Response to NRC Regulatory Issue Summary 2009-11, Preparation and Scheduling of Operator Licensing Examinations
ML092360405
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 08/17/2009
From: Mark Draxton
Constellation Energy Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IS-09-011
Download: ML092360405 (3)


Text

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, Maryland 20657 Constellation Energy*

Nuclear Generation Group August 17, 2009 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

SUBJECT:

Document Control Desk Calvert Cliffs Nuclear Power Plant Unit Nos. 1 & 2; Docket Nos. 50-317 & 50-318 Response to NRC Regulatory Issue Summary 2009-11, Preparation and Scheduling of Operator Licensing Examinations (a)

NRC Regulatory Issue Summary 2009-I1, Preparation and Scheduling of Operator Licensing Examinations, dated July 16, 2009

REFERENCE:

The purpose of this letter is to forward Calvert Cliffs Nuclear Power Plant, Inc.'s response to Reference (a). Reference (a) was issued to inform addressees of the Nuclear Regulatory Commission (NRC) staff's need for updated information on projected site-specific operator licensing examination schedules and estimated numbers of applicants planning to take operator licensing examinations and the NRC's generic fundamentals examinations.

The attached NRC Form 536 contains the proposed schedules of examinations intended for preparation and the estimated number of applicants to be tested in site examinations in calendar years 2010 through 2013 and generic fundamentals examinations in calendar years 2010 through 2011. The site does not plan to administer any generic fundamentals examinations in 2009.

Should you have questions regarding this matter, please contact Mr. Jay S. Gaines at (410) 495-5219 or Mr. Mark S. Draxton at (410) 495-5214.

Very truly yours, ark S. Draxton anager -- Training MSD/RDW/bjd

Attachment:

(1)

Response to Regulatory Issue Summary 2009-11, NRC Form 536 cc:

D. V. Pickett, NRC S. J. Collins, NRC Resident Inspector, NRC S. Gray, DNR

ý ozx

ATTACHMENT (1)

RESPONSE TO REGULATORY ISSUE

SUMMARY

2009-11, NRC FORM 536 Calvert Cliffs Nuclear Power Plant, Inc.

August 17, 2009

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 10/31/2011 (10-20080)

Estimated burden per response to comply with this voluntary information collection request:

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations.

Send comments regarding burden estimate to the Records and FOIA/Privacy Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC OPERATOR LICENSING 20555-0001, or by internet e-mail to infocollects@nrc.gov, and to the EXAMINATION DATA Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Calvert Cliffs Nuclear Power Plant, Inc.

Unit Nos. 1 & 2, Docket Nos. 50-317 & 50-318 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2010 CY 2011 CY 2012 CY 2013 ESTIMATED NUMBER OF LICENSEE-PREPARED 1

0 1

0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2010 CY 2011 CY 2012 CY 2013 NUMBER OF REACTOR 5

0 5

0 OPERATORS NUMBER OF SENIOR REACTOR OPERATORS -

4 0

5 0

INSTANT NUMBER OF SENIOR REACTOR OPERATORS -

5 0

5 0

UPGRADE NUMBER OF SENIOR REACTOR OPERATORS -

0 0

0 0

LIMITED PROPOSED DATES PRIMARY DATE August 2, 2010 August 6, 2012 ALTERNATE DATE August 13, 2012 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED CY 2010 CY 2011 NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

0 0

10 0

0 0

0 CANDIDATES NRC(. FORM 536 (10-2008)