ML092400410

From kanterella
Jump to navigation Jump to search
IR 05000443-09-007; 02/25/2009-07/16/2009; Seabrook Station, Unit No. 1; Plant Modifications
ML092400410
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 08/28/2009
From: David Lew
Division Reactor Projects I
To: O'Keefe M, St.Pierre G
NextEra Energy Seabrook
burritt, AL
References
EA-09-145 IR-09-007
Download: ML092400410 (16)


See also: IR 05000443/2009007

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

475 ALLENDALE ROAD

KING OF PRUSSIA, PA 19406-1415

August 28, 2009

EA-09-145

Mr. Gene St. Pierre

Site Vice President

NextEra Energy Seabrook, LLC

Seabrook Station

c/o Mr. Michael OKeefe

P.O. Box 300

Seabrook, NH 03874

SUBJECT:

SEABROOK STATION, UNIT NO. 1 - NRC INSPECTION REPORT

05000443/2009007; PRELIMINARY WHITE FINDING

On July 16, 2009, the NRC completed an inspection at the Seabrook Station, Unit No. 1.

The enclosed report documents the inspection findings discussed during an exit meeting on

July 16, 2009, with Mr. Paul Freeman and other members of your staff.

This inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

This report documents one self-revealing finding that has preliminarily been determined to be

White, a finding with low to moderate increased importance to safety that may require additional

NRC inspections. As described in Section 1R18 of the attached report the finding is associated

with the failure to establish adequate design control measures to modify a cooling water flange

on the B emergency diesel generator (EDG), which led to the failure of the diesel during a test

on February 25, 2009. This finding was assessed based on the best available information,

using the applicable Significance Determination Process (SDP). The final resolution will be

conveyed in separate correspondence.

Following the B EDG failure on February 25, 2009, NextEra investigated the event, evaluated

the condition of the EDG and its support systems, and restored the EDG and its cooling system

to an operable status. Following completion of repairs, NextEra performed extensive

maintenance operability and reliability runs on the B EDG, and declared it operable on

March 2, 2009. This finding does not represent an immediate safety concern because of the

corrective actions you have taken.

G. St. Pierre

2

The finding is an apparent violation of NRC requirements and is being considered for escalated

enforcement action in accordance with the Enforcement Policy, which can be found on the

NRCs Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement

In accordance with the NRC Inspection Manual Chapter (IMC) 0609, we intend to complete our

evaluation using the best available information and issue our final determination of safety

significance within 90 days of the date of this letter. The significance determination process

encourages an open dialogue between the NRC staff and the licensee; however, the dialogue

should not impact the timeliness of the staffs final determination. We understand that you

continue to evaluate the results of your risk determination for the B EDG failure. We encourage

you to provide the results of your evaluation to us when it is finalized using the process as

described below.

Before we make a final decision on this matter, we are providing you with an opportunity

(1) to attend a Regulatory Conference where you can present to the NRC your perspective on

the facts and assumptions the NRC used to arrive at the finding and assess its significance, or

(2) submit your position on the finding to the NRC in writing. If you request a Regulatory

Conference, it should be held within 30 days of the date of this letter and we encourage you to

submit supporting documentation at least one week prior to the conference in an effort to make

the conference more efficient and effective. If a Regulatory Conference is held, it will be open

for public observation. If you decide to submit only a written response, such submittal should be

sent to the NRC within 30 days of the date of this letter. If you decline to request a Regulatory

Conference or submit a written response, you relinquish your right to appeal the final SDP

determination, in that by not doing either you fail to meet the appeal process outlined in the

Prerequisite and Limitation Sections of Attachment 2 of IMC 0609.

Please contact Art Burritt at 610-337-5069, and in writing, within 10 days from the issue date of

this letter to notify the NRC of your intentions. If we have not heard from you within 10 days, we

will continue with our significance determination and enforcement decision and you will be

advised of the results of our deliberations on this matter.

Because the NRC has not made a final determination in this matter, no Notice of Violation is

being issued for this inspection finding at this time. In addition, please be advised that the

number and characterization of the apparent violation may change as a result of further NRC

review. The final resolution of this finding will be conveyed in separate correspondence.

The attached report also documents one licensee-identified finding of very low safety

significance (Green) that involved a violation of NRC requirements (Section 4OA7). If you

contest this violation, you should provide a response within 30 days of the date of this

inspection report, with the basis for your denial, to the Nuclear Regulatory Commission,

ATTN.: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional

Administrator, Region I; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Seabrook

Station. The information you provide will be considered in accordance with Inspection Manual

Chapter 0305.

G. St. Pierre

3

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure, and your response (if any), will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA by James W. Clifford Acting for/

David C. Lew, Director

Division of Reactor Projects

Docket Nos:

50-443

License Nos: NPF-86

Enclosure:

Inspection Report 05000443/2009007

w/Attachment: Supplemental Information

cc w/encl:

M. Nazar, Senior Vice President and Chief Nuclear Officer

A. Khanpour, Vice President, Engineering Support

M. Warner, Vice President, Nuclear Plant Support

M. Mashhadi, Senior Attorney, Florida Power & Light Company

M. Ross, Managing Attorney, Florida Power & Light Company

M. OKeefe, Manager, Licensing Manager

P. Freeman, Plant General Manager

K. Wright, Manager, Nuclear Training, Seabrook Station

S. Colman, FEMA, Region I

Office of the Attorney General, Commonwealth of Mass

K. Ayotte, Attorney General, State of NH

O. Fitch, Deputy Attorney General, State of NH

P. Brann, Assistant Attorney General, State of Maine

R. Walker, Director, Radiation Control Program, Dept. of Public Health, Commonwealth of MA

C. Pope, Director, Homeland Security & Emergency Management, State of NH

R. Hughes, Director, Licensing and Performance Improvement

J. Giarrusso, MEMA, Commonwealth of Mass

D. O'Dowd, Administrator, Radiological Health Section, DPHS, DHHS, State of NH

J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company

T. Crimmins, Polestar Applied Technology

R. Backus, Esquire, Backus, Meyer and Solomon, NH

Town of Exeter, State of New Hampshire

Board of Selectmen, Town of Amesbury

S. Comley, Executive Director, We the People of the United States

R. Shadis, New England Coalition Staff

M. Metcalf, Seacoast Anti-Pollution League

G. St. Pierre

4

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure, and your response (if any), will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA by James W. Clifford Acting for/

David C. Lew, Director

Division of Reactor Projects

Distribution w/encl: (via e-mail)

S. Collins, RA

M. Dapas, DRA

D. Lew, DRP

J. Clifford, DRP

A. Burritt, DRP

L. Cline, DRP

A. Turilin, DRP

D. Holody, ORA

W. Raymond, DRP, SRI

J. Johnson, DRP, RI

E. Jacobs, DRP, OA

L. Trocine, RI OEDO

H. Chernoff, NRR

R. Nelson, NRR

D. Egan, NRR, PM

R. Ennis, NRR, Backup

N. Valentine, NRR

ROPreportResources@nrc.gov

Region I Docket Room (with concurrences)

ML092400410

SUNSI Review Complete: LC (Reviewer=s Initials)

DOCUMENT NAME: G:\\DRP\\BRANCH3\\INSPECTION\\REPORTS\\ISSUED\\SEA0907.DOC

After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure

"E" = Copy with attachment/enclosure "N" = No copy

OFFICE

RI/DRP

RI/DRP

RI/DRP

RI/DRS

RI/ORA

RI/DRP

NAME

WRaymond/LC for LCline/LC

ABurritt/LC for

CCahill/CC DHolody/AD for DLew/JWC for

DATE

08/ 27/09

08/27/09

08/27 /09

08/27/09

08/27/09

08/27/09

OFFICIAL RECORD COPY

1

Enclosure

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No.:

50-443

License No.:

NPF-86

Report No.:

05000443/2009007

Licensee:

NextEra Energy Seabrook, LLC

Facility:

Seabrook Station, Unit No.1

Location:

Seabrook, New Hampshire 03874

Dates:

February 25, 2009 through July 16, 2009

Inspectors:

W. Raymond, Senior Resident Inspector

C. Cahill, Senior Reactor Analyst, DRS

K. Mangan, Senior Reactor Inspector, DRS

R. Moore, Reactor Inspector, DRP

J. Heinly, Reactor Inspector, DRP

J. Rady, Reactor Inspector, DRS

E. Burket, Reactor Inspector, DRS

Approved by:

David C. Lew, Director

Division of Reactor Projects

2

Enclosure

SUMMARY OF FINDINGS

IR 05000443/2009007; 02/25/2009-07/16/2009; Seabrook Station, Unit No. 1; Plant

Modifications.

The report covered a four-month period of inspection by resident and regional inspectors. The

significance of most findings is indicated by their color (Green, White, Yellow, or Red) using

Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP) and the

cross-cutting aspect of a finding is determined using IMC 0305, Operating Reactor Assessment

Program. One apparent violation was identified. Findings for which the SDP does not apply

may be Green or be assigned a severity level after NRC management review. The NRCs

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG-1649, "Reactor Oversight Process," Revision 4, dated December 2006.

Cornerstone: Mitigating Systems

Preliminary White. A self-revealing apparent violation of 10 CFR 50, Appendix B, Criterion III,

Design Control was identified following a review of the identified causes for the failure of the B

EDG jacket water cooling system on February 25, 2009. Specifically, NextEras failure to

adequately control design changes implemented on the B EDG jacket water cooling system in

January 2009 led to the failure of the gasket on flange JTR005 in the B EDG jacket water

cooling system on February 25.

The inspectors determined that this finding is more than minor because it is associated with the

design control attribute of the Mitigating Systems Cornerstone and affects the cornerstone

objective to ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Specifically, design modification 08MSE11,

intended to address flange JTR005 alignment and change the flange gasket design was

inadequate and resulted in inoperability of the B EDG. In accordance with IMC 0609,

Significance Determination Process, a Phase 3 risk analysis was performed and determined

that the calculated delta CDF for the finding was 2.27E-6, which represents a low to moderate

safety significance or White finding. The cause of the finding is related to the corrective action

component of the cross-cutting area of problem identification and resolution because NextEra

did not thoroughly evaluate problems in a timely manner such that resolutions address causes

(P.1(c)). Specifically, NextEra did not adequately evaluate deficient conditions when addressing

B EDG cooling water flange leaks, failed to adequately use readily available internal operating

experience, and failed to adequately evaluate and correct the impact of engine vibrations on

flange JTR005 integrity, contributing to a subsequent failure of the flange. (1R18)

Other Findings

Violations of very low safety significance (Severity Level IV) that were identified by NextEra,

have been reviewed by the inspectors. Corrective actions taken or planned by the licensee

have been entered into the licensee=s corrective action program. These violations and the

licensee=s corrective action tracking numbers are listed in Section 4OA7 of this report.

3

Enclosure

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Mitigating Systems

1R18 Plant Modifications (71111.18)

a.

Inspection Scope

On February 25, 2009, the B EDG failed to complete a routine operability test when a

leak occurred on the engine from a two bolt flange (joint JTR005) on the right bank (RB)

turbocharger at the connection to the jacket water return line. NRC Inspection Report

2009002 documented NextEras immediate response and the NRCs initial review of the

event. As of the end of the inspection documented in that report, NextEras evaluation of

the causes for the failure were still ongoing and the inspectors had identified several

issues of concern regarding the adequacy of the repairs and modifications completed

during the January 2009 overhaul and the adequacy of corrective actions taken to

assess and correct the potential effect of the RB turbo vibrations on EDG operability.

The NRC opened URI 05000443/2009002-01 to track NextEras completion of the root

cause evaluation for the February 25 event and the NRCs subsequent review of

NextEras completed evaluation.

To close URI 05000443/2009002-01 the inspectors reviewed NextEra actions to monitor

B EDG conditions and address identified deficiencies including work completed during

the B EDG overhaul conducted between January 29 and February 2, 2009. The

inspectors reviewed NextEra modifications to the B EDG jacket water cooling system

piping and gaskets on flanged connections, including the design changes in

00MMOD531, 06MSE037, 08MSE211 and EC144905. In particular, the inspectors

reviewed the flange gasket change completed per maintenance support evaluation

(MSE) 08MSE211, and the repairs conducted per work order (WO) 0821400 to address

alignment. The inspectors also reviewed NextEra actions to address vibrations in the RB

turbo during engine operation and the results of the root cause investigation for the

February 25, 2009 event, including the evaluations conducted for Action Request AR

191440. This inspection did not represent an inspection sample.

b.

Findings

Introduction. A self-revealing apparent violation (AV) of 10 CFR 50, Appendix B,

Criterion III, Design Control was identified following a review of the identified causes for

the failure of the B EDG jacket water cooling system on February 25, 2009. Specifically,

NextEras failure to adequately control design changes implemented on the B EDG

jacket water cooling system in January 2009 led to the failure of the gasket on flange

JTR005 in the B EDG jacket water cooling system on February 25.

Description. Operators shutdown the B EDG during a routine operability test on February

25, 2009, when a leak developed in the RB turbo jacket water cooling line at a 2-bolt

flanged connection. The NextEra investigation of the failure found the bolts for flange

JTR005 loose and the gasket material severely damaged and blown out along a part of

its circumference. Portions of the flange gasket were compressed 60% versus the

4

Enclosure

vendor recommended maximum of 16%. The flange faces had irregularities (bowing and

cupped surfaces) and there was a misalignment (gap) between the RB turbo outlet flange

and the jacket water coolant pipe flange. The gap ranged from 0.164 to 0.245 inches,

and by comparison, the installed gasket material had a nominal thickness of 0.0625

inches. NextEra evaluated the apparent cause of the flange failure and repaired the

flange under EC144905 and Work Order 1185637. The repairs included changes to

address the flange misalignment, gasket material compression, and positive measures to

prevent rotation of the bolts.

The NextEra Root Cause evaluation identified several factors that contributed to the

failure of the B EDG jacket water cooling line at flange JTR005. In January 2009

NextEra had implemented design change 08MSE211 to change the flange JTR005

gasket design from a 1/8-inch thick full-face gasket to a 1/16-inch annular configuration.

The design change was implemented per work order WO 0821400, which also

conducted maintenance to address flange JTR005 alignment. The root cause was that

the 1/16 inch annular gasket installed under 08MSE211 was an inadequate design for

the flange specific conditions. The combination of thinner gasket annular design, cupped

surfaces, flexed flange, flange gap and bolt loosening from vibration resulted in gasket

compression well below the minimum required. The gasket vendor specified a bolt pre-

load to achieve a 6000 psi compressive force, with a minimum of 3244 psi needed to

make the flange connection leak tight. NextEra found that most of the gasket surface

was at 1000 psi or less. This resulted in an essentially free floating gasket with no

sealing pressure in the area where the gasket failed. Thus, even though flange JTR005

successfully passed a post work test as part of WO 0821400 on January 31, 2009, the

as-built gasket design and flange conditions in combination with vibrations which

loosened the bolts, left flange JTR005 in a condition to fail with continued B EDG

operation.

The cause of the flange JTR005 leak on February 25 was the inadequate design and

design control measures used to change the flange gasket from full face to annular

configuration. Design Change 08MSE211 addressed leakage considerations by

stipulating attributes in the gasket design that address compressive load. 08MSE211 did

not address the suitability of the gasket design with adequate consideration of the flange

performance history. The gasket design did not adequately consider flange specific

conditions (bowing under pre-load, surface irregularities), misalignment (gap) or the

effects of vibration. 08MSE211 and WO 0821400 stipulated that the flange condition was

required to be true and flat, but provided inadequate instructions to the workers on how

to achieve the required conditions. The work was assumed to be within the skill of the

worker. The work order was also intended to correct flange JTR005 alignment issues.

NextEra concluded the excessive gap found between the flange faces was likely caused

by the welding completed during WO 0821400. Although 08MSE211 stated, reweld as

required ensuring piping is not pulled, the design control measure was inadequate

because no specific guidance was provided. Similarly, although WO 0821400 stated the

repair should eliminate any misalignment issues providing care is taken not to pull the

flange in final weld out, the work order provided no guidance on how to verify or

measure flange JTR005 alignment after welding. Design change 08MSE211 and WO 0821400 failed to adequately control the welding process relative to flange alignment;

failed to address flange specific irregularities; and failed to address vibration that could

impact bolt torque and gasket compressive load. As a consequence, the B EDG jacket

water cooling line was left in a condition to fail at flange JTR005 with continued B EDG

operation. The inspectors determined that this was a performance deficiency.

5

Enclosure

The inspectors also determined that the primary contributing cause for the performance

deficiency was that NextEra did not adequately use internal operating experience or

adequately evaluate deficient conditions when addressing the B EDG cooling water

flange issues. The work control, corrective action and engineering records show a

documented history of leakage from flange JTR005. While preparing and implementing

the gasket design change per 08MSE211, NextEra did not adequately research the

performance history for flange JTR005. Readily available plant operating experience

showed that a flexible gasket material installed under 06MSE037 was a proven design

providing leak free service for two years. The flexible gasket design could better tolerate

flange surface imperfections, was better for a flange experiencing vibrations, and could

better accommodate gaps between flange surfaces. Had the performance history been

adequately considered, NextEra could have either retained the 06MSE037 proven

design, or better prepared the 08MSE211 design change to address flange JTR005

conditions. Further, NextEra did not thoroughly evaluate problems such that resolutions

addressed causes. Specifically, during the repairs to flange JTR005 per WO 0821400,

on January 29, workers requested the use of a locking mechanism on the flange because

the fasteners were found less than the required torque (CR200901470). In an evaluation

dated February 5, 2009, NextEra concluded a locking feature would be evaluated if the

fasteners were loose in the future. The flange failed during the next EDG run on

February 25. The failure to adequately review the request for locking devices or evaluate

why they were needed was a missed opportunity to prevent vibration induced loosening

of the flange bolts. Locking wires were added to the flange as part of the subsequent

design change and repair activity under EC144905.

Analysis. The performance deficiency associated with this finding was that inadequate

design control measures used to correct flange alignment and change the gasket design

on the B EDG right bank turbocharger jacket water cooling line resulted in the B EDG

cooling water line failure on February 25, 2009. The Seabrook design control manual

requires that the design measures for safety related systems consider the equipment

performance history and whether materials are suitable for the application and

conditions. Specifically, design change 08MSE211 was inadequate because it did not

adequately consider the flange performance history and the suitability of gasket materials

and thickness relative to flange specific conditions (cupping and bowing); it did not

adequately consider welding stresses during repair and then failed to assure flange

alignment was acceptable after welding; and, it did not address the impacts of known

vibrations on flange performance and gasket compressive load.

The inspectors determined that this finding is more than minor because it is associated

with the design control attribute of the Mitigating Systems Cornerstone and affects the

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. Specifically, design

modification 08MSE11, intended to address flange JTR005 alignment and change the

gasket design was inadequate and resulted in inoperability of the B EDG. In accordance

with IMC 0609, Significance Determination Process, Phase 1 worksheets, a Phase 2

risk analysis was required because the finding represents an actual loss of safety

function of a single train for greater than the TS allowed outage time of 14 days.

The Phase 2 risk evaluation was performed in accordance with IMC 0609, Appendix A,

Attachment 1, User Guidance for Significance Determination of Reactor Inspection

Findings for At-Power Situations. The total exposure period for the degraded condition

6

Enclosure

was approximately 625 hours0.00723 days <br />0.174 hours <br />0.00103 weeks <br />2.378125e-4 months <br /> (26 days). Using Seabrooks Phase 2 SDP notebook, pre-

solved worksheets, and an initiating event likelihood of 3-30 days, the inspector identified

that this finding is of potentially substantial safety significance (Yellow). The finding

affected sequences in the loss of offsite power (LOOP) and LOOP and Loss of Class 1E

4.16 kV AC Bus A (E5) (LEACA) worksheets. For the LOOP condition, sequences that

resulted in a station blackout (SBO) were the dominant contributor to core damage. For

the LEACA condition, sequences that involved a stuck open relief valve were the

dominant contributor to core damage. The sum of the sequences in the LOOP and

LEACA, for the identified exposure period resulted in a Yellow. In recognition that the

Phase 2 notebook typically yields a conservative result, a NRC Region I Senior Reactor

Analyst (SRA) performed a Phase 3 risk assessment of this finding.

The SRA used the Seabrook Standardized Plant Analysis Risk (SPAR) model, Revision

3.50, dated July 2, 2009, and Graphical Evaluation Module (GEM), in conjunction with

the System Analysis Programs for Hands-On Integrated Reliability Evaluations

(SAPHIRE), Version 7, software to estimate the internal risk contribution. In discussions

with the licensee, it was discovered that the SPAR model for Seabrook did not credit

instrument air accumulators. Information on these backup accumulators was included in

the SDP notebook. Additionally, Seabrook questioned the modeling of switchgear

ventilation and provided design information to support the modeling revision to reflect the

design success criteria. The SRA worked with Idaho National Laboratory (INL) and

modified the model to correct the instrument air dependencies and modified the

ventilation success criteria. Specific changes included:

1. Basic event SWS-FAN-FC-RMCOOL (1E-3) was added to the SWS switchgear

cooling fault trees (EPS-DGNA-SWS, EPS-DGNB-SWS, SWS-RMCLA, SWS-

RMCLB). This event was ANDed with the existing SWS switchgear ventilation

logic.

2. Basic event IAS-TNK-FC-ADV (4.8E-8) was added to the atmospheric steam dump

valve (ADV) air supply fault tree (MSS-ADVS-AIR). This event allows operation of

the ADVs based on the air supply of the accumulators. The information provided

indicated that these accumulators would facilitate 10 cycles over a period of 10

hours.

The following assumptions were used for this assessment:

1. To closely approximate the type of failure exhibited by the B EDG, the SRA used the

B EDG failure to run basic event <EPS-EDN-FR-1B > and changed its failure

probability to 1.0, representing a 100 percent failure-to-run condition.

2. The exposure time for this condition was 625 hours0.00723 days <br />0.174 hours <br />0.00103 weeks <br />2.378125e-4 months <br /> (546.95 hours0.0011 days <br />0.0264 hours <br />1.570767e-4 weeks <br />3.61475e-5 months <br />, plus 77.75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br />

of unavailability during troubleshooting and repair).

3. Based upon the nature of the failure, no additional operator recovery credit was

provided.

4. All remaining events were left at their nominal failure probabilities.

5. Cutset probability calculation truncation was set at 1E-13.

Based upon the above assumptions, the Seabrook SPAR model internal contribution to

conditional core damage probability (CCDP) was calculated at 1.8E-6. This low E-6 delta

CCDP value represents a low to moderate safety significance (White). The dominant

internal event sequences involve a loss of offsite power event with subsequent failure of

the A EDG and the supplemental emergency power system (SEPS) resulting in a Station

7

Enclosure

Black Out. Additionally, the site fails to recover a diesel generator within four hours and

the failure to recover offsite power within four hours. These Phase 3 SPAR model results

correlate well to the Phase 2 SDP Notebook dominant core damage sequences.

The Seabrook Probabilistic Safety Assessment (PSA) is a full scope model that includes

events such as seismic events, internal fires and internal floods. The PSA summarizes

the contribution mainly from a turbine building fire or flooding as representing

approximately 31% of the total (internal and external) core damage frequency, or nearly

one third of the annualized risk. For the given exposure period this equates to an

external events delta CCDP of 4.7E-7. The NRC does not have an external risk model

for Seabrook. Consequently, the SRA used the licensees external risk assessment to

quantify the external risk contribution for this condition.

The SRA used IMC 0609, Appendix H, Containment Integrity Significance Determination

Process, to determine if this finding was a significant contributor to a large early release.

The Seabrook containment is classified as a pressurized water reactor large-dry

containment design. Based upon the dominant sequences involving loss of offsite power

and station blackout (SBO) initiating events, per Appendix H, Table 5.2, Phase 2

Assessment Factors - Type A Findings at Full Power, the failure of the B EDG does not

represent a significant challenge to containment integrity early in the postulated core

damage sequences. Consequently, this finding does not screen as a significant large

early release contributor because the close-in populations can be effectively evacuated

far in advance of any postulated release due to core damage. Accordingly, the risk

significance of this finding is associated with the delta CDF value, per IMC 0609,

Appendix H, Figure 5.1, and not delta LERF.

The Seabrook model used to evaluate the condition was RISKMAN model DBGOOS

which was based on SB2006NM. For the given assumptions, for a failure of the B EDG

to run, over the given exposure period, the licensee calculated CDF was 1.48E-6.

The contribution from internal events was 1.01E-6, and external event contribution was

4.7E-7. Similar to the NRC internal risk contribution, Seabrooks model illustrates that

the largest percentage of internal risk is derived from station blackout events.

For the given assumptions, the licensee and NRC results are in close agreement. As a

result, the calculated total risk significance of this finding is based upon NRC analysis.

The calculated risk is the summation of internal and external risk contributions (delta

CCDP internal + delta CCDP external (fires and floods) = delta CCDP total) which

equates to; 1.8E-6 + 4.7E-7 = 2.27E-6 delta CCDP. Annualized, this value of 2.27E-6

delta CDF represents a low to moderate safety significance or White finding.

The cause of the finding is related to the corrective action component of the cross-cutting

area of problem identification and resolution in that the licensee failed to thoroughly

evaluate problems in a timely manner such that resolutions address causes (P.1(c)).

Specifically, NextEra failed to adequately evaluate deficient conditions when addressing

B EDG cooling water flange leaks, failed to adequately use readily available internal

operating experience, and failed to adequately evaluate and correct the impact of engine

vibrations on flange JTR005 integrity.

Enforcement. 10 CFR 50, Appendix B, Criterion III, Design Control, states, in part, that

measures shall be established to assure that regulatory requirements and the design

basis for systems and components are correctly translated into specifications and

8

Enclosure

instructions. Measures shall also be established for the selection and review for

suitability of application of materials and parts that are essential to the safety-related

functions of the systems and components.

The Seabrook Station Design Control Manual (DCM) was developed pursuant to the

above to establish design control measures for safety related components, including the

emergency diesel generators. DCM Chapter 2, Section 8.0, describes the Maintenance

Support Evaluation (MSE) as the design control measure to implement in support of

maintenance. When preparing the MSE, the DCM requires that the design inputs and

interdisciplinary review guidelines on Figures 4-1-1 through 4-1-14 shall be used to

prepare and develop the design change and understand the areas impacted. DCM

Figure 4-1-1, Design Inputs, and Figure 4-1-3, Independent Reviewer Guidelines,

requires that the design shall consider mechanical requirements such as stresses and

vibration; whether materials are suitable for the application; credible failure modes of

connected equipment; and, account for equipment performance history.

Contrary to the above, design change 08MSE211, implemented by Work Order 0821400 on January 29 - 31, 2009, to modify and repair a two bolt flange (joint JTR005)

on the B EDG right bank turbocharger, did not adequately consider: mechanical

requirements such as stresses and vibration; whether materials were suitable for the

application; credible failure modes of connected equipment; and, account for equipment

performance history. Specifically, design change 08MSE211 and WO 0821400 did not

adequately address the suitability of materials relative to flange specific conditions

(cupping and bowing); did not adequately control welding stresses during repair and did

not assure post weld flange alignment was acceptable; did not adequately consider the

flange performance history and potential failures; and, did not address the impacts of

known vibrations on flange performance and gasket compression. As a result, the B

EDG turbocharger flange JTR005 was left in a condition to fail with continued B EDG

operation, and the diesel was declared inoperable during a test on February 25, 2009,

when the flange gasket blew out causing a rapid loss of jacket cooling water. This issue

was entered into Seabrooks corrective action program as CR 191440. Pending final

determination of significance, this finding is identified as an AV (AV 05000443/2009007-

01, Inadequate B EDG Design Change). Therefore URI 05000443/2009002-01 was

closed.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On July 16, 2009, the resident inspectors presented the inspection results to Mr. Paul

Freeman and other members of his staff, who acknowledged the finding. NextEra

acknowledged that none of the material examined by the inspectors during the inspection

was considered proprietary in nature.

9

Enclosure

4OA7 Licensee-Identified Violation

The following violation of very low safety significance (Severity Level IV) was identified by

NextEra. It was a violation of NRC requirements that met the criteria of Section VI of the

NRC Enforcement Policy, NUREG-1600, for being dispositioned as a non-cited violation

(NCV).

10 CFR 50, Appendix B, Criterion XVI, Corrective Action, requires that measures be

established to assure that conditions adverse to quality are promptly identified and

corrected. In the case of significant conditions adverse to quality, the measure shall

assure that the cause of the condition is determined and corrective action is taken to

preclude repetition.

The Florida Power and Light (FPL) Energy Quality Assurance Topical Report (QATR)

was written pursuant to the above and states in Section A-6 that FPL implements a

corrective action program to promptly identify and correct conditions adverse to quality.

Procedure PI-AA-205 requires that significant conditions adverse to quality be resolved

through corrective actions to prevent recurrence.

Contrary to the above, NextEra Nuclear Oversight issued a finding on April 9, 2009, (QR

090-017) after determining that past corrective actions for B EDG turbocharger vibration

issues were inadequate and have not been effective based on a past and recent history

of increased vibration, bolt failures, bolt loosening, turbocharger related coolant piping

weld failures, coolant system leaks and a failure in some instances to document these

conditions in the condition reporting system. The failure to resolve long standing and

increasing vibration and related issues for the B EDG constituted ineffective corrective

action.

The finding was more than minor because the ineffective action to resolve turbocharger

vibrations impacted the availability and reliability of a mitigating system. Further,

turbocharger vibration was causal to the B EDG failure on February 25, 2009 (reference

Section 1R18 above). The finding had very low safety significance because it did not

involve a loss of safety function or impact the safety function for a time greater than the

allowed outage time in the technical specifications. While increased vibrations were

causal to the February 25th B EDG failure, they were not the root cause since the cooling

water system would have failed due the inadequate gasket design and irregular flange

conditions. Further, the finding identified in QR 09-017 is separate from NRC Violation

20090701 since the inadequate design change resulting in the February 25 B EDG

failure occurred during the discrete time period of January 29-31, 2009, whereas the

corrective actions for the B EDG turbocharger vibrations have been ongoing for a longer

period of time (reference 2001 CR 200107312). The inspectors determined that the

Criterion XVI violation was licensee-identified. NextEra entered the issue into the

corrective action program as CR 00194370.

A-1

Attachment

SUPPLIMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

R. Arn, Engineering

K. Browne, Assistant Operations Manager

R. Campo, Plant Engineer

P. Freeman, Plant General Manager

G. Kim, Risk Analyst

K. Kiper, Risk Analyst

N. Levesque, Engineering Supervisor

E. Metcalf, Operations Manager

M. Ossing, Engineering Support Manager

M. Palumbo, Plant Engineer

R. Plante, Maintenance Supervisor

R. Samson, Maintenance Supervisor

G. St. Pierre, Site Vice President

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened 05000443/2009007-01

AV

Inadequate B EDG Design Change

Closed 05000443/2009002-01

URI

B EDG Emergency Shutdown During Testing on

2/25/09

LIST OF DOCUMENTS REVIEWED

Miscellaneous

Operations Logs - Various

MRC Associates Report, Modal Analysis of the Turbocharger on the B EDG, June 1992

Fairbank Morse Engineering Report, Turbocharger Vibration, September 27, 1991

Risk Significance of DG-B Failure February 25, 2009, 5/7/09 and 5/27/2009

Engineering Evaluations EE-09-002, Revision 0, 6/24/09; Revision 1, 7/29/09

B EDG Vibration Monitoring Data

System Engineering Notes on B EDG turbocharger vibrations, July 1999

Fairbank Morse/Coltec Industries Engineering Report, Turbocharger Vibration, 9/27/91

ARC Associates Report, Modal Analysis of the Turbocharger Section of the B Diesel

Generator, 6/9/92

Condition Reports

Root Cause Analysis for CR 191440, 194370

Action Requests 00191440, 00191586, 00191608

CR200901470, CR199917417, CR200901470, CR200107312, CR200304671,

CR200509803, CR200210604, CR200412056, CR200505245, CR200509803,

CR200800136, CR200801690, CR200809251, CR200809307, CR200901505

A-2

Attachment

Design Changes

DCR 94-00012, EDG Safety Classification Review, DCN 01

06MSE037, EDG Cooling Water System Gasket Replacement (AFLAS)

00MMOD531, EDG Turbocharger Cooling Water Piping Upgrade, DCN 12 94-064, D.G. Cooling Water System Gasket Replacement, Rev 01

08MSE211, EDG Turbocharger CC Water Piping Optional Gasket Configuration and

Bolting Type

EC144905, EDG Turbocharger CC Piping Outlet Cover Modification/Gasket

Replacement

Drawings

Drawing B20466, DG Cooling Water System Detail

Drawing 1-NHY-310882, CWD for Pressurizer Pressure Control Valve PCV-456B

P&ID 1-NHY-506402, DB - DG B Lube Oil System Control Loop Diagram

P&ID 1-NHY-504120, DG - DG Temperature Scanner Logic Diagram

P&ID 1-NHY-310008, 4160 Bus E6 One Line Diagram

P&ID 1-DG-B20463, Diesel Generator Lube Oil System Train B Detail

1-NHY-310002, Unit Electrical Distribution One Line Diagram, Rev. 40

1-NHY-310010, D1A and DG-1B One Line Diagram Sh.1, Rev. 14

1-NHY-310010, DG-1A and DG-1B One Line Diagram Sh.2, Rev. 4

Work Orders

Work Orders (WO) 0821400, 0812472, 0442764, 05131067, 072419, 0805715,

01185637

Procedures

PI-AA-205, Condition Identification and Corrective Action

PI-AA-01, Corrective Action and Condition Reporting

ES0815.002, General Welding Procedure, Rev 00, Chg 21

ES0815.004, Welding of Carbon Steel Materials, Rev 00, Chg 08

ES1807.001, Visual Examination Procedure for Welding, Rev 07, Chg 02

MA-AA-203, Work Order Planning Process, Rev 5

MA-AA-202, Work Order Execution Process, Rev 2

MS0517.03, Flange Maintenance, Rev 9

Manuals

FPLE Quality Assurance Topical Report (QATR), Section A-6, Corrective Action

Design Change Manual (DCM), Revisions 37- 45

DCM Sections 1.0, 2.0 and 8.0

DCM Figures 4-1-1 through 4-1-14

DCM Figure 4-1-1, Design Inputs

DCM Figure 4-1-3, Independent Reviewer Guidelines

A-3

Attachment

LIST OF ACRONYMS

AR

Action Request

CR

Condition Report

DCM

Design Control Manual

EDG

Emergency Diesel Generator

LERs

Licensee Event Reports

MSE

Maintenance Support Evaluation

NCV Non-Cited Violation

NRC

U.S. Nuclear Regulatory Commission

NRR

Nuclear Reactor Regulation

PARS

Publicly Available Records

RB

Right Bank

RV Reactor Vessel

SDP

Significance Determination Process

TS

Technical Specifications

UFSAR

Updated Final Safety Analysis Report

WO Work Order