MONTHYEARIR 05000321/20240102024-11-0606 November 2024 NRC Inspection Report 05000321/2024010 and 05000366/2024010 ML24299A2222024-10-31031 October 2024 Audit Summary for License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components IR 05000321/20240032024-10-30030 October 2024 Edwin I Hatch, Units 1 and 2 - Integrated Inspection Report 05000321/2024003 and 05000366/2024003 NL-24-0357, Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines2024-10-30030 October 2024 Notification of Deviation from the Inspection Frequency Requirements of the Boiling Water Reactor Vessel and Internals Project (BWRVIP) BWR Jet Pump Assembly Inspection and Flaw Evaluation Guidelines ML24292A1602024-10-22022 October 2024 Request for Withholding Information from Public Disclosure License Amendment Request to Revise Technical Specification Surveillance Requirements to Increase Safety/Relief Valve Setpoints ML24290A0792024-10-18018 October 2024 SLR Environmental Preapplication Meeting Summary ML24303A4102024-10-17017 October 2024 Dir Results Letter to NRC - Hatch - Hurricane Helene IR 05000321/20244012024-10-10010 October 2024 Security Baseline Inspection Report 05000321-2024401 and 05000366-2024401 ML24256A0282024-09-12012 September 2024 2024 Hatch Requal Inspection Corporate Notification Letter NL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024 Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc IR 05000321/20240912024-08-27027 August 2024 NRC Investigation Report 2-2023-003 and NOV - NRC Inspection Report 05000321/2024091 and 05000366/2024091 IR 05000321/20240052024-08-26026 August 2024 Updated Inspection Plan for Edwin I. Hatch Nuclear Plant, Units 1 and 2 - Report 05000321/2024005 and 05000366/2024005 NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information IR 05000321/20240022024-08-0808 August 2024 Edwin I Hatch Nuclear Plants, Units 1 and 2 – Integrated Inspection Report 05000321-2024002 and 05000366-2024002 NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 ML24198A1252024-07-16016 July 2024 Edwin I Hatch Nuclear Plant Units 1 - 2 Notification of Conduct of Title 10 of the Code of Federal Regulations 50 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 05000321/LER-2024-003, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link 05000321/LER-2024-002-01, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 ML24163A0532024-06-14014 June 2024 Audit Plan - Alternative Seismic Method LAR ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations IR 05000321/20240902024-05-15015 May 2024 NRC Inspection Report 05000321-2024090 and 05000366-2024090, Investigation Report 2-2023-003; and Apparent Violation NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 05000321/LER-2024-002, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 IR 05000032/20240112024-04-25025 April 2024 Notification of Edwin I. Hatch Nuclear Plant - Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 0500032/2024011 and 05000366/2024011 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 05000366/LER-2024-002, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications IR 05000321/20240012024-04-22022 April 2024 Integrated Inspection Report 05000321/2024001 and 05000366/2024001 NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint 05000321/LER-2024-001, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. ML23275A2402024-03-22022 March 2024 SNC Fleet - Issuance of Environmental Assessment and Finding of No Significant Impact Regarding Exemption from the Requirements of 10 CFR Part 73, Section 73.2, Definitions (EPID Nos. L-2023-LLE-0018 & L-2023-LLE-0021) - Letter NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission ML24069A0012024-03-0909 March 2024 – Correction of Amendment No. 266 Regarding License Amendment Request Regarding Relocation of Specific Surveillance Frequencies to a Licensee-Controlled Program (TSTF-425, Revision 3) ML24047A0362024-03-0404 March 2024 Response to Hatch and Vogtle FOF Dates Change Request (2025) NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 IR 05000321/20230062024-02-28028 February 2024 Annual Assessment Letter Edwin I. Hatch Nuclear Plant Units 1 and 2 - Nrc Inspection Report 05000321/2023006 and 05000366/2023006 2024-09-09
[Table view] |
Text
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II SAM NUNN ATLANTA FEDERAL CENTER 61 FORSYTH STREET, SW, SUITE 23T85 ATLANTA, GEORGIA 30303-8931 October 28, 2008 Mr. Dennis R. Madison Vice President - Hatch Southern Nuclear Operating Company, Inc.
Edwin I. Hatch Nuclear Plant 11028 Hatch Parkway North Baxley, GA 31513
SUBJECT:
HATCH NUCLEAR PLANT - TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000321/2008007 AND 05000366/2008007
Dear Mr. Madison:
On September 18, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a team inspection at your Hatch Nuclear Plant. The enclosed report documents the results of the inspection, which were discussed on September 18, 2008, with Mr. John Lewis and other members of your staff.
The inspection examined activities conducted under your license as they relate to the implementation of B.5.b Phase 2 and 3 mitigating strategies, your compliance with the Commissions rules and regulations, and with the conditions of your operating license. Within these areas, the inspection involved examination of selected procedures and representative records, observations of activities, and interviews with personnel.
Based on the results of the inspection, one NRC-identified finding of very low safety significance was identified. However, because this violation was of very low safety significance and because it was entered into your corrective action program, the NRC is treating the issue as a Non-Cited Violation in accordance with Section VI.A.1 of the NRCs Enforcement Policy. If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the United States Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at Hatch.
DOCUMENT TRANSMITTED HEREWITH CONTAINS OFFICIAL USE ONLY - SECURITY RELATED INFORMATION. WHEN SEPARATED FROM ENCLOSURE, THIS DOCUMENT IS DECONTROLLED
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION SNC 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the sensitive information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Sincerely,
/RA/
Scott M. Shaeffer, Chief Reactor Projects Branch 2 Division of Reactor Projects Docket Nos.: 50-321, 50-366 License Nos.: DPR-57, NPF-5
Enclosure:
Inspection Report 05000321, 05000366/2008007 w/
Attachment:
Supplemental Information cc w/encl: (See page 3)
DOCUMENT TRANSMITTED HEREWITH CONTAINS OFFICIAL USE ONLY - SECURITY RELATED INFORMATION. WHEN SEPARATED FROM ENCLOSURE, THIS DOCUMENT IS DECONTROLLED
_________________________ X SUNSI REVIEW COMPLETE CWR OFFICE RII:DRP RII:DRP RII:DRP RII:DRS RII:DRS NRR:PSPB SIGNATURE CWR /RA/ SMS /RA? via email via email via email via email NAME CRapp* SShaeffer PNiebaum GLaska JMiller DNelson DATE 10/28/2008 10/27/2008 10/16/2008 10/15/2008 10/15/2008 10/21/2008 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION SNC 3 cc w/encl: Laurence Bergen L. Mike Stinson Oglethorpe Power Corporation Vice President 2100 East Exchange Place Fleet Operations Support Tucker, GA 30085-1349 Southern Nuclear Operating Company, Inc. Dr. Carol Couch P.O. Box 1295 Director Birmingham, AL 35201-1295 Environmental Protection Department of Natural Resources Moanica Caston 2 Martin Luther King Drive, S.E.
Vice President and General Counsel Suite 1152 East Tower Southern Nuclear Operating Company, Inc. Atlanta, GA 30334 Bin B-022 P.O. Box 1295 Cynthia Sanders Birmingham, AL 35201-1295 Program Manager Radioactive Materials Program Raymond D. Baker Department of Natural Resources Licensing Manager 4220 International Parkway Licensing-Hatch Suite 110 Southern Nuclear Operating Company, Inc. Atlanta, GA 30354 P.O. Box 1295 Birmingham, AL 35201-1295 Chairman Appling County Commissioners cc w/Inspection Summary: County Courthouse Jeffrey T. Gasser 69 Tippins Street, Suite 201 Executive Vice President Baxley, GA 31513 Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Mr. K. Rosanski Birmingham, AL 35201-1295 Resident Manager Oglethorpe Power Corporation David H. Jones Hatch Nuclear Plant Vice President P.O. Box 2010 Engineering Baxley, GA 31515 Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Senior Engineer Birmingham, AL 35201-1295 Power Supply Municipal Electric Authority of Georgia cc w/o encl: 1470 Riveredge Parkway NW Arthur H. Domby, Esq. Atlanta, GA 30328-4684 Troutman Sanders Nations Bank Plaza Reece McAlister 600 Peachtree Street, NE, Suite 5200 Executive Secretary Atlanta, GA 30308-2216 Public Service Commission 244 Washington Street, SW Atlanta, GA 30334 DOCUMENT TRANSMITTED HEREWITH CONTAINS OFFICIAL USE ONLY - SECURITY RELATED INFORMATION. WHEN SEPARATED FROM ENCLOSURE, THIS DOCUMENT IS DECONTROLLED
OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION SNC 4 Letter to Dennis R. Madison from Scott M. Shaeffer dated October 28, 2008
SUBJECT:
HATCH NUCLEAR PLANT - TI 2515/171 VERIFICATION OF SITE SPECIFIC IMPLEMENTATION OF B.5.b PHASE 2 AND 3 MITIGATING STRATEGIES INSPECTION REPORT NO. 05000321, 05000366/2008007 Distribution w/encl:
C. Evans, RII L. Slack, RII OE Mail RIDSNRRDIRS PUBLIC R. Martin, NRR DOCUMENT TRANSMITTED HEREWITH CONTAINS OFFICIAL USE ONLY - SECURITY RELATED INFORMATION. WHEN SEPARATED FROM ENCLOSURE, THIS DOCUMENT IS DECONTROLLED