Letter Sequence Other |
---|
|
|
MONTHYEARML0829504322008-09-0101 September 2008 R. E. Ginna Draft - Section C Operating Exam (Folder 2) Project stage: Draft Other ML0829504252008-09-0101 September 2008 R. E. Ginna Draft - Section B Operating Exam (Folder 2) Project stage: Draft Other ML0829504222008-09-0101 September 2008 R. E. Ginna Draft - Section a Operating Exam (Folder 2) Project stage: Draft Other ML0829503892008-09-0101 September 2008 R. E. Ginna Draft - RO & SRO Written Exam (Folder 2) Project stage: Draft Other ML0829503842008-09-0101 September 2008 R. E. Ginna Draft - Outlines (Folder 2) Project stage: Draft Other ML0829503492008-09-17017 September 2008 NRC Comments on Draft Licensee-Developed Exam (Written & Operating Tests) (Folder 2) Project stage: Draft Other ML0831106652008-10-17017 October 2008 R. E. Ginna Final - Operating Exam, Sections a, B, and C (Folder 3) Project stage: Other ML0831106592008-10-17017 October 2008 R. E. Ginna Handouts to Applicants (Folder 3) Project stage: Other ML0831106192008-10-17017 October 2008 R. E. Ginna Final - RO & SRO Written Examination with Answer Key (401-5 Format) (Folder 3) Project stage: Other ML0831105902008-10-17017 October 2008 R. E. Ginna Final Outlines (Folder 3) Project stage: Other ML0835101112008-12-0505 December 2008 R. E. Ginna Nuclear Power Plant, LLC, NRC Operator Licensing Initial Exam Results, (Cover Letter Publicly Available; Enclosures Withheld from Public) Project stage: Other ML0836602532008-12-29029 December 2008 Final Qa/Related Operator Licensing Exam Forms (Folder 1) Project stage: Other 2008-12-05
[Table View] |
Similar Documents at Ginna |
---|
Category:Letter
MONTHYEARIR 05000244/20230042024-02-0505 February 2024 LLC - Integrated Inspection Report 05000244/2023004 ML24026A0112024-01-26026 January 2024 R. E. Ginna Nuclear Power Plant, Relief Request Associated with Inservice Testing of B Auxiliary Feedwater Pump IR 05000244/20230102023-12-19019 December 2023 LLC - Age-Related Degradation Inspection Report 05000244/2023010 ML23348A0992023-12-15015 December 2023 R. E. Ginna Nuclear Power Plant Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0029 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23347A0092023-12-13013 December 2023 Annual Commitment Change Notification ML23346A0142023-12-12012 December 2023 LLC - Senior Reactor and Reactor Operator Initial License Examinations ML23341A1252023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request - Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements ML23321A1392023-11-17017 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information and Request for Additional Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000244/20230032023-10-25025 October 2023 LLC - Integrated Inspection Report 05000244/2023003 ML23292A0282023-10-19019 October 2023 LLC - Notification of Conduct of a Fire Protection Team Inspection RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-108, Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles2023-10-11011 October 2023 Proposed Alternative for Examinations of Examination Categories B-B, B-D, and C-A Steam Generator Pressure Retaining Welds and Full Penetration Welded Nozzles RS-23-105, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2023-10-10010 October 2023 Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML23258A1382023-09-18018 September 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000244/2023010 IR 05000244/20230052023-08-31031 August 2023 Updated Inspection Plan for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23235A1722023-08-23023 August 2023 Re. Ginna Nuclear Power Plant, Transmittal of 2023 Owner'S Activity Report IR 05000244/20234012023-08-15015 August 2023 LLC - Material Control and Accounting Program Inspection Report 05000244/2023401 (Cover Letter Only) IR 05000244/20230022023-08-0303 August 2023 LLC - Integrated Inspection Report 05000244/2023002 ML23191A0592023-07-21021 July 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 155 Adoption of TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Revision 1 IR 05000244/20234022023-07-19019 July 2023 R. E. Ginna Nuclear Power Plant - Security Baseline Inspection Report 05000244/2023402 (Cover Letter Only) RS-23-083, Withdrawal - Proposed Alternatives Related to the Steam Generators2023-06-27027 June 2023 Withdrawal - Proposed Alternatives Related to the Steam Generators RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-050, Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube.2023-05-22022 May 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube. ML23135A0412023-05-15015 May 2023 2022 Annual Radioactive Effluent Release Report and 2022 Annual Radiological Environmental Operating Report ML23121A0482023-05-0101 May 2023 R. E. Ginna Nuclear Power Plant Core Operating Limits Report Cycle 44, Revision 0 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000244/20230012023-04-26026 April 2023 LLC - Integrated Inspection Report 05000244/2023001 ML23100A0302023-04-10010 April 2023 2023 10 CFR 50.46 Annual Report ML23114A1152023-03-29029 March 2023 Electronic Reporting of Exposure Data for 2022 RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23075A0872023-03-15015 March 2023 R. E. Ginna Nuclear Power Plant - Project Manager Assignment ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000244/20220062023-03-0101 March 2023 Annual Assessment Letter for R.E. Ginna Nuclear Power Plant, LLC (Report 05000244/2022006) ML22364A0242023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant Issuance of Amendments Nos. 231, 231, 232, 232, and 154 Regarding Adoption of TSTF-246 ML23060A1622023-03-0101 March 2023 R. E. Ginna Nuclear Power Plant, Supplemental Information - Proposed Alternatives Related to the Steam Generators RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23005A1762023-02-23023 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No. 153 Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes ML23005A1222023-02-22022 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Amendment No 152 Adopt TSTF-315-Revise Technical Specification 3.1.8, Physics Tests Exceptions - Mode 2 RS-23-040, Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators2023-02-21021 February 2023 Constellation Energy Generation, LLC, Supplemental Information - Proposed Alternatives Related to the Steam Generators ML22287A0692023-02-0808 February 2023 R. E. Ginna Station - Forward Fit Analysis (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and 0094) ML23031A2992023-02-0707 February 2023 R. E. Ginna Nuclear Power Plant - Withdrawal of an Amendment Request ML23010A0112023-02-0101 February 2023 R. E. Ginna Nuclear Power Plant - Issuance of Relief Request Associated with Inservice Testing of Refueling Water Storage Tank Outlet Value RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000244/20223012023-01-20020 January 2023 Initial Operator Licensing Examination Report 05000244/2022301 IR 05000244/20220122023-01-12012 January 2023 LLC - Design Basis Assurance Inspection (Teams) Inspection Report 05000244/2022012 ML22362A0382022-12-28028 December 2022 R. E. Ginna Nuclear Power Plant - Letter to Withdraw Application to Revise Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML22348A2062022-12-14014 December 2022 Re. Ginna Nuclear Power Plant - Annual Commitment Change Notification RS-22-123, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator2022-12-0707 December 2022 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator 2024-02-05
[Table view] |
Text
December 5, 2008 Mr. Mark A. Geckle Manager, Training R.E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519
Subject:
NRC Operator Licensing Initial Exam Results R. E. Ginna Nuclear Power Plant, LLC (Cover letter publicly available; enclosures withheld from public.)
Dear Mr. Geckle:
The purpose of this letter is to inform you of the individual examination results for your applicants on the initial written examination conducted on November 7, 2008, and the walk-through (overall) and/or simulator operating tests administered October 27 to November 11, 2008 at your facility. This meets the intent of Section E.1 of ES-501 of NUREG 1021, Operator Licensing Examination Standards for Power Reactors. This information is considered proprietary in accordance with 10 CFR 2.390 and it supplements the information contained in the related examination report for your facility which will be issued shortly.
As indicated in Enclosure 1, the completed ES-501-2, Power Plant Licensing Examination Results Summary, nine individuals who took the examination passed. contains the individual results ES-303-1 and 303-2, Operator License Examination Report, for each of the applicants. Contained therein are the deficiencies noted for each applicant. In accordance with your Systems Approach to Training (SAT) Program, we expect that you will review these results and provide appropriate remedial training for the individual independent of the overall pass status. The applicants have authorized the release of this information to your facility by signing Block 19A of their license applications (i.e., NRC Form 398). is a copy of the licenses.
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5046.
Sincerely,
/RA/
Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety
M. A. Geckle Docket No. 050-244 License No. DRP-18
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc w/licenses:
J. T. Carlin, Site Vice President
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5046.
Sincerely,
/RA/
Samuel L. Hansell, Jr., Chief Operations Branch Division of Reactor Safety Docket No. 050-244 License No. DRP-18
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc w/licenses:
J. T. Carlin, Site Vice President Distribution: w/o enclosures:
Master Exam File SUNSI Review Complete: SLH (Reviewer=s Initials)
ADAMS PKG NO.: ML080030004 DOCUMENT NAME: G:\DRS\Operations Branch\FISH\Exam 09-Ginna Oct 08 (U01687)\ExamNotificationLtr1.doc After declaring this document AAn Official Agency Record,@ it will be released to the Public.
OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CJBixler/CJB THFish/TF SLHansell/SLH DATE 12/05/08 12/05/08 12/ 05/08 OFFICIAL RECORD COPY