MONTHYEARRS-09-007, Company, LLC, Application for Approval of Indirect Transfer of Control of Licenses2009-01-29029 January 2009 Company, LLC, Application for Approval of Indirect Transfer of Control of Licenses Project stage: Request ML0906403052009-03-0606 March 2009 Application for Indirect License Transfer of Licenses, Supplemental Information Request for Acceptance Review Project stage: Acceptance Review LR-N10-0355, Salem/Operations, S1.OP-AB.RC-0001(Q), Rev. 9, Reactor Coolant System Leak.2009-03-18018 March 2009 Salem/Operations, S1.OP-AB.RC-0001(Q), Rev. 9, Reactor Coolant System Leak. Project stage: Request RS-09-040, Additional Information - Application for Approval of Indirect Transfer of Control of Licenses2009-03-18018 March 2009 Additional Information - Application for Approval of Indirect Transfer of Control of Licenses Project stage: Request ML0907902522009-03-19019 March 2009 Acceptance Review Email to Exelon Corporation Exelon Corporations Application for Indirect Transfer of South Texas Project, Units 1 and 2, Facility Operating Licenses Project stage: Acceptance Review ML0907103302009-04-30030 April 2009 Corp., Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0913803242009-05-18018 May 2009 Corporation - Email from Licensee, Revised Requested Date for NRC Approval to September 30, 2009, Exelon Request for Indirect Transfer of Nrg Energys 44 Percent Share in South Texas Project, Units 1 and 2 Project stage: Request ML0908305622009-06-30030 June 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0908400692009-06-30030 June 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0908404602009-06-30030 June 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0908500282009-06-30030 June 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0907101852009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other NRC-2009-0292, Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing2009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0907102682009-07-0101 July 2009 Notice of Consideration of Approval of Application for Indirect License Transfer Resulting from Proposed Merger Between Exelon Corp., and Nrg Energy, Inc., and Opportunity for a Hearing Project stage: Other ML0911101592009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other NRC-2009-0289, FRN: General Notice. Braidwood, Units 1 and 2 - Notice of Consideration of Approval of Application Re Proposed Merger and Opportunity for a Hearing2009-07-0101 July 2009 FRN: General Notice. Braidwood, Units 1 and 2 - Notice of Consideration of Approval of Application Re Proposed Merger and Opportunity for a Hearing Project stage: Other ML0908607992009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Meger and Opportunity for a Hearing (Cover Letter) Project stage: Other ML0909205532009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Letter Project stage: Other ML0909206932009-07-0101 July 2009 Cover Letter-Notice of Consideration of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0909207382009-07-0101 July 2009 Frn:General Notice. LaSalle, Units 1 and 2 - Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0911101232009-07-0101 July 2009 Cover Ltr. - Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0911101342009-07-0101 July 2009 FRN: General Notice. Braidwood, Units 1 and 2 - Notice of Consideration of Approval of Application Re Proposed Merger and Opportunity for a Hearing Project stage: Other ML0911101492009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger and Opportunity for a Hearing Project stage: Other ML0911904742009-07-0101 July 2009 Notice of Consideration of Approval of an Application for Indirect License Transfer Resulting from the Proposed Merger Between Exelon Corporation and Nrg Energy, Inc., and Opportunity for a Hearing Project stage: Other NRC-2009-0296, Exelon Corporation - Notice of Consideration of Approval of Application Regarding Proposed Merger of Nrg Energy, Inc., Indirect Transfers of Nrg South Texas Project Facility Operating Licenses, and Opportunity for a Hearing (TAC Nos. M2009-07-0101 July 2009 Exelon Corporation - Notice of Consideration of Approval of Application Regarding Proposed Merger of Nrg Energy, Inc., Indirect Transfers of Nrg South Texas Project Facility Operating Licenses, and Opportunity for a Hearing (TAC Nos. ME0650 Project stage: Other ML0908301682009-07-0101 July 2009 Notice of Consideration of Approval of Application Regarding Proposed Merger of Nrg Energy, Inc., Indirect Transfers of Nrg South Texas Project Facility Operating Licenses, and Opportunity for a Hearing Project stage: Other ML0908301932009-07-0101 July 2009 Corporation - Notice of Consideration of Approval of Application Regarding Proposed Merger of Nrg Energy, Inc., Indirect Transfers of Nrg South Texas Project Facility Operating Licenses, and Opportunity for a Hearing Project stage: Other ML0921006862009-07-24024 July 2009 Corporation Withdrawal of Application for Approval of Indirect Transfer of Control of Licenses Project stage: Withdrawal ML0921000842009-07-27027 July 2009 E-mail Attaching Balch & Bingham Llp July 24, 2009 Letter - Withdrawal of Request for Approval of Indirect Transfer of Control of Licenses for Nrg South Texas LP Project stage: Withdrawal 05000498/LER-2009-001, For South Texas Project, Unit 1 Regarding Oil Reservoir for Essential Chiller 12B Below Required Temperature2009-07-30030 July 2009 For South Texas Project, Unit 1 Regarding Oil Reservoir for Essential Chiller 12B Below Required Temperature Project stage: Request RS-09-103, Corporation Withdrawal of Application for Approval of Indirect Transfer of Control of Licenses2009-07-30030 July 2009 Corporation Withdrawal of Application for Approval of Indirect Transfer of Control of Licenses Project stage: Withdrawal ML0923305222009-08-31031 August 2009 Letter to Notice of Withdrawal of Indirect License Transfer Request Project stage: Withdrawal ML0922204942009-09-0101 September 2009 Letter, Withdrawal of Application for Indirect Transfer of Control of Operating Licenses Project stage: Withdrawal ML0922205062009-09-0101 September 2009 FRN: Braidwood, Byron, Clinton, Dresden, LaSalle, Limerick, Oyster Creek, Peach Bottom, Quad Cities, Salem, Three Mile Island, Zion, and South Texas Project - Notice of Withdrawal of Application for Indirect Transfer of Control of Operating Project stage: Withdrawal 2009-06-30
[Table View] |
Text
From:
Mohan Thadani Sent:
Thursday, March 19, 2009 4:11 PM To:
david.distel@exeloncorp.com; kenneth.ainger@exeloncorp.com
Subject:
EXELON CORPORATION: ACCEPTANCE OF APPLICATION FOR INDIRECT TRANSFER OF SPECIFIED LICENSES Mr. Christopher M. Crane President and Chief Operating Officer Exelon Corporation 10 S. Dearborn Chicago, IL 60603
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2, BYRON STATION, UNITS 1 AND 2, CLINTON POWER STATION, DRESDEN NUCLEAR POWER STATION, UNITS 1, 2, AND 3, LASALLE COUNTY STATION, UNITS 1 AND 2, LIMERICK GENERATING STATION, UNITS 1 AND 2, OYSTER CREEK GENERATING STATION, PEACH BOTTOM ATOMIC POWER STATION, UNITS 1, 2, AND 3, QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2, SALEM GENERATING STATION, UNITS 1 AND 2, THREE MILE ISLAND NUCLEAR STATION, UNIT 1, ZION NUCLEAR POWER STATION, UNITS 1 AND 2, AND SOUTH TEXAS PROJECT, UNITS 1 AND 2 - RE: ACCEPTANCE OF APPLICATION FOR INDIRECT TRANSFER OF SPECIFIED LICENSES (TAC NOS. ME0650 AND ME0651)
Dear Mr. Crane:
By application dated January 29, 2009, Exelon Corporation (Exelon), acting on behalf of itself, Exelon Xchange Corporation (Xchange Corp.), Exelon Ventures Company, LLC (Exelon Ventures), and Exelon Generation Company, LLC (Exelon Generation), (together Applicants) requested the U.S. Nuclear Regulatory Commission (NRC) staff's consent to the indirect transfer of control of the NRC licenses for NRG South Texas LPs (NRG South Texas) 44 percent share of ownership interest in South Texas Project, Units 1 and 2 (STP), and to the extent required, the Exelon Generations facilities referenced above.
The NRC staff performed an acceptance review to determine if there is sufficient technical information in scope and depth to allow the staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements. Based on its review, the NRC staff concluded that supplemental information was needed in order to determine the acceptability of the Exelon Corporation's January 29, 2009 application.
By letter dated March 6, 2009, the NRC staff's informed the Exelon Corporation that supplemental information outlined in the March 6, 2009 letter was necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed application
in terms of regulatory requirements, and the protection of public health and safety and the environment. In order to make the application complete, the NRC staff requested that the applicants provide the requested supplemental information by March 20, 2009. This would enable the NRC staff to begin its detailed technical review.
On March 18, 2009, the applicant responded to the NRC staff's request, enclosing the requested supplemental information.
The NRC staff has reviewed the Exelon's January 29, 2009 application, and the March 18, 2009 supplemental information, and concluded that together the two submittals do provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed indirect transfers of the specified licenses in terms of regulatory requirements, and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its detailed technical review, you will be advised of it by separate correspondence.
If you have any questions, please contact me at (301) 415-1476 or email Mohan.Thadani@nrc.gov.
Mohan C Thadani Senior Project Manager Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov