Request for Additional Information (Second Round) Regarding Technical Specification Change Related to Diesel Generator Maximum Steady State Frequency
ML083250488
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 11/21/2008
From: Beltz T
Plant Licensing Branch III
To: Rencheck M
Indiana & Michigan Electric Co
beltz T, NRR/DORL/LPL3-1, 301-415-3049
References
TAC MD8773, TAC MD8774
Download: ML083250488 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 21, 2008 Mr. Michael W. Rencheck Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, MI 49106 SUB.IECT:

D. C. COOK NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION (SECOND ROUND) REGARDING TECHNICAL SPECIFICATION CHANGE RELATED TO DIESEL GENERATOR MAXIMUM STEADY STATE FREQUENCY (TAC NOS. MD8773 and MD8774)

Dear Mr. Rencheck:

By application dated June 27,2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML071910238), Indian Michigan Power Company (I&M) (the licensee) requested changes to the Donald C. Cook Nuclear Plant, Units 1 and 2, Technical Specifications (TS), Section 3.8.1, related to the maximum diesel generator (DG) steady state frequency. In response to U.S. Nuclear Regulatory Commission (NRC) staff requests for additional information (RAI), the licensee provided supplemental information in letters dated April 28, 2008 (ADAMS Accession No. ML081280649) and September 4,2008 (ADAMS Accession No. ML082600469).

The NRC staff reviewed the information provided in the September 4, 2008, letter, in which I&M proposed additional changes to TS Section 3.8.1. Based on the review, the NRC staff requested additional information regarding the proposed change to the maximum DG frequency allowed within 2 seconds following rejection of the single largest post-accident load (surveillance requirement 3.8.1.10.c).

The draft RAI was sent to your staff on November 13, 2008 (ADAMS Accession No. ML083250175). On November 17,2008, NRC and I&M staff discussed the draft RAls and agreed that they could be formally issued. Accordingly, the finalized RAls are issued as an enclosure to this letter.

M. Rencheck

- 2 Please respond within 30 days of receipt of this letter. Feel free to contact me if you need clarification of this RAI.

Sincerely,//

'--~.~

~//

-Po,-

(,/.-='-t..

erry A. Beltz, Senior Project Manager Plant Licensing Branch '"-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-315 and 50-316

Enclosure:

As stated cc: Distribution via ListServ

REQUEST FOR ADDITIONAL INFORMATION D.C. COOK NUCLEAR PLANT, UNITS 1 AND 2 TECHNICAL SPECIFICATION CHANGE RELATED TO DIESEL GENERATOR <DG) MAXIMUM STEADY STATE FREQUENCY In supplemental information dated September 4, 2008 (ADAMS Accession No. ML082600469),

the licensee proposed change to the maximum DG frequency allowed within 2 seconds following rejection of the single largest post-accident load in the surveillance requirement (SR) 3.8.1.1O.c from 61.2 hertz (Hz) to 60.5 Hz.

In the Technical Specification (TS) Bases SR 3.8.1.10, the licensee stated that 2 seconds specified is equal to approximately 60 percent of the 3.49 seconds load sequence interval associated with sequencing of the largest load. According to the Updated Final Safety Analysis Report, Section 8.4, the largest sequenced load is the Centrifugal Charging Pump (600 hp) which is sequenced at 13 seconds; i.e., 3 seconds after the first block load connection at 10 seconds. The next load is sequenced at 17 seconds.

(1) Please explain how the 2 seconds specified is equal to approximately 60 percent of the load sequence interval associated with sequencing of the largest load.

(2) Please explain the basis for the 3.49 second sequence interval which is stated in the TS Bases.

ENCLOSURE

ML083250488

  • RAI transmitted b letter dated 11/07/2008 ML083120562 OFFICE LPL3-1\\PM LPL3-1/LA EEEB/BC
  • NAME TBeltz

."... THarris~':

GWilson DATE 11/"1 8

11/a 1108 11/07/08