Request for Extension of Duke Response Time to Referenced Letter
ML091470265
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 05/20/2009
From: Baxter D
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
FOIA/PA-2012-0325
Download: ML091470265 (2)


Text

PDuke DAVE BAXTER Vice President aEnergy Oconee Nuclear Station Duke Energy ON01 VP / 7800 Rochester Highway Seneca, SC 29672 May 20, 2009 864-873-4460 864-873-4208 fax dabaxter@dukeenergy.corn U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555-0001

Subject:

Duke Energy Carolinas, LLC Oconee Nuclear Station, Units 1, 2, and 3 Renewed Facility Operating License, DPR-38, DPR-47, and DPR-55 Docket Numbers 50-269, 50-270, and 50-287 Request for Extension of Duke Response Time to Referenced Letter

Reference:

NRC Letter from Joseph G. Giitter to Dave Baxter; "EVALUATION OF DUKE ENERGY CAROLINAS, LLC (DUKE), SEPTEMBER 26, 2008, RESPONSE TO NUCLEAR REGULATORY COMMISSION (NRC) LETTER DATED AUGUST 15, 2008, RELATED TO EXTERNAL FLOODING AT OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (OCONEE) (TAC NOS. MD8224, MD8225, AND MD8226)," dated April 30, 2009.

On May 11, 2009, Duke Energy Carolinas, LLC (Duke), Federal Energy Regulatory Commission (FERC) and Hydropower Consultant HDR-DTA personnel participated in a closed meeting with NRR and Region II staff at NRC headquarters. At this meeting, Duke presented information related to inundation studies involving a postulated failure of the Jocassee Dam and potential flooding at the Oconee Nuclear Station.

From discussions of the updated inundation model, additional insights were revealed that will warrant further research. Duke has determined that an additional 30 days beyond the 30 day response time stated in the referenced letter, will be needed to incorporate these additional insights. Consequently, Duke will provide an interim response within the requested 30 days and a final response within 60 days from May 11, 2009, respectively.

Inquiries on this letter should be directed to Robert C. Meixell of the Oconee Regulatory Compliance Group at (864) 873-3279.

Sincerely, Dave Baxter, Vice President Oconee Nuclear Station 4oo(

www. duke-energy.com

U. . iXuclear Regulatory Commission Mhy 20, 2009 Page 2 bc:

Mr. Allen G. Howe Office of Nuclear Reactor Regulation Department of Operating Licensing U.S. Nuclear Regulatory Commission Mail Stop 8 E1A Washington, DC 20555 Mr. Joseph G. Giiter Office of Nuclear Reactor Regulation Department of Operating Licensing U.S Nuclear Regulatory Commission Mail Stop 8 E1A Washington, DC 20555 Mr. Luis Reyes USNRC - Region II Sam Nunn Atlanta Federal Center, Suite 23T85, 61 Forsyth St., SW, Atlanta, GA 30303-8931 Mr. J. F. Stang, Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8 G9A Washington, DC 20555 Mr. Andy Hutto NRC Senior Resident Inspector Oconee Nuclear Station Susan E. Jenkins, Manager, Infectious and Radioactive Waste Management, Bureau of Land and Waste Management Department of Health & Environmental Control 2600 Bull Street, Columbia, SC 29201