MONTHYEARL-PI-08-022, Prairie Lsland, Units 1 and 2, Annual Report of Personnel Radiation Exposure2008-04-11011 April 2008 Prairie Lsland, Units 1 and 2, Annual Report of Personnel Radiation Exposure Project stage: Request ML0829506042008-10-23023 October 2008 RAI Re the Analysis of Severe Accident Mitigation Alternatives for Prairie Island Nuclear Generating Plant, Units 1 and 2 Project stage: RAI ML0829505512008-10-23023 October 2008 Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application (Tac Nos. MD8513 and MD8514) Project stage: Approval ML0829708182008-11-0404 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application Project stage: RAI ML0828309472008-11-0505 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application Project stage: RAI ML0832400322008-11-19019 November 2008 Request for Additional Information License Renewal Application, Prairie Island Nuclear Generating Plant, Units 1 & 2 Project stage: RAI ML0830105852008-11-19019 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application Project stage: RAI ML0831803942008-11-19019 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application Project stage: RAI ML0831809622008-11-20020 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application Project stage: RAI ML0832505912008-11-25025 November 2008 Request for Additional Information Boraflex Neutron Absorbing Material in Spent Fuel Pool Racks and the Protective Coatings Program Project stage: RAI ML0831805582008-11-25025 November 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application Project stage: RAI ML0832507162008-12-0101 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application (TAC Nos. MD8513 and MD8514) RAI 2.4.1-1, 2.4.3-1, 2.4.7-1, 2.4.7-2, 2.4.8-1, 2.4.11-1 Project stage: RAI ML0833100782008-12-0202 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application Project stage: RAI L-PI-08-098, Responses to NRC Requests for Additional Information Dated November 5, 2008 Regarding Application for Renewed Operating Licenses2008-12-0505 December 2008 Responses to NRC Requests for Additional Information Dated November 5, 2008 Regarding Application for Renewed Operating Licenses Project stage: Response to RAI ML0832507202008-12-0505 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application (TAC MD8513 and MD8514). RAIB2.1.3-1; B2.1.27-1; B2.1.8-1; B2.1.8-2; B2.1.8-3; B2.1.8-4; B2.1.19-1; B Project stage: RAI ML0830105612008-12-10010 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant Units 1 & 2, License Renewal Application Project stage: RAI ML0832503292008-12-16016 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application Project stage: RAI ML0831705612008-12-18018 December 2008 Enclosurequest for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application Project stage: RAI ML0831705662008-12-18018 December 2008 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 & 2, License Renewal Application (TAC Nos. MD8513 and MD8514) Cover Letter Project stage: RAI ML0908600632009-02-10010 February 2009 Meeting Summary, Telephone Conference Call Between the NRC and Prairie Island, Concerning Requests for Additional Information Pertaining to the Prairie Island Units 1 and 2, License Renewal Application Project stage: Meeting ML0908600622009-02-11011 February 2009 Summary of Telephone Conference Call Between NRC and Prairie Island Nuclear Generating Plant, Concerning Requests for Additional Information Pertaining to License Renewal Application Project stage: RAI ML0903706742009-02-18018 February 2009 Notice of Meeting with Northern States Power Corporation, Minnesota, (NSPM) to Discuss RAI in the License Renewal Review for PINGP Project stage: RAI ML0903406842009-02-20020 February 2009 Request for Additional Information for Prairie Island Nuclear Generating Units 1 and 2, License Renewal Application (Tac Nos. MD8513 and MD8514) Project stage: RAI ML0908600612009-02-23023 February 2009 Summary of Telephone Conference Call Held Between NRC and Prairie Island, Concerning Request for Additional Information Pertaining to the Prairie Island Units 1 and 2 Project stage: RAI ML0906305452009-03-0202 March 2009 Meeting Slides, Praire Island Refueling Cavity Leakage Project stage: Meeting ML0908404212009-03-31031 March 2009 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML0909300262009-04-0606 April 2009 Meeting Summary, Meeting Between NRC Staff and Northern States Power Company, Minnesota (NSPM) Project stage: Meeting L-PI-09-047, Responses to NRC Requests for Additional Information Dated March 31, 2009 and Follow Up Questions Regarding Application for Renewed Operating Licenses2009-04-0606 April 2009 Responses to NRC Requests for Additional Information Dated March 31, 2009 and Follow Up Questions Regarding Application for Renewed Operating Licenses Project stage: Response to RAI ML0908500092009-04-21021 April 2009 License Renewal Application, Safety Audit Report Project stage: Other ML0833001072009-04-21021 April 2009 Scoping and Screening Audit Summary Regarding the Prairie Island Nuclear Generating Plant, Units 1 and 2, License Renewal Application Project stage: Other ML0911701242009-05-29029 May 2009 Summary of Telephone Conference Call Held Between NRC and Northern States Power Company, Concerning Draft Requests for Additional Information Pertaining to the PINGP, Units 1 and 2, License Renewal Application Project stage: Draft RAI ML0915404122009-06-10010 June 2009 Request for Additional Information for the Review of the Prairie Island Nuclear Generating Plant, Units 1 and 2, License Renewal Application Project stage: RAI ML11147A1392011-06-27027 June 2011 Enclosure 2: Prairie Island Nuclear Generating Plant, Unit 2, Renewed Facility Operating License Project stage: Request ML11147A1402011-06-27027 June 2011 Notice of Issuance of Renewed Facility Operating License Nos. DPR-42 and DPR-60 for an Additional 20-Year Period Record of Decision Project stage: Request ML11147A1372011-06-27027 June 2011 Renewed Facility Operating License Project stage: Request ML11147A1232011-06-27027 June 2011 Issuance of Renewed Facility Operating Licenses for Prairie Island Nuclear Generating Plant Project stage: Approval ML11172A0202011-06-27027 June 2011 Technical Specifications, Unit 1, Renewed Facility Operating License for Prairie Island Nuclear Generating Plant Project stage: Other ML11172A0222011-06-27027 June 2011 Technical Specifications, Unit 2, Renewed Facility Operating License for Prairie Island Nuclear Generating Plant Project stage: Other 2008-04-11
[Table View] |
Text
April 6, 2009 LICENSEE:
Northern States Power Company, Minnesota FACILITY:
Prairie Island Nuclear Generating Plant Units 1 and 2
SUBJECT:
SUMMARY
OF MEETING HELD ON MARCH 2, 2009 BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND NORTHERN STATES POWER COMPANY, MINNESOTA, REPRESENTATIVES TO DISCUSS THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT UNITS 1 AND 2, LICENSE RENEWAL APPLICATION On March 2, 2009, the Nuclear Regulatory Commission staff (NRC or the staff) met with members of Northern States Power Company, Minnesota (NSPM or the applicant) in a public meeting to discuss the license renewal application (LRA) for the Prairie Island Nuclear Generating Plant Units 1 and 2. The purpose of the meeting was to discuss the NRC staffs request for additional information concerning the Unit 2 reactor cavity leakage path and potential impact on the primary containment liner. A list of attendees is provided in Enclosure 1 and the meeting agenda is provided in Enclosure 2.
The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm. Copies of the slides used by the applicant are available in ADAMS under Accession No. ML090630545. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC's PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail at PDR@nrc.gov.
/RA/
Richard Plasse, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosures:
- 1. Attendance List
- 2. Agenda cc w/encls: See next page
April 6, 2009 LICENSEE:
Northern States Power Company, Minnesota FACILITY:
Prairie Island Nuclear Generating Plant Units 1 and 2
SUBJECT:
SUMMARY
OF MEETING HELD ON MARCH 2, 2009 BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND NORTHERN STATES POWER COMPANY, MINNESOTA, REPRESENTATIVES TO DISCUSS THE PRAIRIE ISLAND NUCLEAR GENERATING PLANT UNITS 1 AND 2, LICENSE RENEWAL APPLICATION On March 2, 2009, the Nuclear Regulatory Commission staff (NRC or the staff) met with members of Northern States Power Company, Minnesota (NSPM or the applicant) in a public meeting to discuss the license renewal application (LRA) for the Prairie Island Nuclear Generating Plant Units 1 and 2. The purpose of the meeting was to discuss the NRC staffs request for additional information concerning the Unit 2 reactor cavity leakage path and potential impact on the primary containment liner. A list of attendees is provided in Enclosure 1 and the meeting agenda is provided in Enclosure 2.
The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm. Copies of the slides used by the applicant are available in ADAMS under Accession No. ML090630545. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC's PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail at PDR@nrc.gov.
/RA/
Richard Plasse, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosures:
- 1. Attendance List
- 2. Agenda cc w/encls: See next page DISTRIBUTION: See next page ADAMS Accession Number: ML090930026 OFFICE LA:DLR PM:RPB2:DLR BC:RPB2:DLR NAME SFigueroa RAPlasse RKuntz DATE 04/06/09 04/06/09 04/06/09 OFFICIAL RECORD COPY
Letter to Northern States Power Company from R. Plasse, dated April 06, 2009 DISTRIBUTION:
SUBJECT:
HARD COPY:
DLR RF E-MAIL:
PUBLIC PUBLIC [or NON-PUBLIC, if appropriate]
RidsNrrDlrResource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDciCsgb Resource RidsNrrDraAfpb Resource RidsNrrDraApla Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter T. Combs, OCA T. Madden, OCA R. Shane OCA B. Keeling, OCA R. Plasse N. Goodman T. Wengert J. Gessner, RIII K.Stoedter, RIII P. Zurawski, RIII RidsOpaMailResource I. Couret, OPA V. Mitlyng B. Mizuno, OGC
Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Peter M. Glass Assistant General Counsel Xcel Energy Services, Inc.
414 Nicollet Mall (MP4)
Minneapolis, MN 55401 Manager, Regulatory Affairs Prairie Island Nuclear Generating Plant Northern States Power Minnesota 1717 Wakonade Drive East Welch, MN 55089 Manager - Environmental Protection Division Minnesota Attorney General=s Office 445 Minnesota St., Suite 900 St. Paul, MN 55101-2127 U.S. Nuclear Regulatory Commission Resident Inspector's Office 1719 Wakonade Drive East Welch, MN 55089-9642 Administrator Goodhue County Courthouse P.O. Box 408 Red Wing, MN 55066-0408 Commissioner Minnesota Department of Commerce 85 7th Place East, Suite 500 St. Paul, MN 55101-2198 Tribal Council Prairie Island Indian Community ATTN: Environmental Department 5636 Sturgeon Lake Road Welch, MN 55089 Charles R. Bomberger Vice President of Nuclear Projects 414 Nicollet Mall, (MP4)
Minneapolis, MN 55401 Dennis L. Koehl Chief Nuclear Officer Northern States Power Minnesota 414 Nicollet Mall (MP4)
Minneapolis, MN 55401 Joel P. Sorenson Director, Site Operations Prairie Island Nuclear Generating Plant Northern States Power Minnesota 1717 Wakonade Drive East Welch, MN 55089
ENCLOSURE 1 MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION STAFF AND NORTHERN STATES POWER COMPANY, MINNESOTA PRAIRIE ISLAND NUCLEAR GENERATING PLANT UNITS 1 AND 2 LICENSE RENEWAL APPLICATION U.S. NUCLEAR REGULATORY COMMISSION ROOM 03-B4 11555 ROCKVILLE PIKE ROCKVILLE, MARYLAND 20852 MEETING ATTENDANCE LIST MARCH 2, 2009 PARTICIPANTS AFFILIATIONS Gene Eckholt Northern States Power Company (NSPM)
Richard Pearson NSPM Steve Skoyen NSPM Tom Downing NSPM Jeff Gorman Dominion Engineering Samson Lee U.S. Nuclear Regulatory Commission (USNRC)
Raj Auluck USNRC David Wrona USNRC Zuhan Xi USNRC Bryce Lehman USNRC Dan Huang USNRC Hans Ashar USNRC Briana Balsam USNRC Nate Goodman USNRC Jim Davis USNRC Don Brittner USNRC Alice Paulsen USNRC Bill Rogers USNRC Allen Hiser USNRC David Alley USNRC Richard Plasse USNRC Francis Cameron Prairie Island Indian Community Dan Naus (via telecon)
Oak Ridge National Laboratory
ENCLOSURE 2 MEETING BETWEEN THE NUCLEAR REGULATORY COMMISSION STAFF AND NORTHERN STATES POWER COMPANY, MINNESOTA PRAIRIE ISLAND NUCLEAR GENERATING PLANT UNITS 1 AND 2 LICENSE RENEWAL APPLICATION U.S. NUCLEAR REGULATORY COMMISSION ROOM 03-B4 11555 ROCKVILLE PIKE ROCKVILLE, MARYLAND 20852 MEETING AGENDA MARCH 2, 2009 I.
Introduction and Opening Remarks 10 minutes II.
Discussion of the Response to the Request for Additional Information 80 minutes III. Public Comments 30 minutes IV. Adjourn