ML082770565

From kanterella
Jump to navigation Jump to search
Extended Power Uprate Pre-Application Meeting Slides
ML082770565
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 10/27/2008
From: Richard Guzman
Plant Licensing Branch 1
To:
Guzman R
References
Download: ML082770565 (22)


Text

Agenda

  • Plant Information
  • Power Ascension Testing
  • EP'U Modifications
  • Ac:hieving NMP2 Licensed EPU Power Level
  • TS Instrument Setpoint Impacts
  • License Amendment Submittal Format
  • Schedule
  • Summary 2

Plant Information

  • Nirle Mile Point Unit 2

- (jE BWR 5 Operating License in 1986 - 3323 MWt

- lin 1995, uprated to 104.3% OLTP - 3467 MWt IExtended Power Uprate to 120% OLTP - 3988 MWt

  • CLTP and EPU rated core flow = 108.5 Mlbm/hr
  • CLTP and EPU operating dome pressure = 1035 psia
  • EPU rated mai n steam flow = 17.636 Mlbm / hr I~MP2 is licensed to MELLLA and 105% core flow 3

Power Ascension Test Plan Bases

  • Bases

- SRP 14.2.1

- GE Topical Report requirements

- Industry experience

  • Performance

-- Validate equipment performance

- Utilize tiered and monitored approach to EPU power ascension

- Periodic data review by PORC and NRC 4

I~

j

/*

The wav energy works.

)\,"'::., 'S'J,.*.T;'**

Power Ascension Test Plan J'>

  • Mclnaged as an Infrequently Performed Test or Evolution (IPTE) in accordance with station procedures
  • IP-rE Manager and Power Ascension Test Director assigned
  • Mclnagement Oversight Board reviews
  • Start-up testing administrative requirements

- Roles and responsibility development

- Industry benchmarking

- Test plan and implementing test procedure development

- Acceptance criteria and predefined actions to address test anomalies established in procedure

- Power ascension test training

- Just-in-Time briefs 5

Power Ascension Test Plan Details

  • Incrernental Approach:

Similar to approach used in other EPUs Baseline data at 90% CLTP and 100% CLTP followed by constant rod line power ascension

- Power ascension rate < 1% / hour

- Plateaus at discrete power levels

- 96 hour0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> hold at 105% and 110% CLTP

- PORC and NRC reviews at designated plateaus

- Integrated with modification functional testing 6

Maj~Dr Power Ascension Tests Test 90% 100% 102.5% 105% 107.5% 110% 112.5% 115%

of CLTP of CLTP of CLTP of CLTP of CLTP of CLTP of CLTP of CLTP Chemistry X X X X Steam Dryer X X Every 1% Power Vibration Monitoring Steam Dryer Performance X X X X X X X (Moisture Carryover)

Radiation Measurements X X X X Core Performance X X X X X X X X Pressure Regulator X X X X X Feedwater X X X X X Piping Vibration X X Every 1% power Perfornnance Monitoring X X X X X X X X 7

Power Ascension Testing - Steam Dryer

~

~

  • Evaluation  !;

~

t

  • o

~

Strain gage limit curves ~

~

Collection of vibration data at every 1% increase

- Evaluation each 2.5% power increase

  • Monitoring

- MSL strain gages

- MSL accelerometers

- MSL moisture carryover

  • Reporting

- Provide data for NRC review at designated plateaus 8 *.

Power Ascension Testing - Steam Dryer

-- i Limit Curves I

  • Initial criteria derived utilizing EPU startup CLTP strain gage I data ~I" jf'

,:l Level 1: ,

l\

  • Defined by multiplying the CLTP MSL PSD traces by the ~

square of the minimum alternating stress ratio ~

  • If Level 1 is exceeded, immediately reduce power to an  !

acceptable level ~"

- Level 2:

  • Defined by multiplying the CLTP MSL PSD traces by 0.64 of the square of the minimum alternating stress ratio
  • If Level 2 is reached or exceeded, power ascension is stopped and a reanalysis of the dryer stress is conducted using the MSL data at the new power level 9

Condensate/Feedwater System Testing

  • Major Modified Components

- Replace feedwater pump internals and speed increaser

- Replace heater drain pumps

  • Modification Testing

- Pump performance curve validation

- Vibration/temperature monitoring

- System performance monitoring

  • Power Ascension Testing

- Level control system setpoint changes

- Maximum feedwater run-out analysis 10

Large Transient Testing

-- - It,i:n

  • Generator Load Reject and MSIV Full Closure Tests i NMP2 has tested large transient events and has documented results

- Gains from large transient testing are minimal and are outweighed by the potential harm large transient testing can cause

- Advanced analytical methods and training facilities accurately and adequately simulate large transient events and system performance

- Unnecessary plant challenge

  • NMP will request that these tests be waived for EPU 11

EPU Modifications

- Feedwater motor cable replacement

- Install additional turbine building HVAC area coolers

- Heater drain system modifications

  • Steam Systems

- Replace relief valves for 5t h & 6t h point feedwater heaters and scavenging steam piping

- Re-rate 5t h & 6t h point feedwater heaters & MSRs

- High pressure turbine replacement

- Replace LP turbine cross-around piping relief valves

- Replace atmospheric exhaust hood diaphragms 12

EPlJ Modifications

- - I

  • ARTS/MELLLA
  • Recirculation runback initiation logic
  • Instrument modifications / setpoint changes
  • Piping vibration monitoring modifications
  • Balance of Plant piping support modifications
  • Environmental Qualification modifications
  • Isophase bus duct cooling modifications
  • Mitigation systems (HWC & GEZIP trim replacements)
  • Design Basis Reconciliation 13

Achieving NMP2 Licensed EPU Power Level

~I

~

~

o

  • EPU modifications will be completed in 2010 to  ?

~

o o

support increase to 120% OLTP

  • NMP2 will operate up to 120% OLTP during Cycle 13
  • Operational impact of EPU 14

Optimize Operation at 120% OLTP I

  • NMP2 is considering

- Jet pump performance improvements

- Recirculation pump adjustable speed drives

- MELLLA+

16

T~5 Instrument Setpoint Impacts I

~

~f

- Basis for Safety Limit determination

  • SL-LSSS setpoints not impacted

- Methodology and sample calculations (previously provided)

- Analytical Limits, Allowable Values & LTSP

- Administrative controls

- TS notes as applicable 17

T~; Instrument Setpoint Impacts  :'It'

~

. ;J:

'it II

  • Setpoint methodology

- NRC-approved GEH methodology

- Consistent with CLTR

- Consistent with ARTS-MELLLA amendment

  • TS Setpoint Changes

- APRM Flow-Biased STP Scram

- Main Steam High Flow

- Turbine First-Stage Pressure Scram and RPT Bypass 18

EPLJ License Amendment Submittal Common Industry Issues

  • No Mixed Core

- Current core is GE14 -no change for EPU

- Containment overpressure not required to achieve EPU

  • Grid Stability

- NYISO Impact Study approved for 120% OLTP

- Grid modifications not required

  • Steam Dryer

- BWRVI P methodology applied 19

EPU License Amendment Submittal

  • Submittal Content

- License changes

- Power Uprate Safety Analysis Report

  • Content based on CPPU LTR

- Environmental. report

- Topical area attachments

  • Incorporation of Lessons Learned from Previous Industry Submittals 20

NMP2 EPU Timeline 2006 2007 2008 I 2009 I 2010 I 2011 I 2012 co co ....

so o o to to o

o

.c o

co o

o o

~

N iii

~

111 QI 111 111

ii ~

111

?: u.  ::t 2i  :=E o

Receive NRC*

  • Submit EPU Approval of to NRC MELLLA+

(if pursued) 0

[J Submit Alternate Source Term to NRC Receive NRC.

Approval of ARTS/MELLLA

  • Implement MELLLA+

CYCLE 13 (if pursued)

Start EPU .submit conceptual ARTS/MELLLA phase to NRC Submit terminei. MELLLA+ to

,lA+ will be NRC ursued O:onceptual ) Design

~ ... _._ .. - .. - . . I 21

Summary

--'-------------------------------------------------------------------------------------...,.,:1"",

it:

  • Power ascension testing plan is consistent with previously approved EPU submittals
  • Major modification scope is established
  • Setpoint methodologies consistent with industry guidance and NMP2 ARTS/MELLLA amendment
  • Major EPU industry issues have been addressed
  • Submittal will be consistent with RS-001 guidance and CLTR
  • NMP2 prepared to submit in December 2008 22