP/1/A/5000/ES-0.1, Reactor Trip Response, is in progress and completed through subsequent step 11.
Total feed flow to S/G's is < 450 GPM and CA Pumps 1A and 1 B are not running. U-1 TD CA pump has tripped and is unavailable CF Isolation has not occurred.
The CRSRO directs you to place the 1 A CF Pump in service, and establish CF to the S/G's in accordance with Enclosure 4 of EP/1/A/5000/ES-0.1.
NUREG 1021, Revision 9
Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM E 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM E 2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Manually Align Phase B HVAC Eguipment JPM No.:
2009 Systems - Control Room JPM E KIA
Reference:
028, A4.01, 4.0/4.0 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator manually starts both Trains of the VE and VX Systems.
Required Materials:
None General
References:
EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection Handouts:, Phase B HVAC Equipment, of EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection., Phase B HVAC Equipment, of EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Manually Align Phase B HVAC Eguipment JPM No.:
2009 Systems - Control Room JPM E KIA
Reference:
028, A4.01, 4.0/4.0 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator manually starts both Trains of the VE and VX Systems.
Required Materials:
None General
References:
EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection Handouts:, Phase B HVAC Equipment, of EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection., Phase B HVAC Equipment, of EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C Time Critical Task:
Validation Time:
NO 5 minutes Page 3 of 11 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM E Form ES-C-1 NUREG 1021, Revision 9 Appendix C Time Critical Task:
Validation Time:
NO 5 minutes Page 3 of 11 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM E Form ES-C-1 NUREG 1021, Revision 9
Appendix C Page 4 of 11 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Resetto IC # 39, 100% Power, MOL. Go to RUN.
- 2.
Insert:
- a.
MALF-NC008A Large Break LOCA on Trigger 1.
Form ES-C-1
- b.
MALF-ISE004A (Both)Failure of Train A of Phase B Containment Isolation MALF-ISE004B (Both)Failure of Train B of Phase B Containment Isolation
- 3.
Actuate Trigger 1
- 4.
Perform steps 1 through 13 of EP/1/A/5000/E-0 (Including manually actions to overcome failure of Containment Phase B Isolation).
- 5.
Freeze Simulator.
- 1.
Reset Simulator to Temporary Snap IC-126 (December, 2008).
- 2.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 3.
Leave Simulator in FREEZE until operator is ready to begin.
NOTE: FWST level is depleting rapidly and could interfere with the performance of this JPM.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C Page 4 of 11 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC # 39, 100% Power, MOL. Go to RUN.
- 2.
Insert:
- a.
MALF-NC008A Large Break LOCA on Trigger 1.
Form ES-C-1
- b.
MALF-ISE004A (Both)Failure of Train A of Phase B Containment Isolation MALF-ISE004B (Both)Failure of Train B of Phase B Containment Isolation
- 3.
Actuate Trigger 1
- 4.
Perform steps 1 through 13 of EP/1/A/5000/E-0 (Including manually actions to overcome failure of Containment Phase B Isolation).
- 5.
Freeze Simulator.
- 1.
Reset Simulator to Temporary Snap IC-126 (December, 2008).
- 2.
Momentarily go to RUN to acknowledge Alarms then place Simulator in FREEZE.
- 3.
Leave Simulator in FREEZE until operator is ready to begin.
NOTE: FWST level is depleting rapidly and could interfere with the performance of this JPM.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C Page 5 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EPI1/Al5000/E-O, Enclosure 2, Phase B HVAC Equipment.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Steps 1 11.a) Check VE The operator observes the System in operation as 1A VE Fan Green status follows: VE Fans - ON.
light LIT, and Red status light OFF and determines that the fan is OFF.
The operator observes the 1 B VE Fan Green status light LIT, and Red status light OFF and determines that the fan is OFF.
- 2 (Steps 1.a RNO a.1-2) Start The operator places the 1 A fans as follows:
VE Fan control switch to ON, and observes the Red Select "ON".
status light LIT, Green Return switch to "AUTO".
status light OFF.
The operator returns the 1A VE Fan control switch to AUTO.
The operator places the 1 B VE Fan control switch to ON, and observes the Red status light LIT, Green status light OFF.
The operator returns the 1 B VE Fan control switch to AUTO.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C Page 5 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/1IA15000/E-O, Enclosure 2, Phase B HVAC Equipment.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT Simulator Instructor NOTE: Leave Simulator in FREEZE until operator is ready to begin.
1 (Steps 1/1.a) Check VE The operator observes the System in operation as 1A VE Fan Green status follows: VE Fans - ON.
light LIT, and Red status light OFF and determines that the fan is OFF.
The operator observes the 1 B VE Fan Green status light LIT, and Red status light OFF and determines that the fan is OFF.
- 2 (Steps 1.a RNO a.1-2) Start The operator places the 1 A fans as follows:
VE Fan control switch to ON, and observes the Red Select "ON".
status light LIT, Green Return switch to "AUTO".
status light OFF.
The operator returns the 1 A VE Fan control switch to AUTO.
The operator places the 1 B VE Fan control switch to ON, and observes the Red status light LIT, Green status light OFF.
The operator returns the 1 B VE Fan control switch to AUTO.
2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C STEPS 3
4 5
Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS (Step 1.b) Ensure all damper mode select switches in "AUTO!':
1 AVS-D-7 Mode Select 1 AVS-D-8 Mode Select 1 AVS-D-2 Mode Select 1 AVS-D-3 Mode Select.
(Step 1.c) Annulus pressure being maintained -
NEGATIVE.
System in operation as follows: Time since Phase B actuation - GREATER THAN 10 MINUTES.
STANDARD The operator observes that the 1 AVS-D-7 Mode Select Switch is in AUTO.
The operator observes that the 1 AVS-D-8 Mode Select Switch is in AUTO.
The operator observes that the 1 AVS-D-2 Mode Select Switch is in AUTO.
The operator observes that the 1 AVS-D-3 Mode Select Switch is in AUTO.
The operator observes 1VEP-5100 and 1VEP-5110 are indicating -3" water column and determines that the Annulus pressure is negative.
After the cue, the operator recognizes that the time since Phase B actuation is greater than 10 minutes and proceeds to Step 2.b.
Stu Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C STEPS 3
4 5
Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS STANOARO (Step 1.b) Ensure all damper mode select switches in "AUTO":
1 AVS-O-7 Mode Select The operator observes that the 1 A VS-O-7 Mode Select Switch is in AUTO.
1 AVS-O-8 Mode Select The operator observes that the 1 AVS-O-8 Mode Select Switch is in AUTO.
1 AVS-O-2 Mode Select The operator observes that the 1 AVS-O-2 Mode Select Switch is in AUTO.
1 AVS-O-3 Mode Select.
The operator observes that the 1 AVS-O-3 Mode Select Switch is in AUTO.
(Step 1.c) Annulus pressure The operator observes being maintained -
1 VEP-51 00 and 1 VEP-511 0 NEGATIVE.
are indicating -3" water column and determines that the Annulus pressure is negative.
(Steps 2/2.a) Check VX After the cue, the operator System in operation as recognizes that the time follows: Time since Phase B since Phase B actuation is actuation - GREATER greater than 10 minutes and THAN 10 MINUTES.
proceeds to Step 2.b.
Cue:
1t:
PhaseBlsolatiorfon Unit "
l' actuated 12 minutes ' "
ago.
- .;;i;~
- !si'.:.. :
~v,~"t-
'?'.~".;.:
>(i' '.
,.!'!" V' Form ES-C-1 S/U COMMENTS REQUIREO FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, ReVISion 9
Appendix C STEPS 6
- 7 Page 7 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.b) Check the following - OPEN:
1 RAF-D-4 (1 B Cont Air Ret The operator observes that the 1 RAF-D-4 Green status Fan To Lwr Cont Test A) light is LIT, Red status light is OFF.
1 VX-2B (1 B H2 Skimmer The operator observes that the 1VX-2B Green status Fan Isol Test A) light is LIT, Red status light is OFF.
1 RAF-D-2 (1A Cont Air Ret The operator observes that Fan To Lwr Cont Test A) the 1 RAF-D-2 Green status light is LIT, Red status light is OFF.
The operator observes that 1VX-1A (1A H2 Skimmer the 1VX-1A Green status Fan Isol Test A).
light is LIT, Red status light is OFF.
(Step 2.b RNO) open The operator presses and dampers.
holds the 1 RAF-D-4 OPEN pushbutton and observes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1 VX-2B OPEN pushbutton and observes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1 RAF-D-2 OPEN pushbutton and observes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1VX-1A OPEN pushbutton and observes the Red status light is LIT, Green status light is OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C STEPS 6
- 7 Page 7 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.b) Check the following - OPEN:
1 RAF-D-4 (1 B Cont Air Ret The operator obseNes that the 1 RAF-D-4 Green status Fan To Lwr Cont Test A) light is LIT, Red status light is OFF.
1VX-2B (1B H2 Skimmer The operator obseNes that the 1 VX-2B Green status Fan Isol Test A) light is LIT, Red status light is OFF.
1 RAF-D-2 (1 A Cont Air Ret The operator obseNes that Fan To Lwr Cont Test A) the 1 RAF-D-2 Green status light is LIT, Red status light is OFF.
The operator obseNes that 1VX-1A (1A H2 Skimmer the 1 VX-1 A Green status Fan Isol Test A).
light is LIT, Red status light is OFF.
(Step 2.b RNO) open The operator presses and dampers.
holds the 1 RAF-D-4 OPEN pushbutton and obseNes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1VX-2B OPEN pushbutton and obseNes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1 RAF-D-2 OPEN pushbutton and obseNes the Red status light is LIT, Green status light is OFF.
The operator presses and holds the 1VX-1A OPEN pushbutton and obseNes the Red status light is LIT, Green status light is OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C STEPS 8
- 9 10 Page 8 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.c) Check The operator observes the Containment Air Return 1A CAR Fan Green status fans - ON.
light LIT, and Red status light OFF.
The operator observes the 1 B CAR Fan Green status light LIT, and Red status light OFF.
(Step 2.c RNO) start fans.
The operator depresses the START pushbutton for the 1A CAR Fan, and observes the Red status light LIT, Green status light OFF.
The operator depresses the START pushbutton for the 1 B CAR Fan, and observes the Red status light LIT, Green status light OFF.
(Step 2.d) Check H2 The operator observes the Skimmer fans - ON.
1 A H2 Skimmer Fan Green status light LIT, and Red status light OFF.
The operator observes the 1 B H2 Skimmer Fan Green status light LIT, and Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C STEPS 8
- 9 10 Page 8 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.c) Check The operator observes the Containment Air Return 1A CAR Fan Green status fans - ON.
light LIT, and Red status light OFF.
The operator observes the 1 B CAR Fan Green status light LIT, and Red status light OFF.
(Step 2.c RNO) start fans.
The operator depresses the START pushbutton for the 1 A CAR Fan, and observes the Red status light LIT, Green status light OFF.
The operator depresses the START pushbutton for the 1 B CAR Fan, and observes the Red status light LIT, Green status light OFF.
(Step 2.d) Check H2 The operator observes the Skimmer fans - ON.
1 A H2 Skimmer Fan Green status light LIT, and Red status light OFF.
The operator observes the 1 B H2 Skimmer Fan Green status light LIT, and Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C STEPS ELEMENTS Page 9 of 11 PERFORMANCE INFORMATION STANDARD
- 11 (Step 2.d RNO) start fans.
The operator depresses the START pushbutton for the 1 A H2 Skimmer Fan, and observes the Red status light LIT, Green status light OFF.
The operator depresses the START pushbutton for the 1 B H2 Skimmer Fan, and observes the Red status light LIT, Green status light OFF.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C STEPS ELEMENTS Page 9 of 11 PERFORMANCE INFORMATION STANDARD
- 11 (Step 2.d RNO) start fans.
The operator depresses the START pushbutton for the 1 A H2 Skimmer Fan, and observes the Red status light LIT, Green status light OFF.
The operator depresses the START pushbutton for the 1 B H2 Skimmer Fan, and observes the Red status light LIT, Green status light OFF.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room J PM E NUREG 1021, Revision 9
Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM E Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM E NUREG 1021, Revision 9 Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM E Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM E NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET You are the Unit 2 BOP.
Unit 1 has experienced a Large Break LOCA.
The crew is implementing EP/1/A/SOOO/E-0, Reactor Trip or Safety Injection.
The CRSRO has directed you to check Phase B HVAC equipment in accordance with Enclosure 2, "Phase B HVAC Equipment," of EP/1/A/SOOO/E-0, "Reactor Trip or Safety Injection."
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET You are the Unit 2 BOP.
Unit 1 has experienced a Large Break LOCA.
The crew is implementing EP/1/A/5000/E-0, Reactor Trip or Safety Injection.
The CRSRO has directed you to check Phase B HVAC equipment in accordance with Enclosure 2, "Phase B HVAC Equipment," of EP/1/A/5000/E-0, "Reactor Trip or Safety Injection."
NUREG 1021, Revision 9
Appendix C Page 1 of 13 PERFORMANCE INFORMATION Form ES-C-1 81M JPM F 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Page 1 of 13 PERFORMANCE INFORMATION Form ES-C-1 81M JPM F 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C Page 2 of 13 PERFORMANCE INFORMATION Form ES-C-1 Facility:
Task
Title:
McGuire Perform Diesel Generator Operability Test KIA
Reference:
064, A4.06, 3.9/3.9 Task No.:
JPM No.:
2009 Systems - Control Room JPM F (Alternate Path)
Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant
-~-
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The 1 B DG is started from the Control Room and prepared for parallel operation with 1 ETB. The 1 B DG is stopped using its normal stop switch when indications of a sudden loss of crankcase vacuum and a loss of Engine speed are observed.
Required Materials:
None General
References:
PT/11A143501002B, "Diesel Generator 1 B Operability Test."
2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Page 2 of 13 PERFORMANCE INFORMATION Form ES-C-1 Facility:
Task
Title:
McGuire Perform Diesel Generator Operability Test KIA
Reference:
064, A4.06, 3.9/3.9 Task No.:
JPM No.:
2009 Systems - Control Room JPM F (Alternate Path)
Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom X
Plant
-~-
Simulator READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The 1 B DG is started from the Control Room and prepared for parallel operation with 1 ETB. The 1 B DG is stopped using its normal stop switch when indications of a sudden loss of crankcase vacuum and a loss of Engine speed are observed.
Required Materials:
None General
References:
PT/1/A/4350/002B, "Diesel Generator 1 B Operability Test."
2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C Handouts:
Time Critical Task:
Validation Time:
Page 3 of 13 PERFORMANCE INFORMATION Form ES-C-1 PT/1/N4350/002B, "Diesel Generator 1 B Operability Test," with 3.1 marked up for place-keeping through Step 2.6.
NO 20 minutes 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Handouts:
Time Critical Task:
Validation Time:
Page 3 of 13 PERFORMANCE INFORMATION Form ES-C-1 PT/1/N43501002B, "Diesel Generator 1 B Operability Test," with 3.1 marked up for place-keeping through Step 2.6.
NO 20 minutes 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C Page 4 of 13 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC # 20, 100% Power, MOL. Go to RUN.
- 2.
Ensure that the A Train is the operating Train.
- 3.
Insert DG006B2, over-under excitation value = 95.
Form ES-C-1
- 4.
1AD-111D06 = ON, DIG B Panel trouble (Simulates Before & After LOP On).
- 5.
Insert MALF-DG002B, DIG B FAILS TO MINIMUM SPEED, Assign to Trigger #1.
- 1.
Reset Simulator to Temporary Snap IC-127 (December, 2008).
- 2.
Momentarily go to run and acknowledge alarms.
NOTE: During the NLO Actions of JPM Step 10, Simulator Instructor must DELETE 1AD-111006 = ON (Simulates Before & After LOP Off)
THEN, assign 1AD-11/D06 = ON to Trigger #1, DIG B Panel trouble (Simulates High Crankcase Pressure).
NOTE: At step 6 once DIG had come up to voltage and freq, DELETED DG006B2. This will allow the student to control voltage.
2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Page 4 of 13 PERFORMANCE INFORMATION SIMULATOR OPERATIONAL GUIDELINES
- 1.
Reset to IC # 20, 100% Power, MOL. Go to RUN.
- 2.
Ensure that the A Train is the operating Train.
- 3.
Insert DG006B2, over-under excitation value = 95.
Form ES-C-1
- 4.
1AD-111D06 = ON, DIG B Panel trouble (Simulates Before & After LOP On).
- 5.
Insert MALF-DG002B, DIG B FAILS TO MINIMUM SPEED, Assign to Trigger #1.
- 1.
Reset Simulator to Temporary Snap IC-127 (December, 2008).
- 2.
Momentarily go to run and acknowledge alarms.
NOTE: During the NLO Actions of JPM Step 10, Simulator Instructor must DELETE 1AD-111D06 = ON (Simulates Before & After LOP Off)
THEN, assign 1AD-111D06 = ON to Trigger #1, DIG B Panel trouble (Simulates High Crankcase Pressure).
NOTE: At step 6 once DIG had come up to voltage and freq, DELETED DG006B2. This will allow the student to control voltage.
2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C Page 5 of 13 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout PT/1/Al4350/002B, Enclosure 13.1, marked up for place-keeping through Step 2.6.
START TIME:
STEPS ELEMENTS STANDARD SIU COMMENTS REQUIRED FOR UNSAT
- 1 (Step 2.7) Place Control The operator places the Room "1 B DIG Mode Control Room" 1 B DIG Select" to applicable Mode Select" to C/R.
position:
"LOCAL" to start DIG from local panel OR "C/R" to start DIG from Control Room 2
(Step 2.8) Notify Unit 1 The operator informs the Control Room that adjusting OATC that adjusting Main Main Generator voltage Generator voltage while the while the DIG is tied to the DIG is tied to the grid will grid will significantly affect significantly affect the the power factor on the power factor on the operating DIG.
operating DIG.
Cue:
Acknowledge as the U-1 OATC.
3 (Caution prior to Step 2.9)
The operator reads Caution Steps 2.9-2.12 should be and proceeds to Step 2.9.
performed in less than two minutes.
2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Page 5 of 13 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout PT/1/A/4350/002B, Enclosure 13.1, marked up for place-keeping through Step 2.6.
START TIME:
STEPS ELEMENTS STANDARD SIU COMMENTS REQUIRED FOR UNSAT
- 1 (Step 2.7) Place Control The operator places the Room "1 B DIG Mode Control Room" 1 B DIG Select" to applicable Mode Select" to C/R.
position:
"LOCAL" to start DIG from local panel OR "C/R" to start DIG from Control Room 2
(Step 2.8) Notify Unit 1 The operator informs the Control Room that adjusting OATC that adjusting Main Main Generator voltage Generator voltage while the while the DIG is tied to the DIG is tied to the grid will grid will significantly affect significantly affect the the power factor on the power factor on the operating DIG.
operating DIG.
Cue:
Acknowledge as the U-1 OATC.
3 (Caution prior to Step 2.9)
The operator reads Caution Steps 2.9-2.12 should be and proceeds to Step 2.9.
performed in less than two minutes.
2009 Systems - Control Room J PM F NUREG 1021, Revision 9
Appendix C STEPS
- 4
- 5 6
Page 6 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.9) Rotate "Load The operator contacts the Limit" control knob on NEO and directs that the Woodward Governor "Load Limit" control knob on Actuator counter-clockwise Woodward Governor to "SLOW START" position.
Actuator be rotated counter-clockwise to "SLOW START" position.
Cue:
NEO reports. that the Load Lil11itcontrol***krtobis in the "SLOW START" position.
(Step 2.10) Depress The operator depresses the "START" on "1 B Diesel START pushbutton on the Generator."
1 B DIG, and observes Red status light LIT, and Green status light OFF.
The operator observes status light 1 SI-15/B-3 LIT momentarily then OFF, and THEN status light 1 SI-15/B-4 LIT.
(Step 2.11) Check DIG The operator observes 1 B starts and reaches 95%
DG Frequency to be ::::60.2 speed (57 Hz or local start Hz.
timer times out).
Simulator.. Operator:
DELETE"DG006B2" to allow student to control I voltage.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS
- 4
- 5 6
Page 6 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.9) Rotate "Load The operator contacts the Limit" control knob on NEO and directs that the Woodward Governor "Load Limit" control knob on Actuator counter-clockwise Woodward Governor to "SLOW START" position.
Actuator be rotated counter-clockwise to "SLOW START" position.
Cue:
NEO reports that the Load Limit control knob is in the "SLOW START" position.
(Step 2.10) Depress The operator depresses the "START" on "1B Diesel ST ART pushbutton on the Generator."
1 B DIG, and observes Red status light LIT, and Green status light OFF.
The operator observes status light 1 SI-15/B-3 LIT momentarily then OFF, and THEN status light 1 SI-15/B-4 LIT.
(Step 2.11) Check DIG The operator observes 1 B starts and reaches 95%
DG Frequency to be ::::60.2 speed (57 Hz or local start Hz.
timer times out).
Simulator Operator:
DELETE "DG006B2" to allow student to control voltage.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C STEPS
- 7 8
9 Page 7 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.12) When DIG has The operator contacts the started, rotate "Load Limit" NEO and directs that the control knob on Woodward "Load Limit" control knob on Governor fully clockwise Woodward Governor (MAX FUEL).
Actuator be rotated fully clockwise.
Cue:
NEO reports that the Load Limit control knob isin the "MAX FUEL" position.
(Step 2.13) Record DIG The operator records the start date/time:
current time and date in the space provided.
(Step 2.14) Evaluate The operator requests the operability of 1 B DIG.
CRSRO to evaluate the operability of the 1 B DIG inoperable.
Cue:
Exarniner*Acknowledge as the CRSRO and Initial Step 2.. 14 irrprocedure.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS
- 7 8
9 Page 7 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.12) When DIG has The operator contacts the started, rotate "Load Limit" NEO and directs that the control knob on Woodward "Load Limit" control knob on Governor fully clockwise Woodward Governor (MAX FUEL).
Actuator be rotated fully clockwise.
Cue:
NEO reports that the Load Limit control knob is in the "MAX FUEL" position.
(Step 2.13) Record DIG The operator records the start date/time:
current time and date in the space provided.
(Step 2.14) Evaluate The operator requests the operability of 1 B DIG.
CRSRO to evaluate the operability of the 1 B DIG inoperable.
Cue:
Examiner Acknowledge as the CRSRO and Initial Step 2.14 in procedure.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C STEPS 10 ELEMENTS (Steps 2.15-21) Local actions.
Page 8 of 13 PERFORMANCE INFORMATION STANDARD The operator observes that Step 2.15-2.21 are local actions and directs the NEO to perform these actions in the procedure and report back to the Control Room.
Simulator Operator:
DELETE 1 AD*11ID06:: ON (Simulates Before & After LOP Off) THEN, assign 1AD-11/D06 =ON to Trigger #1, D/GB Panel trouble* (Simulates High Crankcase Pressure).
i****
Cue:
- .*ii N EO r~p()rts that local actions have been taken and steps* 2.15 through 2.21 areisigned off in the procedure.
Cue:
Ifasked, theNLOreports:
- . OllleveUsvisiblein the Gov~rnorisight*9Iass.
JacketWaterpressure is
- >24pslg.
LlJbeOilpressureJs>36 psig.
The Before&.AfterLOP isOFFandinAUTO.
1LD-113B.(1BD/GLube Oil Filter Bypass) indicates Closed.
Fuel Oil Press IJreis > 32 psig.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS ELEMENTS 10 (Steps 2.15-21) Local actions.
Page 8 of 13 PERFORMANCE INFORMATION STANDARD The operator observes that Step 2.15-2.21 are local actions and directs the NEO to perform these actions in the procedure and report back to the Control Room.
Simulator Operator:
DELETE 1AD-111D06 = ON (Simulates Before & After LOP Off) THEN, assign 1AD-111D06 = ON to Trigger #1, DIG B Panel trouble (Simulates High Crankcase Pressure).
Cue:
NEO reports that local actions have been taken and steps 2.15 through 2.21 are signed off in the procedure.
Cue:
If asked, the NLO reports:
Oil level is visible in the GOVernor sight glass.
Jacket Water pressure is
> 24 psig.
Lube Oil pressure is > 36 psig.
The Before & After LOP is OFF and in AUTO.
1LD-113B (18 DIG Lube Oil Filter Bypass) indicates Closed.
Fuel on Pressure is > 32 psig.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C STEPS 11 12 13 14
- 15 Page 9 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.22) Check the The operator turns on OAC following on OAC (Turn-on Code RNESS1 Band Code - RNESS1 B):
observes that 1 RN-71 B is OPEN and that there is 1RN-71B (B KD HX Supply
==1500 gpm through the 1 B Isol) indicates "OPEN."
DIG HeatExchange~
RN flow indicated through DIG Heat Exchanger.
(Step 2.23) Check the following:
The operator observes 1 B Steady-state DIG volts 3740 DIG voltage to be==3953 V.
- 4580 V.
The operator observes 1 B Steady-state DIG frequency DIG frequency to be==60.2 58.8 - 61.2 Hz.
Hz.
(Step 2.24) Ensure Control The operator observes the Room" 1 B DIG Mode Control Room" 1 B DIG Select" to applicable Mode Select" to C/R.
position:
"LOCAL" to load DIG from local panel OR "C/R" to load DIG from Control Room (Step 2.25) Check "Line The operator observes line Volts" 3960-4360 V.
voltage to be==4069 V.
(Step 2.26) Adjust DIG The operator rotates the 1 B voltage 50-100 V higher DIG Voltage Adjust switch than line voltage using "1 B to RAISE and adjusts DG DIG Voltage Adjust."
voltage to==4119-4169 V.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS 11 12 13 14
- 15 Page 9 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.22) Check the The operator turns on OAC following on OAC (Turn-on Code RNESS1 Band Code - RNESS1 B):
observes that 1 RN-71 B is OPEN and that there is 1RN-71B (B KD HX Supply
==1500 gpm through the 1 B Isol) indicates "OPEN."
DIG HeatExchange~
RN flow indicated through DIG HeatExchange~
(Step 2.23) Check the following:
The operator observes 1 B Steady-state DIG volts 3740 DIG voltage to be==3953 V.
- 4580 V.
The operator observes 1 B Steady-state DIG frequency DIG frequency to be==60.2 58.8 - 61.2 Hz.
Hz.
(Step 2.24) Ensure Control The operator observes the Room" 1 B DIG Mode Control Room "1 B DIG Select" to applicable Mode Select" to C/R.
position:
"LOCAL" to load DIG from local panel OR "C/R" to load DIG from Control Room (Step 2.25) Check "Line The operator observes line Volts" 3960-4360 V.
voltage to be==4069 V.
(Step 2.26) Adjust DIG The operator rotates the 1 B voltage 50-100 V higher DIG Voltage Adjust switch than line voltage using "1 B to RAISE and adjusts DG DIG Voltage Adjust."
voltage to==4119-4169 V.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C STEPS 16 17
- 18
- 19 Page 10 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Caution prior to Step 2.27)
The operator reads the Failure of the Droop Caution and proceeds to Permissive could result in Step 2.27.
erratic DIG operation while paralleled to the bus.
(Step 2.27) IF OAC The operator observes OAC available, check OAC point Point M1 D3356 indicates M 1 D3356 (1 B DIG Droop COMPLETE.
Permissive) indicates "COMPLETE."
(Step 2.28) Place "1 B DIG The operator places the 1 B Synch" to "ON."
DIG Synch Switch to ON, and observes synch scope stopped at 5 o'clock.
(Step 2.29) Using 1 B DIG The operator uses the Gov Cntrl, adjust DIG speed Governor Control adjust so to allow synchroscope to that the synchroscope is move slowly and smoothly moving slowly and smoothly in the FAST (clockwise) in the FAST (clockwise) direction.
direction.
Simulator Operator:
Operate Trigger #1 to fail DIG to minimum speed.
Note: SynchroscopewHI rapidly change direction.,
and 1AD.. 11/D*6willalarm.
(Alternate Path)
Cue:
The operator may contact the NEO.
If so, report that the DGis makil1gagreat deal of noise.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS 16 17
- 18
- 19 Page 10 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Caution prior to Step 2.27)
The operator reads the Failure of the Droop Caution and proceeds to Permissive could result in Step 2.27.
erratic DIG operation while paralleled to the bus.
(Step 2.27) IF OAC The operator observes OAC available, check OAC point Point M1 D3356 indicates M 1 D3356 (1 B DIG Droop COMPLETE.
Permissive) indicates "COMPLETE."
(Step 2.28) Place "1 B DIG The operator places the 1 B Synch" to "ON."
DIG Synch Switch to ON, and observes synch scope stopped at 5 o'clock.
(Step 2.29) Using 1 B DIG The operator uses the Gov Cntrl, adjust DIG speed Governor Control adjust so to allow synchroscope to that the synchroscope is move slowly and smoothly moving slowly and smoothly in the FAST (clockwise) in the FAST (clockwise) direction.
direction.
Simulator Operator:
Operate Trigger #1 to fail DIG to minimum speed.
Note: Synchroscope will rapidly change direction, and 1AD-11/D-6 will alarm.
(Alternate Path)
Cue:
The operator may contact the NEO.
If so, report that the DG is making a great deal of noise.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C STEPS
- 20 Page 11 of 13 PERFORMANCE INFORMATION ELEMENTS (Precaution 6.7) IF a sudden loss of crankcase vacuum is indicated, together with an unusual knock or sudden decrease of speed, stop engine with normal stop switch to ensure circulation of LD and KD for at least 20 minutes.
Engine covers must remain in place during this cooling period, since engine vapors may ignite.
STANDARD The operator places the 1 B DIG normal stop switch to STOP.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
SIU Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C STEPS
- 20 Page 11 of 13 PERFORMANCE INFORMATION ELEMENTS STANDARD (Precaution 6.7) IF a The operator places the 1 B sudden loss of crankcase DIG normal stop switch to vacuum is indicated, STOP.
together with an unusual knock or sudden decrease of speed, stop engine with Examiner NOTE:
normal stop switch to ensure circulation of LD and The critical portion of this KD for at least 20 minutes.
step isto Stop the Diesel.
Engine covers must remain While the preferred in place during this cooling means to stop the Diesel period, since engine vapors is via the normal stop may ignite.
switch, if the operator stops the engine via the emergency stop pushbutton, the critical portion of the step is satisfied.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C Page 12 of 13 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM F Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM F NUREG 1021, Revision 9 Appendix C Page 12 of 13 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM F Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM F NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 is operating at 100% power.
A monthly test of the 1 B Emergency Diesel Generator is required.
The A Train is the operating Train.
The System Engineer wants to start and stop the Diesel from the Control Room.
PT/1/A/43501002B Enclosure 13.1 is complete through Step 2.6.
Two NEOs, Bob and Carol are standing by at the 1 B DIG to assist. They have a copy of the PT, and can be reached at ext. 4276 The CRSRO has directed you to conduct a Slow Start of the 1 B Emergency Diesel Generator starting with Step 2.7 of Enclosure 13.1 of PT/1/A/43501002B, "Diesel Generator 1 B Operability Test."
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 is operating at 100% power.
A monthly test of the 1 B Emergency Diesel Generator is required.
The A Train is the operating Train.
The System Engineer wants to start and stop the Diesel from the Control Room.
PT/1/N43501002B Enclosure 13.1 is complete through Step 2.6.
Two NEOs, Bob and Carol are standing by at the 1 B DIG to assist. They have a copy of the PT, and can be reached at ext. 4276 The CRSRO has directed you to conduct a Slow Start of the 1 B Emergency Diesel Generator starting with Step 2.7 of Enclosure 13.1 of PT/1/N43501002B, "Diesel Generator 1 B Operability Test."
NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 81M JPM G 2009 Systems - Control Room JPM G NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 SIM JPM G 2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 Facility:
Task
Title:
KIA
Reference:
Examinee:
Facility Evaluator:
Method of testing:
McGuire Restore Repaired Power Range Channel to Service 015 A2.01 3.5/3.9 Simulated Performance:
Task No.:
JPM No.:
2009 Systems - Control Room JPM G (Alternate Path)
Examiner:
Date:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
Complete a restoration of a previously failed Power Range Channel and recognize that the instrument has failed again during the restoration. All critical tasks evaluated as satisfactory.
Required Materials:
N43 Control Power Fuses General
References:
AP/1/N5500/16, Malfunction of Nuclear Instrumentation Handouts:
AP/1/N5500/16, Malfunction of Nuclear Instrumentation, Case III, marked up for place-keeping through Step 21.
2009 Systems - Control Room JPM G NUREG 1021, Revision 9 Appendix C Facility:
Task
Title:
KJA
Reference:
Examinee:
Facility Evaluator:
Method of testing:
Job Performance Measure Worksheet Form ES-C-1 McGuire Restore Repaired Power Range Channel to Service 015 A2.01 3.5/3.9 Task No.:
JPM No.:
2009 Systems - Control Room JPM G (Alternate Path)
Examiner:
Date:
Simulated Performance:
Actual Performance:
x Classroom Simulator x
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
. Initial Conditions:
V\\MHb:r\\it1::at160%p~wer; P6W~rR.ang.e Chc;mn~I.N4~Jt;lfled high.
Th~~~htroIR?~P1'. w.r~rr)0'y~d pow~~Ran~~*Cha~nel.N43from
?~;~~j:~~ in.Cl~¢g9~<:I~,~\\I'v'i.,tffl}~P~p,"M~.,lf(:lQ9ti8n of Nuclear.
... *'n.:'stlt:lm* *e**."ntati'o'n''Case/I:I'I.>'> ****:'**.*:,i' \\ii. '\\.
'u' i,
- ~The instf~hlent has b~en out of service for 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.
IAE has indicated that the chahnel has been repaired and can now be restored to,service.
Task Standard:
Complete a restoration of a previously failed Power Range Channel and recognize that the instrument has failed again during the restoration. All critical tasks evaluated as satisfacto~.
Required Materials:
N43 Control Power Fuses General
References:
AP/1 IA/5500/16, Malfunction of Nuclear Instrumentation Handouts:
AP/1/A/5500/16, Malfunction of Nuclear Instrumentation, Case III, marked up for place-keeping through Step 21.
2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C Time Critical Task:
NO Validation Time:
5 minutes 2009 Systems - Control Room JPM G Job Performance Measure Worksheet Form ES-C-1 NUREG 1021, Revision 9 Appendix C Time Critical Task:
Validation Time:
Job Performance Measure Worksheet Form ES-C-1 The CRsRohasqir~~t~q'Y!;'i~9!r~~t917~Pb\\,verRange Channel N43 to servi~},ip~9~~rrqi~~c,giMtlr..... ~p22Cbf;n;p16,"fv1~JfunctipJ1iOfNucl~ar Inst~umerl~~~lb)~,;~~:'<jase HI, "Power Range M~'1~~,if:)c;;tiQfl.".'".. '.. ;'
NO 5 minutes 2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C Job Performance Measure Worksheet Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1. Reset simulator to IC-39, 100% Power
- 2. Place in RUN and allow time to stabilize
- 3. Insert Malfunction ENB13F, Power Range Channel Failure, N43
- 4. Perform the actions of AP/1/N5500/16 up through step 21.
- 5. Run CAEPZZPR43BS
- 6. Remove Malfunction.
- 7. Freeze the Simulator.
- 1. Reset to IC-129.
NOTE: The Simulator Instructor will need to insert Malfunction ENB013F just prior to Step 13 of JPM.
2009 Systems - Control Room JPM G NUREG 1021, Revision 9 Appendix C Job Performance Measure Worksheet Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1. Reset simulator to IC-39, 100% Power
- 2. Place in RUN and allow time to stabilize
- 3. Insert Malfunction ENB13F, Power Range Channel Failure, N43
- 4. Perform the actions of AP/1/A/5500/16 up through step 21.
- 5. Run CAEPZZPR43BS
- 6. Remove Malfunction.
- 7. Freeze the Simulator.
- 1. ResettoIC-129.
NOTE: The Simulator Instructor will need to insert Malfunction ENB013F just prior to Step 13 of JPM.
2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C Page 5 of 10 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/Al5500/16, with Case III marked up for place-keeping through step 21.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Step 22) WHEN malfunctioning P/R channel repaired, THEN perform the following:
(Step 22.a) Ensure Operator checks fuses installed in Power Range B instrument power fuses in Drawer.
"POWER RANGE B" drawer installed.
- 2 (Step 22.b) Install control Operator inserts fuses into power fuses in "POWER Power Range A Drawer.
RANGE A" drawer.
The operator observes the Drawer lights come back on.
- 3 (Step 22.c) Select "RESET" Operator selects RESET on on the "RATE MODE the Rate Mode Switch and SWITCH".
allows spring-return to NORMAL.
The operator observes the Positive Rate Trip light extinguishes.
4 (Step 22.d) Check reactor Operator observes other power - GREATER THAN Power Range Channels and 25%.
determines that the plant is at 100% power.
2009 Systems - Control RoomJPM G NUREG 1021, Revision 9 Appendix C Page 5 of 10 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/Al5500/16, with Case III marked up for place-keeping through step 21.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Step 22) WHEN malfunctioning P/R channel repaired, THEN perform the following:
(Step 22.a) Ensure Operator checks fuses installed in Power Range B instrument power fuses in Drawer.
"POWER RANGE B" drawer installed.
- 2 (Step 22.b) Install control Operator inserts fuses into power fuses in "POWER Power Range A Drawer.
RANGE A" drawer.
The operator observes the Drawer lights come back on.
- 3 (Step 22.c) Select "RESET" Operator selects RESET on on the "RATE MODE the Rate Mode Switch and SWITCH".
allows spring-return to NORMAL.
The operator observes the Positive Rate Trip light extinguishes.
4 (Step 22.d) Check reactor Operator observes other power - G REA TER THAN Power Range Channels and 25%.
determines that the plant is at 100% power.
2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C STEPS 5
6
- 7
- 8
- 9 Page 6 of 10 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 22.e) Check the Operator observes that the following bistable - LIT:
P/R HI FLUX LO STPT Bistable light is LIT (1 S12-
"P/R HI FLUX LO STPT" C12).
(1 SI-2).
(Step 22.f) Check the Operator observes that the following bistables - DARK:
P/R HI FLUX HI STPT "P/R HI FLUX HI STPT" Bistable light is DARK (1 SI2-C13).
(1 SI-2)
"P/R HI FLUX RATE" (1SI-Operator observes that the P/R HI FLUX HI RATE
- 3)..
Bistable light is DARK (1SI3-C1 ).
(Step 22.g) Place At Comparator and Rate "COMPARATOR Drawer, Operator places CHANNEL DEFEAT" switch the COMPARATOR to "NORMAL".
CHANNEL DEFEAT switch to NORMAL.
The operator observes the Comparator Defeat light extinguishes.
(Step 22.h) Place "POWER At Detector Current MISMATCH BYPASS" Comparator Drawer, switch to "OPERATE".
Operator places the POWER MISMATCH BYPASS switch to OPERATE.
(Step 22.i) Place "UPPER At Detector Current SECTION" switch to Comparator Drawer, "NORMAL".
Operator places the UPPER SECTION switch to NORMAL.
The operator observes the Channel Defeat light extinguishes.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM G NUREG 1021, Revision 9 Appendix C STEPS 5
6
- 7
- 8
- 9 Page 6 of 10 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 22.e) Check the Operator observes that the following bistable - LIT:
P/R HI FLUX LO STPT Bistable light is LIT (1SI2-
"P/R HI FLUX LO STPT" C12).
(1SI-2).
(Step 22.f) Check the Operator observes that the following bistables - DARK:
P/R HI FLUX HI STPT "P/R HI FLUX HI STPT" Bistable light is DARK (1 SI2-C13).
(1SI-2)
"P/R HI FLUX RATE" (1SI-Operator observes that the P/R HI FLUX HI RATE 3).
Bistable light is DARK (1 SI3-C1).
(Step 22.g) Place At Comparator and Rate "COMPARATOR Drawer, Operator places CHANNEL DEFEAT" switch the COMPARATOR to "NORMAL".
CHANNEL DEFEAT switch to NORMAL.
The operator observes the Comparator Defeat light extinguishes.
(Step 22.h) Place "POWER At Detector Current MISMATCH BYPASS" Comparator Drawer, switch to "OPERATE".
Operator places the POWER MISMATCH BYPASS switch to OPERATE.
(Step 22.i) Place "UPPER At Detector Current SECTION" switch to Comparator Drawer, "NORMAL".
Operator places the UPPER SECTION switch to NORMAL.
The operator observes the Channel Defeat light extinguishes.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C Page 7 of 10 Form ES-C-1 PERFORMANCE INFORMATION STEPS
- 10
- 11
- 12 ELEMENTS (Step 22.j) Place "LOWER SECTION" switch to "NORMAL".
(Step 22.
ace STOP BYPASS" switch to "OPERATE".
S/G PROGRAM LEVEL CHANNEL DEFEAT" switch to "NORM".
2009 Systems - Control Room JPM G STANDARD At Detector Current Comparator Drawer, Operator places the LOWER SECTION switch to NORMAL.
The operator observes the Channel Defeat light extinguishes.
At Detector Current Comparator Drawer, Operator places the ROD STOP BYPASS switch to OPERATE.
At 1 MC2, Operator places the P/R TO S/G PROGRAM LEVEL CHANNEL DEFEAT switch to NORM.
(Alternate Path)
S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C STEPS
- 10
- 11
- 12 Page 7 of 10 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 22.j) Place "LOWER At Detector Current SECTION" switch to Comparator Drawer, "NORMAL".
Operator places the LOWER SECTION switch to NORMAL.
The operator observes the Channel Defeat light extinguishes.
(Step 22.k) Place "ROD At Detector Current STOP BYPASS" switch to Comparator Drawer, "OPERATE".
Operator places the ROD STOP BYPASS switch to OPERATE.
(Step 22.1) Place "PJR TO At 1 MC2, Operator places SJG PROGRAM LEVEL the PJR TO SJG PROGRAM CHANNEL DEFEAT" switch LEVEL CHANNEL DEFEAT to "NORM".
switch to NORM.
Simulator Instructor:
Upon completi.on of Step 22.1 insert Malfunction ENB013F, Failure on N43.
Note: This will cause several MCB alarms. The operator may address ARP1AD-2 or go directly to AP-16.
(Alternate Path)
Form ES-C-1 SJU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C STEPS
- 13 ELEMENTS Page 8 of 10 PERFORMANCE INFORMATION STANDARD (Step 1) Place control rods Operator places Rods in in manual.
MANUAL.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
2009 Systems - Control Room JPM G Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C STEPS
- 13 ELEMENTS Page 8 of 10 PERFORMANCE INFORMATION STANDARD (Step 1) Place control rods Operator places Rods in in manual.
MANUAL.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
2009 Systems - Control Room JPM G Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9
Appendix C Page 9 of 10 VERIFICATION OF COMPLETION Job Performance Measure No.:
2008 Audit JPM G Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Form ES-C-1 Examiner's Signature:
Date:
2009 Systems - Control Room JPM G NUREG 1021, Revision 9 Appendix C Page 9 of 10 VERIFICATION OF COMPLETION Job Performance Measure No.:
2008 Audit JPM G Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Form ES-C-1 Examiner's Signature:
Date:
2009 Systems - Control Room JPM G NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET With Unit 1 at 100% power, Power Range Channel N43 failed high.
The Control Room crew removed Power Range Channel N43 from service in accordance with AP16, "Malfunction of Nuclear Instrumentation," Case III.
The instrument has been out of service for 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.
IAE has indicated that the channel has been repaired and can now be restored to service.
The CRSRO has directed you to restore Power Range Channel N43 to service in accordance with Step 22 of AP16, "Malfunction of Nuclear Instrumentation," Case III, "Power Range Malfunction."
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET With Unit 1 at 100% power, Power Range Channel N43 failed high.
The Control Room crew removed Power Range Channel N43 from service in accordance with AP16, "Malfunction of Nuclear Instrumentation," Case III.
The instrument has been out of service for 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br />.
IAE has indicated that the channel has been repaired and can now be restored to service.
The CRSRO has directed you to restore Power Range Channel N43 to service in accordance with Step 22 of AP16, "Malfunction of Nuclear Instrumentation," Case III, "Power Range Malfunction."
NUREG 1021, Revision 9
Appendix C Page 1 of 15 PERFORMANCE INFORMATION Form ES-C-1 SIM JPM H 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C Page 1 of 15 PERFORMANCE INFORMATION Form ES-C-1 81M JPM H 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C Page 2 of 15 PERFORMANCE INFORMATION Form ES-C-1 Facility:
McGuire Task No.:
MO-7319, MO-3331.3 Task
Title:
Place Standby Component Cooling JPM No.:
2009 Systems - Control Train in Operation Room JPM H KIA
Reference:
008, A4.01, 3.3/3.1 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The '8' Train Component Cooling pumps are started in accordance with AP/1/N5500/21, Loss of Component Cooling Water.
Required Materials:
None General
References:
AP/1/N5500/21, Loss of Component Cooling Water Handouts:
Time Critical Task:
AP/1/N5500/21, Loss of Component Cooling Water, marked up for place-keeping through Step 8.
NO 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C Page 2 of 15 PERFORMANCE INFORMATION Form ES-C-1 Facility:
McGuire Task No.:
MO-7319, MO-3331.3 Task
Title:
Place Standby Component Cooling JPM No.:
2009 Systems - Control Train in Operation Room JPM H KIA
Reference:
008, A4.01, 3.3/3.1 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
Actual Performance:
X Classroom Simulator X
Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The '8' Train Component Cooling pumps are started in accordance with AP/1/N5500/21, Loss of Component Cooling Water.
Required Materials:
None General
References:
AP/1/N5500/21, Loss of Component Cooling Water Handouts:
AP/1/N5500/21, Loss of Component Cooling Water, marked up for place-keeping through Step 8.
Time Critical Task:
NO 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C Validation Time:
15 minutes Page 3 of 15 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM H Form ES-C-1 NUREG 1021, Revision 9 Appendix C Validation Time:
15 minutes Page 3 of 15 PERFORMANCE INFORMATION 2009 Systems - Control Room JPM H Form ES-C-1 NUREG 1021, Revision 9
Appendix C Page 4 of 15 PERFORMANCE INFORMATION Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1. Reset to IC-20, 100% BOC
- 2. Insert MAL-KC010A (1A1 KC Pump trips due to over current)
- 3. Set 1 KC-149 (A KF Hx Outlet Flow Control) to 400 gpm to prevent runout of 1A2 KC Pump
- 4. Freeze Simulator
- 1. Reset Simulator to Temporary Snap IC-130 (December, 2008).
- 2. Momentarily go to run and acknowledge alarms.
2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C Page 4 of 15 PERFORMANCE INFORMATION Form ES-C-1 SIMULATOR OPERATIONAL GUIDELINES
- 1. Reset to IC-20, 100% BOC
- 2. Insert MAL-KC010A (1A1 KC Pump trips due to over current)
- 3. Set 1 KC-149 (A KF Hx Outlet Flow Control) to 400 gpm to prevent runout of 1 A2 KC Pump
- 4. Freeze Simulator
- 1. Reset Simulator to Temporary Snap IC-130 (December, 2008).
- 2. Momentarily go to run and acknowledge alarms.
2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C Page 5 of 15 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/A15500/21, Loss of Component Cooling Water, marked up for place-keeping through step 8.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Step 9) Start standby KC The operator observes B train as follows:
Train KC components as available.
(Step 9.a) Check standby KC train - AVAILABLE TO If the operator asks the START.
CRSRO whether or not Train B of KC is available, provide the following cue:
Cue:
"B" train of KC is available to start.
2 (Step 9.b) Check standby The operator observes KC Surge Tank Level -
1 KCP-5640 and determines GREATER THAN 2 FT.
B Train KC Surge Tank level to be==6.6 ft.
3 (Step 9.c) Start the standby KC train PER one of the The operator proceeds to following:.
To start A train, GO TO To start B train, GO TO 4
(Enclosure 5, Step 1) Check The operator observes the 1 KC-81 B (KC to B NO HX) 1 KC-81 B Green status light CLOSED.
LIT, Red status light OFF.
2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C Page 5 of 15 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/A15500/21, Loss of Component Cooling Water, marked up for place-keeping through step 8.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Step 9) Start standby KC The operator observes B train as follows:
Train KC components as available.
(Step 9.a) Check standby KC train - AVAILABLE TO If the operator asks the START.
CRSRO whether or not Train B of KC is available, provide the following cue:
Cue:
"B" train of KC is available to start.
2 (Step 9.b) Check standby The operator observes KC Surge Tank Level -
1 KCP-5640 and determines GREATER THAN 2 FT.
B Train KC Surge Tank level to be==6.6 ft.
3 (Step 9.c) Start the standby KC train PER one of the The operator proceeds to following:.
To start A train, GO TO To start B train, GO TO 4
(Enclosure 5, Step 1) Check The operator observes the 1 KC-81 B (KC to B NO HX) 1 KC-81 B Green status light CLOSED.
UT, Red status light OFF.
2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS 5
6 7
8 9
10
- 11 Page 6 of 15 PERFORMANCE INFORMATION ELEMENTS (Step 2) Check 1 KC-56A (KC to A NO HX) CLOSED.
(Step 3) Check 1A Train KC pumps - OFF.
(Step 3 RNO) GO TO Step
- 5.
(Step 5) Check 1 B Train KC pumps - OFF.
(Notes prior to Step 6)
Voiding of 1 B train KC may be suspected if any of the following have occurred:
1 B train KC pumps were tripped due to cavitation or air entrainment.
1A train KC pumps were tripped due to cavitation or air entrainment while B train was still cross-tied to A train.
(Step 6) IF voiding of 1 B train KC is suspected, THEN........
(Step 7) Close the following:
(Step 7.a) 1 KC-53B (Trn B Aux Bldg Non Ess Sup Isol)
STANDARD The operator observes the 1 KC-56A Green status light LIT, Red status light OFF.
The operator observes the Red status light LIT, and the Green status light OFF for the 1A2 KC Pump and proceeds to the Step 3 RNO.
The operator proceeds to Step 5.
The operator observes the Green status light LIT, and the Red status light OFF for the 1 B1 and 1 B2 KC Pump.
The operator reads the Notes and proceeds to Step
- 6.
rOWE: (It A.~~)
.;jTlh,ereyjas;nv*j'hdjGatii~n
.tY.* ireftt l l._ntot> ** ; :l.
itatto~l,lt tQtl\\tEJ~if
,:~f Purnptrip.
l
- l.
The operator determines that loss of KC is not due to voiding or air entrainment.
The operator presses the 1KC-53B CLOSE pushbutton and observes the Green status light LIT, Red status light OFF.
Stu Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS 5
6 7
8 9
10
- 11 Page 6 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2) Check 1 KC-56A The operator observes the (KC to A NO HX) CLOSED.
1 KC-56A Green status light LIT, Red status light OFF.
(Step 3) Check 1A Train KC The operator observes the pumps - OFF.
Red status light LIT, and the Green status light OFF for the 1 A2 KC Pump and proceeds to the Step 3 RNO.
(Step 3 RNO) GO TO Step The operator proceeds to
- 5.
Step 5.
(Step 5) Check 1 B Train KC The operator observes the pumps - OFF.
Green status light LIT, and the Red status light OFF for the 1 B1 and 1 B2 KC Pump.
(Notes prior to Step 6)
The operator reads the Voiding of 1 B train KC may Notes and proceeds to Step be suspected if any of the following have occurred:
- 6.
1 B train KC pumps were CUE: (If Asked) tripped due to cavitation or air entrainment.
There was no indication 1A train KC pumps were of air entrainment or tripped due to cavitation or cavitation prior to the 1A1 air entrainment while B train KC Pump trip.
was still cross-tied to A train.
(Step 6) IF voiding of 1 B The operator determines train KC is suspected, that loss of KC is not due to THEN........
voiding or air entrainment.
(Step 7) Close the following:
The operator presses the (Step 7.a) 1 KC-53B (Trn B 1KC-53B CLOSE pushbutton and observes Aux Bldg Non Ess Sup Isol) the Green status light LIT, Red status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS
- 12 13 14
- 15 16
- 17 18 Page 7 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 7) Close the following:
The operator presses the (Step 7.b) 1 KC-2B (Trn B 1 KC-2B CLOSE pushbutton and observes the Green Aux Bldg Non Ess Ret Isol) status light LIT, Red status light OFF.
(Step 7) Close the following:
The operator observes the (Step 7.c) 1 KC-228B (Trn B 1 KC-228B Green status light LIT, Red status light Rx Bldg Non Ess Sup Isol)
OFF.
(Step 7) Close the following:
The operator observes the (Step 7.d) 1KC-18B (Trn B 1 KC-18B Green status light Rx Bldg Non Ess Ret Isol)
LIT, Red status light OFF.
(Step 8) Start 1 B RN pump.
The operator presses the 1 B RN Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
(Step 9) Ensure 1RN-187B The operator observes the (B KC HX Inlet Isol) opens.
1 RN-187B Red status light LIT, Green status light OFF.
(Step 10) Place control The operator places the switch for 1 KC-54B (Train B 1 KC-54B control switch in Recirc Isol.) in "AUTO" the vertical (Auto) position.
position.
(Step 11) Ensure 1 KC-54B The operator observes the (Train B Recirc Isol) opens.
1 KC-54B Red status light LIT, Green status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS
- 12 13 14
- 15 16
- 17 18 Page 7 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 7) Close the following:
The operator presses the (Step 7.b) 1 KC-2B (Trn B 1 KC-2B CLOSE pushbutton and observes the Green Aux Bldg Non Ess Ret Isol) status light LIT, Red status light OFF.
(Step 7) Close the following:
The operator observes the (Step 7.c) 1 KC-228B (Trn B 1 KC-228B Green status light LIT, Red status light Rx Bldg Non Ess Sup Isol)
OFF.
(Step 7) Close the following:
The operator observes the (Step 7.d) 1 KC-18B (Trn B 1 KC-18B Green status light Rx Bldg Non Ess Ret Isol)
LIT, Red status light OFF.
(Step 8) Start 1 B RN pump.
The operator presses the 1 B RN Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
(Step 9) Ensure 1RN-187B The operator observes the (B KC HX Inlet Isol) opens.
1 RN-187B Red status light LIT, Green status light OFF.
(Step 10) Place control The operator places the switch for 1 KC-54B (Train B 1 KC-54B control switch in Recirc Isol.) in "AUTO" the vertical (Auto) position.
position.
(Step 11) Ensure 1 KC-54B The operator observes the (Train B Recirc Isol) opens.
1 KC-54B Red status light LIT, Green status light OFF.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS
- 19 20
- 21 22 23 24 Page 8 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 12) Start 1B1 KC The operator presses the Pump 1 B1 KC Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
(Step 13) Check 1KC-12 Operator determines that (1 B1 KC Pump Discharge)-
1 KC-12 was not throttled LOCALL Y THROTTLED IN initially and proceeds to the STEP 6.
RNO.
(Step 13 RNO a-b) Perform The operator presses the the following:
1 B2 KC Pump START pushbutton and observes Start 1 B2 KC Pump the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
GO TO Step 17.
The operator proceeds to Step 17.
(Step 17) Check ND pumps The operator determines
- ANY ON PRIOR TO from the Initial Conditions ENTERING THIS that the ND pumps are not PROCEDURE.
on and proceeds to the RNO.
(Step 17 RNO) GO TO step The operator proceeds to
- 20.
Step 20.
(Step 20) Check KC leak -
Operator determines that HAS OCCURRED.
KC leak has not occurred and proceeds to the RNO.
Form ES-C-1 Stu COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS
- 19 20
- 21 22 23 24 Page 8 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 12) Start 1B1 KC The operator presses the Pump 1 B1 KC Pump START pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
(Step 13) Check 1KC-12 Operator determines that (1 B1 KC Pump Discharge) -
1 KC-12 was not throttled LOCALL Y THROTTLED IN initially and proceeds to the STEP 6.
RNO.
(Step 13 RNO a-b) Perform The operator presses the the following:
1 B2 KC Pump START pushbutton and observes Start 1 B2 KC Pump the Red status light LIT, Green status light OFF.
The operator observes pump motor amps, discharge pressure and flow increase.
GO TO Step 17.
The operator proceeds to Step 17.
(Step 17) Check ND pumps The operator determines
- ANY ON PRIOR TO from the Initial Conditions ENTERING THIS that the ND pumps are not PROCEDURE.
on and proceeds to the RNO.
(Step 17 RNO) GO TO step The operator proceeds to
- 20.
Step 20.
(Step 20) Check KC leak -
Operator determines that HAS OCCURRED.
KC leak has not occurred and proceeds to the RNO.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS 25
- 26 Page 9 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 20 RNO) Perform the The operator reads the Step following:
and proceeds to Step 20 (Step 20 RNO a) Limit KC RNOb.
pump flow to 4000 gpm per operating KC pump in next step.
(Step 20 RNO) Perform the following:
(Step 20 RNO b) Open the following valves:
The operator presses the 1 KC-18B (Trn B Rx Bldg 1 KC-18B OPEN pushbutton Non Ess Ret Isol) and observes the Red status light LIT, Green status light OFF.
The operator observes MCB Annunciator 1AD-10/A-1 alarm.
1 KC-228B (Trn B Rx Bldg The operator presses the Non Ess Sup Isol) 1 KC-228B OPEN pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes MCB Annunciator 1 AD-10/A-2 alarm.
The operator observes Train B flow increase to
- 1600 gpm.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS 25
- 26 Page 9 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 20 RNO) Perform the The operator reads the Step following:
and proceeds to Step 20 (Step 20 RNO a) Limit KC RNOb.
pump flow to 4000 gpm per operating KC pump in next step.
(Step 20 RNO) Perform the following:
(Step 20 RNO b) Open the following valves:
The operator presses the 1 KC-18B (Trn B Rx Bldg 1 KC-18B OPEN pushbutton Non Ess Ret Isol) and observes the Red status light LIT, Green status light OFF.
The operator observes MCB Annunciator 1 AD-10/A-1 alarm.
1 KC-228B (Trn B Rx Bldg The operator presses the Non Ess Sup Isol) 1 KC-228B OPEN pushbutton and observes the Red status light LIT, Green status light OFF.
The operator observes MCB Annunciator 1AD-10/A-2 alarm.
The operator observes Train B flow increase to
- 1600 gpm.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS
- 27
- 28 Page 10 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 20 RNO) Perform the following:
(Step 20 RNO c) Close the following valves:
The operator presses the 1 KC-230A (Trn A Rx Bldg 1 KC-230A CLOSE Non Ess Sup Isol) pushbutton and observes the Green status light LIT, Red status light OFF.
The operator observes MCB Annunciators 1 AD-16/A-1 through A-4 alarm.
The operator presses the 1 KC-3A (Trn A Rx Bldg Non 1 KC-3A CLOSE pushbutton Ess Ret Isol) and observes the Green status light LIT, Red status light OFF.
The operator observes MCB Annunciators 1AD-16/D-1 through D-4 alarm intermittently.
(Step 20 RNO) Perform the following:
(Step 20 RNO d) Open the The operator presses the following valves 1 KC-2B OPEN pushbutton 1 KC-2B (Trn B Aux Bldg and observes the Red Non Ess Ret Isol.
status light LIT, Green status light OFF.
The operator presses the 1 KC-53B (Tm B Aux Bldg 1 KC-53B OPEN pushbutton Non Ess Sup Isol).
and observes the Red status light LIT, Green status light OFF.
The operator observes Train B flow increase to
==3500 gpm.
(Step 20 RNO e) GO TO The operator proceeds to Step 25.
Step 25.
Form ES-C-1 StU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS
- 27
- 28 Page 10 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 20 RNO) Perform the following:
(Step 20 RNO c) Close the following valves:
The operator presses the 1 KC-230A (Trn A Rx Bldg 1 KC-230A CLOSE Non Ess Sup Isol) pushbutton and observes the Green status light LIT, Red status light OFF.
The operator observes MCB Annunciators 1AD-16/A-1 through A-4 alarm.
The operator presses the 1 KC-3A (Trn A Rx Bldg Non 1 KC-3A CLOSE pushbutton Ess Ret Isol) and observes the Green status light LIT, Red status light OFF.
The operator observes MCB Annunciators 1AD-16/D-1 through D-4 alarm intermittently.
(Step 20 RNO) Perform the following:
(Step 20 RNO d) Open the The operator presses the following valves 1 KC-2B OPEN pushbutton 1 KC-2B (Trn B Aux Bldg and observes the Red Non Ess Ret Isol.
status light LIT, Green status light OFF.
The operator presses the 1 KC-53B (Trn B Aux Bldg 1 KC-53B OPEN pushbutton Non Ess Sup Isol).
and observes the Red status light LIT, Green status light OFF.
The operator observes Train B flow increase to
=3500 gpm.
(Step 20 RNO e) GO TO The operator proceeds to Step 25.
Step 25.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS 29 30
- 31 32
- 33 34 35 Page 11 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 25) Check 1A ND The operator observes the pump - OFF 1 A ND Pump Green status light LIT, Red status light OFF.
(Step 26) Check 1 KC-56A The operator observes the (KC to ND HX) - CLOSED 1 KC-56A Green status light LIT, Red status light OFF.
(Step 27) Place control The operator rotates the switch for 1 KC-51A (Train A 1 KC-51A control switch Recirc Isol) in the "CLOSE" counter-clockwise to position.
CLOSE.
(Step 28) Ensure 1KC~51A The operator observes the (Train A Recirc Isol) closes.
1 KC-51A Green status light LIT, Red status light OFF.
(Step 29) Stop 1A1 and 1A2 The operator observes the pumps.
1 A 1 KC Green status light LIT, Red status light OFF.
The operator presses the 1 A2 KC Pump STOP pushbutton and observes the Green status light LIT, Red status light OFF.
(Step 30) Check KC flow-The operator observes LESS THAN 4000 GPM Train B flow to be 4900 gpm PER OPERATING KC and determines flow to be <
PUMP.
4000 gpm per KC Pump.
(Step 31) Check ND pumps The operator determines
- ANY ON PRIOR TO ND Train A is not in ENTERING THIS operation and goes to the PROCEDURE.
RNa.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS 29 30
- 31 32
- 33 34 35 Page 11 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 25) Check 1A ND The operator observes the pump - OFF 1A ND Pump Green status light LIT, Red status light OFF.
(Step 26) Check 1 KC-56A The operator observes the (KC to ND HX) - CLOSED 1 KC-56A Green status light LIT, Red status light OFF.
(Step 27) Place control The operator rotates the switch for 1KC-51A (Train A 1 KC-51A control switch Recirc Isol) in the "CLOSE" counter-clockwise to position.
CLOSE.
(Step 28) Ensure 1 KC~51A The operator observes the (Train A Recirc Isol) closes.
1 KC-51 A Green status light LIT, Red status light OFF.
(Step 29) Stop 1A 1 and 1A2 The operator observes the pumps.
1 A 1 KC Green status light LIT, Red status light OFF.
The operator presses the 1 A2 KC Pump STOP pushbutton and observes the Green status light LIT, Red status light OFF.
(Step 30) Check KC flow -
The operator observes LESS THAN 4000 GPM Train B flow to be 4900 gpm PER OPERATING KC and determines flow to be <
PUMP.
4000 gpm per KC Pump.
(Step 31) Check ND pumps The operator determines
- ANY ON PRIOR TO ND Train A is not in ENTERING THIS operation and goes to the PROCEDURE.
RNO.
Form ES-C-1 Stu COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS 36 37 38 39 40 Page 12 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 31 RNO) GO TO Step The operator proceeds to
- 37.
Step 37.
(Step 37) Check KC System The operator determines leak - HAS OCCURRED.
KC leak has not occurred and proceeds to the RNO.
(Step 37 RNO) GO TO Step The operator informs the 41 in body of this CRSRO that Enclosure 5 procedure.
has been completed.
(Step 41) Check any The operator observes that letdown path - IN SERVICE.
normal letdown is in service.
(Step 42) Check NC pump thermal barrier valves -
OPEN:
1 KC-394A (A NC Pump The operator observes the 1 KC-394A Red status light Therm Bar Otlt)
LIT, Green status light OFF.
1 KC-345A (C NC Pump The operator observes the 1 KC-345A Red status light Therm Bar Otlt)
LIT, Green status light OFF.
1 KC-364B (B NC Pump The operator observes the 1 KC-364B Red status light Therm Bar Otlt)
LIT, Green status light OFF.
1 KC-413B (D NC Pump The operator observes the 1 KC-413B Red status light Therm Bar Otlt).
LIT, Green status light OFF.
"Oue;<<F"" "'~
/
,, ~,"
,1(4UV:.lvEis a~OPEN,
'Ati~th~rQperatorwill
';y~ontin.e*,w,it~,t~i$
',:~~;(J:;<; *..
- .JpJlVI.f,f. NOT, contiliue tb inexfstep.
Form ES-C-1 StU COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS 36 37 38 39 40 Page 12 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 31 RNO) GO TO Step The operator proceeds to
- 37.
Step 37.
(Step 37) Check KC System The operator determines leak - HAS OCCURRED.
KC leak has not occurred and proceeds to the RNO.
(Step 37 RNO) GO TO Step The operator informs the 41 in body of this CRSRO that Enclosure 5 procedure.
has been completed.
(Step 41) Check any The operator observes that letdown path - IN SERVICE.
normal letdown is in service.
(Step 42) Check NC pump thermal barrier valves -
OPEN:
1 KC-394A (A NC Pump The operator observes the 1 KC-394A Red status light Therm Bar Otlt)
LIT, Green status light OFF.
1 KC-345A (C NC Pump The operator observes the 1 KC-345A Red status light Therm Bar Otlt)
LIT, Green status light OFF.
1 KC-364B (B NC Pump The operator observes the 1 KC-364B Red status light Therm Bar Otlt)
LIT, Green status light OFF.
The operator observes the 1KC-413B (0 NC Pump 1 KC-413B Red status light Therm Bar Otlt).
LIT, Green status light OFF.
Cue:
If all valves are OPEN, Another operator will continue with this procedure, AND Terminate JPM. If NOT, continue to next step.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C STEPS
- 41 Page 13 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 42 RNO) Open valves For any closed Thermal unless required closed to Barrier Outlet isolation isolate leak.
Valve, the operator presses the OPEN pushbutton and observes the Red status light LIT, Green status light OFF.
¢UE~:;
~s< ',:,
- .(,t6~f~~~~ra~()r wIll
- ,~yttinu~ w;il1this
'praqed~n*e.. "
- ~
- : ",:>:,'
)';I, h'"
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C STEPS
- 41 Page 13 of 15 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 42 RNO) Open valves For any closed Thermal unless required closed to Barrier Outlet isolation isolate leak.
Valve, the operator presses the OPEN pushbutton and observes the Red status light LIT, Green status light OFF.
CUE:
Another operator will continue with this procedure.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C Page 14 of 15 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM H Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM H NUREG 1021, Revision 9 Appendix C Page 14 of 15 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - Control Room JPM H Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
Form ES-C-1 2009 Systems - Control Room JPM H NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 is operating at 100% power with "A" train RN and KC in service.
1 A 1 KC pump has tripped on overcurrent and will not restart.
The crew has completed AP/1/A/5500/21 (Loss of KC or KC System Leakage) through subsequent step 8.
The CRSRO has directed you to start the standby KC train starting with Step 9 of AP/1/A/5500/21.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 is operating at 100% power with "A" train RN and KC in service.
1A1 KC pump has tripped on overcurrent and will not restart.
The crew has completed AP/1/A/5500/21 (Loss of KC or KC System Leakage) through subsequent step 8.
The CRSRO has directed you to start the standby KC train starting with Step 9 of AP/1/A/5500/21.
NUREG 1021, Revision 9
Appendix C Page 1 of 7 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM I 2009 Systems -In-Plant JPM I NUREG 1021, Revision 9 Appendix C Page 1 of 7 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM I 2009 Systems - In-Plant JPM I NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 7 PERFORMANCE INFORMATION Task No.:
MO-5022 Form ES-C-1 Task
Title:
Reset Unit 2 Turbine Driven CA Pump Stop Valve per Generic 4 JPM No.:
2009 Systems -In-Plant JPM I KIA
Reference:
APE 054, EA2.05, 3.5/3.7 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant x
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The 2SA-3 (Unit 2 TD CA Pump Turb Stop Valve) is reset and open.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
EP/2/A/5000/G-1, Generic Enclosures, Enclosure 24, Resetting TD CA Stop Valve.
Handouts:
EP/2/A/5000/G-1, Generic Enclosures, Enclosure 24, Resetting TD CA Stop Valve.
2009 Systems - In-Plant JPM I NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 7 PERFORMANCE INFORMATION Task No.:
MO-5022 Form ES-C-1 Task
Title:
Reset Unit 2 Turbine Driven CA Pump Stop Valve per Generic 4 JPM No.:
2009 Systems - In-Plant JPM I KIA
Reference:
APE 054, EA2.05, 3.5/3.7 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant x
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The 2SA-3 (Unit 2 TO CA Pump Turb Stop Valve) is reset and open.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
EP/2/A/5000/G-1, Generic Enclosures, Enclosure 24, Resetting TO CA Stop Valve.
Handouts:
EP/2/A/5000/G-1, Generic Enclosures, Enclosure 24, Resetting TO CA Stop Valve.
2009 Systems - In-Plant JPM I NUREG 1021, Revision 9
Appendix C Time Critical Task:
NO Validation Time:
10 minutes 2009 Systems - In-Plant JPM I Page 3 of 7 PERFORMANCE INFORMATION Form ES-C-1 NUREG 1021, Revision 9 Appendix C Time Critical Task:
NO Validation Time:
10 minutes 2009 Systems - In-Plant JPM I Page 3 of 7 PERFORMANCE INFORMATION Form ES-C-1 NUREG 1021, Revision 9
Appendix C Page 4 of 7 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/2/Al5000/G-1, Generic Enclosures, Enclosure 24, Resetting TO CA Stop Valve.
START TIME:
STEPS
- 1
- 2 ELEMENTS (Step 1) Turn handwheel clockwise to allow mechanical linkage to reconnect.
- 2) Reconnect mechanical linkage by pulling mechanical linkage toward Valve Trip Mechanism and slowly release while ensuring the following connections:
(Step 2.a) At Valve Trip Mechanism: (See Figure below)
Trip Hook is fully engaged with Latch-up Lever.
2009 Systems - In-Plant JPM I STANDARD The operator turns handwheel clockwise.
The operator looks at the mechanical Linkage.
Stu COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C Page 4 of 7 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout EP/2/AlSOOO/G-1, Generic Enclosures, Enclosure 24, Resetting TO CA Stop Valve.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT
- 1 (Step 1) Turn handwheel The operator turns clockwise to allow handwheel clockwise.
mechanical linkage to reconnect.
Cue:
Handwheel rotated clockwise, stem is in.
- 2 (Step 2) Reconnect The operator looks at the mechanical linkage by mechanical Linkage.
pulling mechanical linkage toward Valve Trip Cue:
Mechanism and slowly release while ensuring The Linkage is NOT the following connections:
connected.
The operator pulls the mechanical linkage toward the Valve Trip Mechanism and slowly releases.
Cue:
The mechanical linkage pulled toward Valve Trip Mechanism and is slowly released.
The operator observes the (Step 2.a) At Valve Trip Valve Trip Mechanism figure.
Mechanism: (See Figure below)
Cue:
Trip Hook is fully engaged Trip Hook is fully engaged with Latch-up Lever.
with Latch-up Lever.
2009 Systems - In-Plant JPM I NUREG 1021, Revision 9
Appendix C STEPS
- 3
- 4
- 5 Page 5 of 7 PERFORMANCE INFORMATION ELEMENTS (Step 2.b) At Overspeed Trip Mechanism: (See Figure below)
Tappet nut lays flat against Overspeed Trip Mechanism housing.
Head Lever is vertical.
(Step 3) Slowly turn handwheel counterclockwise to open stop valve while it is reset.
{Step 4) WHEN handwheel reaches full open, position valve 114 turn from open backseat to prevent thermal binding.
STANDARD The operator observes the Overspeed Trip Mechanism figure.
Cue:
Tappet nut is laying flat against Overspeed Trip Mechanism hOl.lsing,AND the Head lever is vertical.
The operator rotates the handwheel in the counter-clockwise direction.
Cue:
The handwheel rotates,and then stops.
The operator rotates the handwheel in the clockwise direction ~ turn.
Cue:
The handwheel rotates until stopped.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
SIU Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM I NUREG 1021, Revision 9 Appendix C STEPS
- 3
- 4
- 5 Page 5 of 7 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.b) At Overspeed The operator observes the Trip Mechanism: (See Overspeed Trip Mechanism Figure below) figure.
Tappet nut lays flat against Cue:
Overs peed Trip Mechanism housing.
Tappet nut is laying flat against Overs peed Trip Head Lever is vertical.
Mechanism housing, AND the Head lever is vertical.
(Step 3) Slowly turn The operator rotates the handwheel handwheel in the counter-counterclockwise to open clockwise direction.
stop valve while it is reset.
Cue:
The handwheel rotates, and then stops.
{Step 4) WHEN handwheel The operator rotates the reaches full open, position handwheel in the clockwise valve 114 turn direction 1;4 turn.
from open backseat to prevent thermal binding.
Cue:
The handwheel rotates until stopped.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM I NUREG 1021, Revision 9
Appendix C Page 6 of 7 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - In-Plant JPM I Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Form ES-C-1 Examiner's Signature:
Date:
--~-------------------------
2009 Systems - In-Plant JPM I NUREG 1021, Revision 9 Appendix C Page 6 of 7 VERIFICATION OF COMPLETION Form ES-C-1 Job Performance Measure No.:
2009 Systems - In-Plant JPM I Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
2009 Systems - In-Plant JPM I NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET The Unit 2 reactor has tripped due to a loss of all offsite power.
2ETA and 2ETB are deenergized.
The crew has entered EP/2/A/5000/ECA-0.0, "LOSS OF ALL AC POWER" While performing Step 7, the RO notices the "TO CA PUMP STOP VLV NOT OPEN" alarm (2AD-5, F-3) is lit.
The CRSRO dispatches you to reset the U-2 TO CA stop valve PER EP/2/A/5000/G-1, "Generic Enclosures," Enclosure 24, "Resetting TO CA Stop Valve."
NOTE: No plant equipment should be operated during the performance ofthis JPM. All actions must be SIMULATED.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET The Unit 2 reactor has tripped due to a loss of all offsite power.
2ETA and 2ETB are deenergized.
The crew has entered EP/2/A/5000/ECA-0.0, "LOSS OF ALL AC POWER" While performing Step 7, the RO notices the "TO CA PUMP STOP VLV NOT OPEN" alarm (2AD-5, F-3) is lit.
The CRSRO dispatches you to reset the U-2 TO CA stop valve PER EP/2/A/5000/G-1, "Generic Enclosures," Enclosure 24, "Resetting TO CA Stop Valve."
NOTE: No plant equipment should be operated during the performance of this JPM. All actions must be SIMULATED.
NUREG 1021, Revision 9
Appendix C Page 1 of 12 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM J 2009 Systems -In-Plant JPM J NUREG 1021, Revision 9 Appendix C Page 1 of 12 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM J 2009 Systems -In-Plant JPM J NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 12 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Aligning Nitrogen To Supply Control JPM No.:
2009 Systems -In-Air to D, E and F VI Compressors Plant JPM J KIA
Reference:
APE 065, AK3.08, 3.7/3.9 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant x
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator aligns Nitrogen from backup cylinders to D, E, and F VI compressors with pressure set between 90-100 psig.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
AP/1/A/5500/22, Loss of VI 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 12 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Aligning Nitrogen To Supply Control JPM No.:
2009 Systems - In-Air to D, E and F VI Compressors Plant JPM J KIA
Reference:
APE 065, AK3.08, 3.7/3.9 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant X
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator aligns Nitrogen from backup cylinders to D, E, and F VI compressors with pressure set between 90-100 psig.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
AP/1/A/5500/22, Loss of VI 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C Handouts:
Time Critical Task:
Validation Time:
Notes:
Page 3 of 12 PERFORMANCE INFORMATION Form ES-C-1 AP/1/N5500/22, Loss of VI, Enclosure 6, D, E and F VI Compressor Operation With Low Control Air.
NO 15 minutes Several valves that need to be operated during this JPM require the use of a ladder. If asked, cue the operator that they may assume ladders are available; however, they should not climb during performance of the JPM.
2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C Handouts:
Time Critical Task:
Validation Time:
Notes:
Page 3 of 12 PERFORMANCE INFORMATION Form ES-C-1 AP/1/A/5500/22, Loss of VI, Enclosure 6, 0, E and F VI Compressor Operation With Low Control Air.
NO 15 minutes Several valves that need to be operated during this JPM require the use of a ladder. If asked, cue the operator that they may assume ladders are available; however, they should not climb during performance of the JPM.
2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C Page 4 of 12 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/Al5500/22, Loss of VI, Enclosure 6 after operator identifies enclosure satellite copy in Service Bldg. Basement at Station Lube Oil House.
NOTE: If operator requests copy of enclosure 6, inform them to use satellite copy.
START TIME:
STEPS 1
2 ELEMENTS (Step 1) Check VI pressure as read on OVIPT5090 (VI Dryer Outlet Hdr Press)
(Unit 2 T6, 739, column 2N-
- 32) - LESS THAN 70 PSIG.
(Step 2) Check KR in service as follows:
STANDARD After the cue, the operator observes VI Header Pressure on OVIPT5090 to be 15 psig.
The operator checks local KR pump indications.
Stu COMMENTS REQUIRED FOR UNSAT Any KR pump - RUNNING Cue:
3 KR pump discharge pressure - GREATER THAN 50 PSIG.
(Step 3) heck D, E, and F VI compressors - ALL OFF 2009 Systems - In-Plant JPM J
&f8\\rlJttG KR pUfllP',are***
flllIfitning.
The operator determines from initial conditions that D, E and F VI compressors are NOT running.
NUREG 1021, Revision 9 Appendix C Page 4 of 12 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/Al5500/22, Loss of VI, Enclosure 6 after operator identifies enclosure satellite copy in Service Bldg. Basement at Station Lube Oil House.
NOTE: If operator requests copy of enclosure 6, inform them to use satellite copy.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Step 1) Check VI pressure After the cue, the operator as read on OVIPT5090 (VI observes VI Header Dryer Outlet Hdr Press)
Pressure on OVIPT5090 to (Unit 2 TB, 739, column 2N-be 15 psig.
- 32) - LESS THAN 70 PSIG.
Cue:
Gage is indicating 15 psig.
2 (Step 2) Check KR in The operator checks local service as follows:
KR pump indications.
Any KR pump - RUNNING Cue:
Band C KR pumps are running.
KR pump discharge Cue:
pressure - GREATER THAN 50 PSIG.
Both gauges read 75 psig.
3 (Step 3) Check D, E, and F The operator determines VI compressors - ALL OFF from initial conditions that D, E and F VI compressors are NOT running.
2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C Page 5 of 12 Form ES-C-1 PERFORMANCE INFORMATION STEPS ELEMENTS 4
(Note prior to Step 4) Steps 4 through 19 align VB to the control air header for D, E, and F VI compressors to ensure proper operation.
5 (Step 4) Check VB compressor - RUNNING
- 6 tep 4 RNO alb) Perform the following:
Depress "START" on both VB compressors IF both VB compressors still off, THEN GO TO Step 20.
2009 Systems - In-Plant JPM J STANDARD The operator reads the Note and proceeds to Step
- 4.
The operator observes that neither VB compressor is running.
The operator presses the START pushbutton for the A VB Compressor.
The operator presses the START pushbutton for the B VB Compressor.
The operator proceeds to step 20.
SIU COMMENTS REQUIRED FOR UNSAT NUREG 1021, Revision 9 Appendix C STEPS 4
5
- 6 Page 5 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Note prior to Step 4) Steps The operator reads the 4 through 19 align VB to the Note and proceeds to Step control air header for D, E,
- 4.
and F VI compressors to ensure proper operation.
(Step 4) Check VB The operator observes that compressor - RUNNING neither VB compressor is running.
Cue:
Both Breathing Air (VB)
Compressors are OFF.
(Step 4 RNO a/b) Perform the following:
The operator presses the Depress "START" on both START pushbutton for the VB compressors A VB Compressor.
Cue:
The A VB Compressor remains OFF.
The operator presses the START pushbutton for the B VB Compressor.
Cue:
The B VB Compressor remains OFF.
IF both VB compressors still The operator proceeds to off, THEN GO TO Step 20.
step 20.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C STEPS 7
8 9
10
- 11 Page 6 of 12 PERFORMANCE INFORMATION ELEMENTS (Step 20) Check D, E, and F VI compressors - ALL OFF.
(Step 21) Observe notes prior to Step 26 and GO TO Step 26.
(Notes prior to Step 26)
Subsequent steps use nitrogen cylinders as control air for VI compressors.
Two nitrogen cylinders are installed in the service bldg, 739, column U-30.
(Step 26) Dispatch maintenance personnel or another operator to bring two additional 225 cubic feet nitrogen cylinders to service bldg, 739, column U-30 in case extra cylinders are needed.
(Step 27/27.a) Align nitrogen cylinders (located in service bldg, 739, column U-30) to supply control air to D, E, and F VI compressors as follows:
Close "F VI COMPRESSOR VORTEX COOLER ISOLATION" valve (located on top of F VI compressor microcontroller panel).
STANDARD The operator determines from initial conditions that D, E and F VI compressors are NOT running.
The operator proceeds to Notes prior to Step 26.
The operator reads the Notes and proceeds to Step
- 26.
The operator contacts maintenance to obtain additional Nitrogen.
eve:
Maintenance has been dispatched, The operator rotates the "F COOLER ISOLATION" valve handle clockwise 90°.
C.ue:....
Th~h~irl~le:js p(;Jrpendicularto pipe flow.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C STEPS 7
8 9
10
- 11 Page 6 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 20) Check D, E, and The operator determines F VI compressors - ALL from initial conditions that OFF.
D, E and F VI compressors are NOT running.
(Step 21) Observe notes The operator proceeds to prior to Step 26 and GO TO Notes prior to Step 26.
Step 26.
(Notes prior to Step 26)
The operator reads the Subsequent steps use Notes and proceeds to Step nitrogen cylinders as control
- 26.
air for VI compressors.
Two nitrogen cylinders are installed in the service bldg, 739, column U-30.
(Step 26) Dispatch The operator contacts maintenance personnel or maintenance to obtain another operator to bring additional Nitrogen.
two additional 225 cubic feet nitrogen cylinders to Cue:
service bldg, 739, column U-30 in case extra cylinders Maintenance has been are needed.
dispatched.
(Step 27/27.a) Align The operator rotates the "F nitrogen cylinders (located COOLER ISOLATION" in service bldg, 739, column valve handle clockwise 90 0
U-30) to supply control air to D, E, and F VI Cue:
compressors as follows:
The handle is Close "F VI COMPRESSOR perpendicular to pipe VORTEX COOLER flow.
ISOLATION" valve (located on top of F VI compressor microcontroller panel).
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C STEPS
- 12
- 13
- 14 ELEMENTS Page 7 of 12 PERFORMANCE INFORMATION STANDARD The operator rotates 1 VI-837 valve handwheel clockwise.
(Step 27.b) Close 1VI-837 (Alternate VI Control Air Supply to D/E/F VI Compressors) (service bldg, 739+8, between col Q-30 r-~-----~~---~~
and F VI Compressor).
(Step 27.c) Close "0 VI C8MPRESSOR VORTEX COOLER ISOLATION" valve (located on top of 0 VI compressor microcontroller panel).
(Step 27.d) Close "E VI COMPRESSOR VORTEX COOLER ISOLATION" Cue:
The handwheel rotates clockwise, and THEN stops.
The operator rotates the "0 COOLER ISOLATION" valve handle clockwise 90°.
Cue:
I The *. handleis perpendic~lar to pipe flOW.}
The operator rotates the "E COOLER ISOLATION" valve handle clockwise 90°.
valve (located on top of E VI I----------------,.-J compressor microcontroller Cue:
panel).
The handle Is perpendicular to pipe flow.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C STEPS
- 12
- 13
- 14 Page 7 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 27.b) Close 1VI-837 The operator rotates 1 VI-(Alternate VI Control Air 837 valve handwheel Supply to D/E/F VI clockwise.
Compressors) (service bldg, 739+8, between col Q-30 Cue:
and F VI Compressor).
The handwheel rotates clockwise, and THEN stops.
(Step 27.c) Close "0 VI The operator rotates the "0 C8MPRESSOR VORTEX COOLER ISOLATION" COOLER ISOLATION" valve handle clockwise 90 0
valve (located on top of 0 VI compressor Cue:
microcontroller panel).
The handle is perpendicular to pipe flow.
(Step 27.d) Close "E VI The operator rotates the "E COMPRESSOR VORTEX COOLER ISOLATION" COOLER ISOLATION" valve handle clockwise 90 0
valve (located on top of E VI compressor microcontroller Cue:
panel).
The handle is perpendicular to pipe flow.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C STEPS
- 15
- 16
- 17
- 18 Page 8 of 12 PERFORMANCE INFORMATION ELEMENTS (Step 27.e) Unlock and close 1 VI-842 (Normal VI Control Air Supply to VI Compressors D, E, and F)
(service bldg, 739, U-30, west side of column).
(Step 27.f) Open 1VI-843 (VI Backup Compressed Nitrogen Cylinders Isol)
(service bldg, 739, U-30, west side of column).
(Step 27.g) Ensure pressure regulating knob on 1 VI-57 4 (VI Nitrogen Cylinder Pressure Regulator) (service bldg, 739, at column U-30) turned fully counterclockwise.
(Step 27.h) Open isolation valve on top of each nitrogen cylinder.
STANDARD The operator removes the lock and rotates 1 VI-842 valve handwheel clockwise.
Cue:
The handwheel rotates clockwise, and THEN stops.
The operator rotates 1 VI-843 valve handwheel counter-clockwise.
Cue:
The handwheel rotates counter-clockWise, and THIiNstops.
The operator rotates the 1 VI-57 4 regulator knob fully counter-clockwise.
Cue:
The knob rotates counter-clockwise, and THEN stops.
The operator rotates the Nitrogen Cylinder valve handwheel fully counter-clockwise.
I Cue:
The valve handwheel rotates counter-clockwise,and TH EN I stops.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C STEPS
- 15
- 16
- 17
- 18 Page 8 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 27.e) Unlock and The operator removes the close 1VI-842 (Normal VI lock and rotates 1 VI-842 Control Air Supply to VI valve handwheel clockwise.
Compressors D, E, and F)
(service bldg, 739, U-30, Cue:
west side of column).
The handwheel rotates clockwise, and THEN stops.
(Step 27.f) Open 1 VI-843 The operator rotates 1 VI-(VI Backup Compressed 843 valve handwheel Nitrogen Cylinders Isol) cou nter -clockwise.
(service bldg, 739, U-30, west side of column).
Cue:
The handwheel rotates counter-clockwise, and THEN stops.
(Step 27.g) Ensure The operator rotates the pressure regulating knob on 1 VI-57 4 regulator knob fully 1 VI-57 4 (VI Nitrogen counter-clockwise.
Cylinder Pressure Regulator) (service bldg, Cue:
739, at column U-30) turned fully counterclockwise.
The knob rotates counter-clockwise, and THEN stops.
(Step 27.h) Open isolation The operator rotates the valve on top of each Nitrogen Cylinder valve nitrogen cylinder.
handwheel fully counter-clockwise.
Cue:
The valve handwheel rotates counter-clockwise, and THEN stops.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C STEPS
- 19
- 20 Page 9 of 12 PERFORMANCE INFORMATION ELEMENTS (Step 27.i) Open the following:
1 VI-572 (VI Nitrogen Cylinder Isolation) (service bldg, 739, at column U-30).
1VI-573 (VI Nitrogen Cylinder Isolation) (service bldg, 739, at column U-30).
(Step 27.j) Turn regu ng knob on 1VI-574 (VI Nitrogen Cylinder Pressure Regulator) (service bldg, 739, at column U-30) clockwise to obtain 90-100 PSIG outlet pressure.
STANDARD The operator rotates the "1VI-572" valve handle counter-clockwise 90°.
The operator rotates the "1VI-573" valve handle counter-clockwise 90°.
The operator rotates the 1VI-574 regulator knob clockwise.
The operator observes pressure between 90-100 psig and stops rotating the 1VI-574 regulator knob.
The outlet pressure is 98 psig.
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems -In-Plant JPM J NUREG 1021, Revision 9 Appendix C STEPS
- 19
- 20 Page 9 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 27.i) Open the The operator rotates the following:
"1VI-572" valve handle counter-clockwise 90°.
1 VI-572 (VI Nitrogen Cylinder Isolation) (service Cue:
bldg, 739, at column U-30).
The handle is in-line with pipe flow.
1 VI-573 (VI Nitrogen The operator rotates the Cylinder Isolation) (service "1 VI-573" valve handle bldg, 739, at column U-30).
counter-clockwise 90°.
Cue:
The handle is in-line with pipe flow.
(Step 27.j) Turn regulating The operator rotates the knob on 1 VI-574 (VI 1 VI-57 4 regulator knob Nitrogen Cylinder Pressure clockwise.
Regulator) (service bldg, 739, at column U-30)
Cue:
clockwise to obtain 90-100 PSIG outlet pressure.
The knob rotates clockwise.
The operator observes pressure between 90-100 psig and stops rotating the 1 VI-57 4 regulator knob.
Cue:
The outlet pressure is 98 psig.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C STEPS 21 22 23 Page 10 of 12 PERFORMANCE INFORMATION ELEMENTS (Caution prior to Step 27.k)
Compressor trip may occur if 1 VI-574 outlet pressure goes below 70 PSIG.
(Step 27.
Periodically ensure 1 VI-57 4 is maintaining 90-100 PSIG outlet pressure.
(Step 28)Check D VI compressor - AVAILABLE TO START.
STANDARD The operator reads the Caution and proceeds to Step 27.k.
The operator ensures 1 VI-574 is maintaining 90-100 PSIG outlet pressure.
Another Operator will complete this enclosure.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Stu Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9 Appendix C STEPS 21 22 23 Page 10 of 12 PERFORMANCE INFORMATION ELEMENTS STANDARD (Caution prior to Step 27.k)
The operator reads the Compressor trip may occur Caution and proceeds to if 1 VI-574 outlet pressure Step 27.k.
goes below 70 PSIG.
(Step 27.k) Periodically The operator ensures 1 VI-ensure 1VI-574 is 574 is maintaining 90-100 maintaining 90-100 PSIG PSIG outlet pressure.
outlet pressure.
Cue:
The outlet pressure is 98 psig.
(Step 28)Check D VI CUE:
compressor - AVAILABLE TO START.
Another Operator will complete this enclosure.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C Page 11 of 12 VERIFICATION OF COMPLETION Form ES-C-1 Job Performance Measure No.:
2009 Systems - In-Plant JPM J Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
2009 Systems -In-Plant JPM J NUREG 1021, Revision 9 Appendix C Page 11 of 12 VERIFICATION OF COMPLETION Form ES-C-1 Job Performance Measure No.:
2009 Systems - In-Plant JPM J Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
2009 Systems - In-Plant JPM J NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A flexible coupling rupture on the Instrument Air System Header has caused all Instrument Air Compressors previously in service to trip.
AP/1/A/5500/22 (Loss of VI) has been implemented.
The C/R SRO has dispatched you to locally check the Air Compressors.
You discover that D, E, and F Compressors have all tripped off and report this to the Control Room.
The C/R SRO checks Instrument Air header pressure and discovers that pressure is less that 20 PSIG.
A, B, and C VI Compressors are all out of service for a major mod ification.
The CRSRO directs you to perform AP/1/A/5500/22, Loss of VI,, D, E, and F VI Compressor Operation With Low Control Air.
NOTE: No plant equipment should be operated during the performance of this JPM. All actions must be SIMULATED.
NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET A flexible coupling rupture on the Instrument Air System Header has caused all Instrument Air Compressors previously in service to trip.
AP/1/A/5500/22 (Loss of VI) has been implemented.
The C/R SRO has dispatched you to locally check the Air Com pressors.
You discover that 0, E, and F Compressors have all tripped off and report this to the Control Room.
The C/R SRO checks Instrument Air header pressure and discovers that pressure is less that 20 PSIG.
A, B, and C VI Compressors are all out of service for a major modification.
The CRSRO directs you to perform AP/1/A/5500/22, Loss of VI,, 0, E, and F VI Compressor Operation With Low Control Air.
NOTE: No plant equipment should be operated during the performance of this JPM. All actions must be SIMULATED.
NUREG 1021, Revision 9
Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM K 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C Page 1 of 11 PERFORMANCE INFORMATION Form ES-C-1 In-Plant JPM K 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Swap Battery Charger EVCA Power JPM No.:
2009 Systems -In-Supply from Unit 1 to Unit 2 Plant JPM K KIA
Reference:
APE 058, AK3.02, 4.0/4.2 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant X
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator aligns power to Battery Charger EVCA from Unit 2 within 20 minutes of dispatch.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
AP/1/A/5500/07, Loss of Electrical Power Handouts:
AP/1/N5500/07, Loss of Electrical Power, Enclosure 22, Swapping Battery Charger Power Supplies.
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C Facility:
McGuire Page 2 of 11 PERFORMANCE INFORMATION Task No.:
Form ES-C-1 Task
Title:
Swap Battery Charger EVCA Power JPM No.:
2009 Systems -In-Supply from Unit 1 to Unit 2 Plant JPM K KIA
Reference:
APE 058, AK3.02, 4.0/4.2 Examinee:
NRC Examiner:
Facility Evaluator:
Date:
Method of testing:
Simulated Performance:
x Actual Performance:
Classroom Simulator Plant x
READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.
Task Standard:
The operator aligns power to Battery Charger EVCA from Unit 2 within 20 minutes of dispatch.
Required Materials:
PPE (Hardhat, Safety Glasses, Hearing Protection, etc.)
General
References:
AP/1/A/550Q/07, Loss of Electrical Power Handouts:
AP/1/A/5500107, Loss of Electrical Power, Enclosure 22, Swapping Battery Charger Power Supplies.
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C Time Critical Task:
Validation Time:
Notes:
Page 3 of 11 PERFORMANCE INFORMATION YES-20 Minutes 15 minutes Form ES-C-1 Start this JPM from the hallway outside of the Ops kitchen area.
Record the Time Critical Completion Time (in step number 13) when the Charger "DC Output" Breaker is closed in.
NOTE: THIS IS A TIME CRITICAL TASK 2009 Systems ~ In-Plant JPM K NUREG 1021, Revision 9 Appendix C Time Critical Task:
Validation Time:
Notes:
Page 3 of 11 PERFORMANCE INFORMATION YES-20 Minutes 15 minutes Form ES-C-1 Start this JPM from the hallway outside of the Ops kitchen area.
Record the Time Critical Completion Time (in step number 13) when the Charger "DC Output" Breaker is closed in.
NOTE: THIS IS A TIME CRITICAL TASK 2009 Systems ~ In-Plant JPM K NUREG 1021, Revision 9
Appendix C Page 4 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/A15500/07, Loss of Electrical Power, Enclosure 22.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Caution prior to Step 1) This enclosure should be performed without delay to limit time battery is supplying DC bus.
2 (Step 1) Perform applicable section(s) as specified in The operator determines (DC Bus from initial conditions that Alignment):
Battery Charger EVCA is the desired charger and To swap power supplies to proceeds to step 2.
EVCA Battery Charger, perform Step 2.
To swap power supplies to EVCB Battery Charger, perform Step 3.
To swap power supplies to EVCC Battery Charger, perform Step 4.
To swap power supplies to EVCD Battery Charger, perform Step 5.
To swap power supplies to EVCS Battery Charger, perform one of the following:
IF 1 EMXH is aligned to EVCS, THEN swap power supplies to 1 EMXH PER Step 6.
OR IF 2EMXH is aligned to EVCS, THEN swap power supplies to 2EMXH PER Step 7.
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C Page 4 of 11 PERFORMANCE INFORMATION (Denote Critical Steps with an asterisk*)
Form ES-C-1 Provide Candidate with Initial Conditions/Cue (Last Page of this JPM), and Handout AP/1/AJ5500/07, Loss of Electrical Power, Enclosure 22.
START TIME:
STEPS ELEMENTS STANDARD S/U COMMENTS REQUIRED FOR UNSAT 1
(Caution prior to Step 1) This enclosure should be performed without delay to limit time battery is supplying DC bus.
2 (Step 1) Perform applicable section( s) as specified in The operator determines (DC Bus from initial conditions that Alignment):
Battery Charger EVCA is the desired charger and To swap power supplies to proceeds to step 2.
EVCA Battery Charger, perform Step 2.
To swap power supplies to EVCB Battery Charger, perform Step 3.
To swap power supplies to EVCC Battery Charger, perform Step 4.
To swap power supplies to EVCD Battery Charger, perform Step 5.
To swap power supplies to EVCS Battery Charger, perform one of the following:
IF 1 EMXH is aligned to EVCS, THEN swap power supplies to 1 EMXH PER Step 6.
OR IF 2EMXH is aligned to EVCS, THEN swap power supplies to 2EMXH PER Step 7.
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C STEPS 3
4 Page 5 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2/2.a) To swap power The operator determines supplies to EVCA Battery from initial conditions that Charger, perform the following:
it is desired to supply Battery Charger EVCA Determine which unit is from Unit 2, and places a desired to supply EVCA:
check mark in front of Unit
- 2.
Unit 1 OR Unit 2 (Steps 2.b.1-2) Have Control The operator determines Room perform the following:
from initial conditions that 1 ETA is NOT energized IF Unit I ETA is energized, and proceeds to step THEN.......
2.b.2.
IF Unit 2 ETA is energized, The operator contacts to THEN:
Control Room and asks if 2ETA is energized.
Cue:
2ETAis energized.
Ensure 2A DIG load The operator contacts the sequencer reset.
Control Room and directs RO to ensure 2A DIG Sequencer is reset and EVCA stop button on 2MC-8 is depressed.
Depress "STOP" for "EVCA Batt Charger" on 2MC-8.
Cue:
2AOJG sequencer is reset, AND STOP Pushbutton has been depressed~
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C STEPS 3
4 Page 5 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2/2.a) To swap power The operator determines supplies to EVCA Battery from initial conditions that Charger, perform the following:
it is desired to supply Battery Charger EVCA Determine which unit is from Unit 2, and places a desired to supply EVCA:
check mark in front of Unit
- 2.
Unit 1 OR Unit 2 (Steps 2.b.1-2) Have Control The operator determines Room perform the following:
from initial conditions that 1 ETA is NOT energized IF Unit I ETA is energized, and proceeds to step THEN.......
2.b.2.
IF Unit 2 ETA is energized, The operator contacts to THEN:
Control Room and asks if 2ETA is energized.
Cue:
2ETA is energized.
Ensure 2A DIG load The operator contacts the sequencer reset.
Control Room and directs RO to ensure 2A DIG Sequencer is reset and EVCA stop button on 2MC-8 is depressed.
Depress "STOP" for "EVCA Batt Charger" on 2MC-8.
Cue:
2A DIG sequencer is reset, AN D STOP Pushbutton has been depressed.
Form ES-C-1 SIU COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C STEPS
- 5 6
Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS (Step 2.c) Open EVCA Battery Charger "DC OUTPUT" breaker (Caution prior to Step 2.d) It may be necessary to apply pressure on the breaker rotary switch in the counterclockwise direction while operating kirk key devices.
STANDARD The operator places the EVCA Battery Charger breaker in down direction.
J,'!C'uln ';;if;':'
.-~~
¥ibt.ke]fsiridftat~'SOFF...
- ?:;~;
(,~~,
~.;
".,.~
J,:i,;
The operator reads the Caution and proceeds to Step 2.d
- 7 (Step 2.d) Open the following breakers:
ECB1-1B (Normal Inc Supply The operator opens the From MCC 1 EMXA)
Normal breaker.
ECB1-1 C (Alt Inc Supply From MCC 2EMXA)
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C STEPS
- 5 6
- 7 Page 6 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.c) Open EVCA Battery The operator places the Charger "DC OUTPUT" EVCA Battery Charger breaker breaker in down direction.
Cue:
Switch is moved in the down direction and breaker indicates OFF.
(Caution prior to Step 2.d) It The operator reads the may be necessary to apply Caution and proceeds to pressure on the breaker rotary Step 2.d switch in the counterclockwise direction while operating kirk key devices.
(Step 2.d) Open the following breakers:
ECB1-1 B (Normal Inc Supply The operator opens the From MCC 1 EMXA)
Normal breaker.
Cue:
"Normal Supply" breaker handle rotated counter clockwise to the "OFF" position.
ECB1-1C (Alt Inc Supply From The operator observes the MCC 2EMXA)
Alternate breaker.
Cue:
Breaker handle is indicating "OFF".
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C STEPS
- 8 9
- 10 Page 7 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.e) Remove kirk key The operator rotates and from breaker in step above.
removes the kirk key from breaker ECB 1-1 B.
Cue:
Kirk key rotatedimd removed.
(Step 2.n IF Unit 1 to supply The operator determines EVCA, THEN perform the from initial conditions that following......
it is NOT desired to supply power to EVCA from Unit 1 and proceeds to step 2.g.
(Step 2.g) IF Unit 2 to supply The operator inserts key EVCA, THEN perform the into the Unit 2 supply following:
breaker and closes it.
Use kirk key and close ECB1-Cue:
1 C (Alt Inc Supply From MCC 2EMXA).
Kirk Key inserted.
"Alternate Supply" breaker handle rotated clockwise to the "ON" position.
Have Unit 2 Control Room The operator contacts the operator start Battery Charger Control Room and EVCA on 2MC-8.
requests that they start the Battery Charger EVCA on 2MC-8.
Cue:
I** Unit 2. RO has started EVCABatt. Charger from 2MC*8
- Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, RevIsion 9 Appendix C STEPS
- 8 9
- 10 Page 7 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.e) Remove kirk key The operator rotates and from breaker in step above.
removes the kirk key from breaker ECB 1-1 B.
Cue:
Kirk key rotated and removed.
(Step 2.n IF Unit 1 to supply The operator determines EVCA, THEN perform the from initial conditions that following......
it is NOT desired to supply power to EVCA from Unit 1 and proceeds to step 2.g.
(Step 2.g) IF Unit 2 to supply The operator inserts key EVCA, THEN perform the into the Unit 2 supply following:
breaker and closes it.
Use kirk key and close ECB1-Cue:
1 C (Alt Inc Supply From MCC 2EMXA).
Kirk Key inserted.
"Alternate Supply" breaker handle rotated clockwise to the "ON" position.
Have Unit 2 Control Room The operator contacts the operator start Battery Charger Control Room and EVCA on 2MC-8.
requests that they start the Battery Charger EVCA on 2MC-8.
Cue:
Unit 2 RO has started EVCA Batt. Charger from 2MC-8.
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, ReVISion 9
Appendix C STEPS 11 12
- 13 Page 8 of 11 PERFORMANCE INFORMATION ELEMENTS (Step 2.h) IF EVCA battery charger DC volts are greater than or equal to 115 volts, THEN GO TO Step 2.j.
(Step 2.j) Ensure EVCA Battery Charger "FLOAT/EQUALIZE" switch in "FLOAT" position.
(Step 2.k) Close EVCA Battery Charger "DC OUTPUT" breaker STANDARD The operator checks EVCA battery charger DC output voltage.
Cue:
Charger DC output voltage is 132 volts.
The operator proceeds to Step 2.j.
The operator places the Battery Charger "FLOAT/EQUALIZE" switch in "FLOAT" position.
Cue:
Switch in "FLOAT" position. The green
" FLOAT" Hghlis illuminated.
The operator places the EVCA Battery Charger "DC OUTPUT" breaker to the UP position.
Cue:
Breaker handle has been pulled into the up
- position, S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C STEPS 11 12
- 13 Page 8 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.h) IF EVCA battery The operator checks charger DC volts are greater EVCA battery charger DC than or equal to 115 volts, output voltage.
THEN GO TO Step 2.j.
Cue:
Charger DC output voltage is 132 volts.
The operator proceeds to Step 2.j.
(Step 2.j) Ensure EVCA The operator places the Battery Charger Battery Charger "FLOAT/EQUALIZE" switch "FLOAT/EQUALIZE" in "FLOAT" position.
switch in "FLOAT" position.
Cue:
Switch in "FLOAT" position. The green "FLOAT" light is illuminated.
(Step 2.k) Close EVCA Battery The operator places the Charger "DC OUTPUT" EVCA Battery Charger breaker "DC OUTPUT" breaker to the UP position.
Cue:
Breaker handle has been pulled into the up position.
Stop Time for Time Critical Task:
-.~-.... --
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C STEPS 14 15 Page 9 of 11 PERFORMANCE INFORMATION ELEMENTS (Step 2.1) Notify Control Room that EVCA Battery Charger is running.
(Step 2.m)!E another battery charger needs to be swapped, THEN perform the applicable step as directed in Step 1.
STANDARD The operator contacts the Control Room and informs the RO that the EVCA Battery Charger is running.
- ew~'t(
....... /
!~~~*U The operator recognizes that no other battery Chargers need to be re-energized.
16 (Step 2.n) Exit this enclosure.
The operator exits the procedure.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
S/U Form ES-C-1 COMMENTS REQUIRED FOR UNSAT 2009 Systems -In-Plant JPM K NUREG 1021, Revision 9 Appendix C STEPS 14 15 16 Page 9 of 11 PERFORMANCE INFORMATION ELEMENTS STANDARD (Step 2.1) Notify Control The operator contacts Room that EVCA Battery the Control Room and Charger is running.
informs the RO that the EVCA Battery Charger is running.
Cue:
The RO acknowledges.
(Step 2.m) IF another battery The operator recognizes charger needs to be swapped, that no other battery THEN perform the applicable Chargers need to be re-step as directed in Step 1.
energized.
Cue:
No other chargers need to be swapped.
(Step 2.n) Exit this enclosure.
The operator exits the procedure.
Terminating Cue:
Evaluation on this JPM is complete.
STOP TIME:
Form ES-C-1 S/U COMMENTS REQUIRED FOR UNSAT 2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Form ES-C-1 Job Performance Measure No.:
2009 Systems - In-Plant JPM K Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Examiner's Signature:
Date:
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9 Appendix C Page 10 of 11 VERIFICATION OF COMPLETION Job Performance Measure No.:
2009 Systems - In-Plant JPM K Examinee's Name:
Date Performed:
Facility Evaluator:
Number of Attempts:
Time to Complete:
Question Documentation:
Result:
SAT UNSAT Form ES-C-1 Examiner's Signature:
Date:
2009 Systems - In-Plant JPM K NUREG 1021, Revision 9
Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 has just experienced a LOOP (Loss of Offsite Power).
The 1 A DIG will not start.
1 ETA is de-energized.
AP/1/N5500107 (Loss of Electrical Power), Case 1 has been entered.
While performing Enclosure 7 (DC Bus Alignment), the RO notices that Vital Battery Charger EVCA is de-energized.
The CRSRO directs you to swap power supplies to the EVCA Battery Charger from Unit 1 to Unit 2 in accordance with AP/1/N5500107 (Loss of Electrical Power), Enclosure 22 (Swapping Battery Charger Power Supplies).
NOTE: No plant equipment should be operated during the performance of this JPM. All actions must be SIMULATED.
NOTE: THIS IS A TIME CRITICAL TASK NUREG 1021, Revision 9 Appendix C INITIAL CONDITIONS:
INITIATING CUE:
Form ES-C-1 JPM CUE SHEET Unit 1 has just experienced a LOOP (Loss of Offsite Power).
The 1 A DIG will not start.
1 ETA is de-energized.
AP/1/A/5500107 (Loss of Electrical Power), Case 1 has been entered.
While performing Enclosure 7 (DC Bus Alignment), the RO notices that Vital Battery Charger EVCA is de-energized.
The CRSRO directs you to swap power supplies to the EVCA Battery Charger from Unit 1 to Unit 2 in accordance with AP/1/A/5500107 (Loss of Electrical Power), Enclosure 22 (Swapping Battery Charger Power Supplies).
NOTE: No plant equipment should be operated during the performance of this JPM. All actions must be SIMULATED.
NOTE: THIS IS A TIME CRITICAL TASK NUREG 1021, Revision 9