MONTHYEARML24022A1172024-01-23023 January 2024 Acceptance of Requested Licensing Action Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24012A2422024-01-16016 January 2024 Acceptance of Requested Licensing Action License Transfer Request ML23236A0042023-12-27027 December 2023 Issuance of Amendment 274 Re Changes to Perm Defueled Emergency Plan and Perm Defueled Emergency Action Level Scheme ML23355A1242023-12-26026 December 2023 Withdrawal of an Amendment Request Re License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML23192A0772023-12-26026 December 2023 Letter Exemption from the Requirements of 10 CFR 140.11(a)(4) Concerning Offsite Primary and Secondary Liability Insurance ML23191A5222023-12-22022 December 2023 Exemption Letter from the Requirements of 10 CFR 50.54(W)(1) Concerning Onsite Property Damage Insurance (EPID - L-2022-LLE-0032) ML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23291A4402023-11-0303 November 2023 Acceptance of Requested Licensing Action Request for Exemption from 10 CFR 50.82(a)(2) to Support Reauthorization of Power Operations IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23275A0012023-10-0202 October 2023 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable ML23215A2302023-08-0303 August 2023 Notice of Organization Change - Chief Nuclear Officer IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23087A0362023-05-0202 May 2023 PSDAR Review Letter ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML23038A0982023-03-15015 March 2023 Request for Withholding Information from Public Disclosure ML23095A0642023-03-14014 March 2023 American Nuclear Insurers, Notice of Cancellation Rescinded PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23052A1092023-02-17017 February 2023 FEMA Letter to NRC, Proposed Commission Paper Language for Palisades Nuclear Plant Emergency Plan Decommissioning Exemption Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) Holtec Decommissioning International, LLC, Palisades Nuclear Plant L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 ML22321A2852022-11-17017 November 2022 LLC Master Decommissioning Trust Agreement for Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance ML22292A2572022-10-25025 October 2022 Permanently Defueled Emergency Plan License Amendment RAI Letter 2024-01-23
[Table view] |
Text
February 20, 2009 Mr. Christopher J. Schwarz Vice President, Operations Entergy Nuclear Operations, Inc.
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 CAL. No.RIII-08-003
SUBJECT:
CLOSURE OF CONFIRMATORY ACTION LETTER CAL RIII-08-003
Dear Mr. Schwarz:
On September 18, 2008, the Nuclear Regulatory Commission (NRC) issued Confirmatory Action Letter (CAL) RIII-08-003 to Entergy Nuclear Operations, Inc. (ENO) to confirm your commitments regarding spent fuel pool Region I storage racks containing less neutron absorber than assumed in the spent fuel pool (SFP) criticality analysis of record. The actions confirmed in the CAL were designed to ensure that the SFP had sufficient criticality margin maintained until compliance with Palisades Nuclear Plant Technical Specification (TS) 4.3.1.1.b and 10 CFR 50.68 Criticality Accident Requirements was restored.
Subsequent to the issuance of the CAL, the NRC performed a number of inspections to evaluate the implementation and effectiveness of your actions to address the four commitments associated with the CAL. The NRCs review of these commitments is documented in Inspection Report 05000255/2008005 (ML090400437).
A license amendment revising the TSs associated with the SFP was approved on February 6, 2009. By letter dated February 11, 2009, you informed the NRC that ENO had completed the actions and commitments associated with the CAL and that the amended TSs had been implemented. Subsequent NRC inspection of your implementation of the amendment identified several issues regarding procedures and training. Specifically, the inspectors identified that procedures needed to support implementation of the amended TSs had not been revised nor had training to licensed personnel on the revised requirements been provided. Based on our concerns, your staff implemented actions that addressed these items. By a letter dated February 20, 2009, you provided detailed information on your actions to ensure that the revised TS was adequately implemented.
Based upon the additional information provided, NRC inspections, and our assessment of the results of your actions, we have concluded that you have reestablished compliance with your license requirements for the spent fuel pool. Effective February 20, 2009, as discussed in a telephone call between you and Anne Boland, NRC RIII Division of Reactor Projects Acting Deputy Director, all commitments and actions documented in CAL RIII-08-003, dated September 18, 2008, are closed.
C. Schwarz Notwithstanding the closure of the CAL, the NRC will evaluate the issues of the SFP Region 1 fuel rack degradation and implementation of the amended TSs in accordance with the Reactor Oversight Process and provide our conclusions via separate correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS),
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by M. Satorius Acting for/
James L. Caldwell Regional Administrator Docket No. 50-255 License No. DPR-20 cc: Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, State Liaison Officer Michigan Department of Environmental Quality Michigan Office of the Attorney General
C. Schwarz Notwithstanding the closure of the CAL, the NRC will evaluate the issues of the SFP Region 1 fuel rack degradation and implementation of the amended TSs in accordance with the Reactor Oversight Process and provide our conclusions via separate correspondence.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS),
accessible from the NRC Web Site at http://ww.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by M. Satorius Acting for/
James L. Caldwell Regional Administrator Docket No. 50-255 License No. DPR-20 cc: Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, State Liaison Officer Michigan Department of Environmental Quality Michigan Office of the Attorney General DOCUMENT NAME: G:\PALI\CAL Closure Memo.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME DBetancourt:dtp JGiessner KOBrien by PL for CPederson by AB for DATE 02/20/09 02/20/09 02/20/09 02/20/09 OFFICE NRR RIII NAME ELeeds by telcon JCaldwell by MS for DATE 2/19/09 02/20/09
OFFICIAL RECORD COPY Letter to C. Schwarz from J. Caldwell dated February 20, 2009
SUBJECT:
CLOSURE OF CONFIRMATORY ACTION LETTER CAL RIII-08-003 DISTRIBUTION SECY OCA Bill Borchardt Bruce Mallett Cynthia Carpenter Nick Hilton James Caldwell Marvin Itzkowitz Catherine Marco Eric Leeds Bruce Boger Daniel Holody Carolyn Evans Kenneth OBrien William Jones John Ellegood John Giessner Eliot Brenner Hubert Bell Guy Caputo Mark Satorius Paul Pelke Patricia Lougheed Ross Telson Viktoria Mitlyng Prema Chandrathil Allan Barker James Lynch Patricia Buckley Tammy Tomczak RidsNrrDirsIrib Tamara Bloomer RidsNrrPMPalisades RidsNrrDorlLpl3-1 Jared Heck DRPIII DRSIII OEMAIL OEWEB