From:
Rick Ennis Sent:
Friday, January 30, 2009 11:10 AM To:
Jeff Keenan Cc:
Subject:
Acceptance Review for TACs ME0337 - 339 - Hope Creek & Salem CLIIP on Reporting Requirements
- Jeff, By letter dated January 5, 2009 (ADAMS Accession No. ML090130385), PSEG Nuclear LLC submitted license amendment requests for Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2. The proposed amendments would delete the license conditions that require reporting of violations of other requirements (e.g., conditions listed in Section 2.C) in the operating licenses. The proposed amendments would also delete similar reporting requirements in the Administrative Section of the Technical Specifications.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff=s acceptance review of these amendment requests. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendments in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact me at (301) 415-1420.
Richard B. Ennis, Senior Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation E-mail Properties Mail Envelope Properties (3D27D29AB75BCD4BAE913B63CBFBBEDFB5F51C5A3F)
Subject:
Acceptance Review for TACs ME0337 - 339 - Hope Creek & Salem CLIIP
on Reporting Requirements Sent Date: 01/30/2009 11:09:56 AM Received Date: 01/30/2009 11:09:56 AM From: Rick Ennis Created By: Rick.Ennis@nrc.gov Recipients:
Jeff.Keenan@pseg.com (Jeff Keenan)
Tracking Status: None Aron.Lewin@nrc.gov (Aron Lewin)
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 11092 01/30/2009 Options Expiration Date:
Priority: olImportanceNormal ReplyRequested: False Return Notification: False Sensitivity: olNormal Recipients received: