Category:Letter
MONTHYEARML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19
[Table view] Category:Inspection Report
MONTHYEARML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 IR 05000528/20233012023-06-0505 June 2023 NRC Examination Report 05000528/2023301, 05000529/2023301 and 05000530/2023301 IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) IR 05000528/20234012023-02-27027 February 2023 NRC Security Inspection Report 05000528/2023401, 05000529/2023401, 05000530/2023401, and 07200044/2023401 (Full Report) IR 05000528/20220042023-01-30030 January 2023 Integrated Inspection Report 05000528/2022004 and 05000529/2022004 and 05000530/2022004 IR 05000528/20220102023-01-17017 January 2023 Design Basis Assurance Inspection (Teams) Inspection Report 05000528/2022010 and 05000529/2022010 and 05000530/2022010 IR 05000528/20220032022-10-24024 October 2022 Units, 1, 2 and 3 Integrated Inspection Report 05000528/2022003, 05000529/2022003, and 05000530/2022003 IR 05000528/20224032022-10-14014 October 2022 Security Baseline Inspection Report 05000528/2022403 and 05000529/2022403 and 05000530/2022403 IR 05000528/20220052022-08-23023 August 2022 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2022005 and 05000529/2022005 and 05000530/2022005) ML22235A6662022-08-23023 August 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000528/2022010, 05000529/2022010, and 05000530/2022010) and Request for Information IR 05000528/20224022022-08-0808 August 2022 Cover Letter Only - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 NRC Security Inspection Report 05000528 2022402, 05000529 2022402, 05000530 2022402, and 07200044 2022402 IR 05000520/20220022022-08-0505 August 2022 Integrated Inspection Report 05000528/2022002 and 05000529/2022002 and 05000520/2022002 IR 05000528/20223012022-06-21021 June 2022 NRC Examination Report 05000528/2022301, 05000529/2022301, and 05000530/2022301 IR 05000528/20220012022-05-0909 May 2022 Integrated Inspection Report 05000528/2022001, 05000529/2022001 and 05000530/2022001 ML22105A0512022-04-19019 April 2022 Review of the 2021 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20224202022-03-0808 March 2022 Security Baseline Inspection Report 05000528/2022420, 05000529/2022420 and 05000530/2022420, Cover Letter IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) IR 05000528/20210042022-02-0707 February 2022 Integrated Inspection Report 05000528/2021004, 05000529/2021004, and 05000530/2021004 IR 05000528/20210032021-11-12012 November 2021 Integrated Inspection Report 05000528/2021003, 05000529/2021003 and 05000530/2021003 IR 05000528/20210152021-10-27027 October 2021 Temporary Instruction 2515/194 Report 05000528/2021015 and 05000529/2021015 and 05000530/2021015 ML21273A3172021-10-0404 October 2021 Station. NON-SENSITIVE IR 05000528/20214042021-09-23023 September 2021 NRC Security Inspection Report 05000528/2021404, 05000529/2021404, 05000530/2021404 and 07200044/2021401 IR 05000528/20214012021-09-14014 September 2021 Security Baseline Inspection Report 05000528/2021401 and 05000529/2021401 and 05000530/2021401 IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) IR 05000528/20210022021-08-0909 August 2021 Integrated Inspection Report 05000528/2021002, 05000529/2021002, and 05000530/2021002 and Exercise of Enforcement Discretion IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 IR 05000528/20210142021-07-14014 July 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000528/2021014, 05000529/2021014 and 05000530/2021014 IR 05000528/20213012021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 IR 05000528/20214032021-05-28028 May 2021 Security Baseline Inspection Report 05000528/2021403; 05000529/2021403 and 05000530/2021403 (Public) IR 05000528/20210012021-05-12012 May 2021 PV 2021001, Palo Verde Nuclear Generating Station - Integrated Inspection Report 05000528/2021001 and 05000529/2021001 and 05000530/2021001 IR 05000528/20210122021-05-0404 May 2021 Triennial Fire Protection Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012 IR 05000528/20210102021-04-28028 April 2021 Biennial Problem Identification and Resolution Inspection Report 05000528/2021010 and 05000529/2021010 and 05000530/2021010 ML21105A1012021-04-19019 April 2021 Review of the 2020 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20210902021-03-0404 March 2021 Notice of Violation; NRC Inspection Report 05000528/2021090, 05000529/2021090, and 05000530/2021090 IR 05000528/20200062021-03-0303 March 2021 Annual Assessment Letter for Palo Verde, Units 1, 2 and 3, (Report 05000528/2020006, 05000529/2020006, and 05000530/2020006) ML21028A4402021-01-28028 January 2021 PV 2020 004 Integrated Inspection Report CAP IR 05000528/20203012021-01-27027 January 2021 NRC Initial Examination Report 05000528/2020301, 05000529/2020301, and 05000530/2020301 2024-01-10
[Table view] |
See also: IR 05000528/2008006
Text
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
UNITED STATES
NUC LE AR RE G UL AT O RY C O M M I S S I O N
R E GI ON I V
612 EAST LAMAR BLVD , SU I TE 400
AR LI N GTON , TEXAS 76011-4125
November 3, 2008
Mr. Randall K. Edington
Executive Vice President, Nuclear
Mail Station 7602
Arizona Public Service Company
P.O. Box 52034
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION, UNITS 1, 2, AND 3 -
SITE-SPECIFIC IMPLEMENTATION OF B.5.B PHASE 2 AND 3 MITIGATING
STRATEGIES TEMPORARY INSTRUCTION INSPECTION (NRC INSPECTION
REPORT 05000528/2008006; 05000529/2008006 AND 05000530/2008006)
Dear Mr.Ridenoure:
In a telephone conversation on October 28, 2008, Messrs. Daniel Hautala, Senior Engineer,
Regulatory Affairs, and Clyde Osterholtz, Team Leader, made arrangements for the Nuclear
Regulatory Commission (NRC) to inspect the site-specific implementation of B.5.b Phase 2
and 3 mitigating strategies at the Palo Verde Nuclear Generating Station, Units 1, 2, and 3. The
inspection is planned for the week of November 17, 2008.
In order for the NRC to adequately prepare for this inspection, please furnish the documents
listed in Enclosure 1 to Mr. Osterholtz in electronic format no later than November 10, 2008.
Please have available on site at the beginning of the inspection the arrangements and
documents listed in Enclosure 2. Mr. Hautala has been advised of this request and provided
with the name and address of the NRC lead inspector.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of
Management and Budget, approval number 3150-0011.
Enclosure transmitted herewith contains SUNSI. When separated from enclosure, this transmittal
document is decontrolled.
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
Arizona Public Service Company -2-
The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per
response, including the time for reviewing instructions, gathering and maintaining the data
needed, and completing and reviewing the collection of information. Send comments on any
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
Arizona Public Service Company -3-
aspect of this collection of information, including suggestions for reducing the burden, to the
Records and FOIA/Privacy Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission,
Washington, D.C. 20555-0001, or by Internet electronic mail to
INFOCOLLECTS.Resource@NRC.GOV; and to the Desk Officer, Office of Information and
Regulatory Affairs, NEOB-10202, (3150-0011), Office of Management and Budget, Washington,
D.C. 20503-0001.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records System (PARS) component of NRC's Agencywide Documents
Access and Management System (ADAMS), accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However,
because of the sensitive information contained in the enclosures, and in accordance with
10 CFR 2.390, a copy of this letters enclosures will not be available for public inspection.
If Safeguards Information is necessary to provide an acceptable response, please provide the
level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-
Related Information-Withhold Under 10 CFR 2.390 and follow the instructions for withholding in
10 CFR 2.390(b)(1).
Thank you for your cooperation in this matter. If you have any questions regarding this
inspection, please contact Clyde Osterholtz at 817 860-8269, or me at 817 860-8159.
Sincerely,
/RA/
Ryan E. Lantz, Chief
Operations Branch
Division of Reactor Safety
Dockets: 50-528; 50-529; 50-530
Licenses: NPF-41; NPF-51; NPF-74
Enclosures:
1. Documentation Requested
Prior to the Inspection
2. Arrangements/Documents Requested
To Be Available On Site during the
Inspection Week
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION
Arizona Public Service Company -4-
cc w/o enclosure:
Scott Bauer, Director
Regulatory Affairs
Palo Verde Nuclear Generating Station
Mail Station 7636
P.O. Box 52034
Phoenix, AZ 85072-2034
Dwight C. Mims
Vice President, Regulatory Affairs and
Plant Improvement
Palo Verde Nuclear Generating Station
Mail Station 7605
P.O. Box 52034
Phoenix, AZ 85072-2034
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION