ML082400045

From kanterella
Jump to navigation Jump to search
Audit of the Licensees Management of Regulatory Commitments
ML082400045
Person / Time
Site: Millstone  
Issue date: 08/29/2008
From: John Hughey
Plant Licensing Branch 1
To: Christian D
Dominion Nuclear Connecticut
Hughey J, NRR/DORL, 301-415-3204
References
RIS-00-017, TAC MD8477, TAC MD8478
Download: ML082400045 (9)


See also: RIS 2000-17

Text

August 29, 2008

Mr. David A. Christian

President and Chief Nuclear Officer

Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT NOS. 2 AND 3 - AUDIT OF THE

LICENSEES MANAGEMENT OF REGULATORY COMMITMENTS

(TAC NOS. MD8477 AND MD8478)

Dear Mr. Christian:

The U.S. Nuclear Regulatory Commission (NRC) informed licensees in Regulatory Issue

Summary (RIS) 2000-17, AManaging Regulatory Commitments Made by Power Reactor

Licensees to the NRC Staff,@ dated September 21, 2000, that the Nuclear Energy Institute

document NEI 99-04, AGuidelines for Managing NRC Commitment Changes,@ contains

acceptable guidance for controlling regulatory commitments. RIS 2000-17 encouraged

licensees to use the NEI guidance or similar administrative controls to ensure that regulatory

commitments are implemented and that changes to the regulatory commitments are evaluated

and, when appropriate, reported to the NRC.

The NRC Office of Nuclear Reactor Regulation has instructed its staff to perform a periodic

audit of licensees commitment management programs to determine whether the licensees

programs are consistent with the industry guidance in NEI 99-04, and that regulatory

commitments are being effectively implemented. The previous audit of the Dominion Nuclear

Connecticut, Inc. (licensee) commitment management program was performed at the Millstone

Power Station, (MPS) Unit Nos. 2 and 3 in Waterford, Connecticut on October 7, 2004

(Agencywide Documents Access and Management Systems (ADAMS) Accession No.

ML043090370).

The subsequent audit was performed at the site on May 20, 2008. The NRC staff concludes

that, based on the audit: (1) the licensee has an adequate program to implement and manage

regulatory commitments; and (2) the licensee has an adequate program to implement and

manage regulatory commitment changes. Details of the audit are set forth in the enclosed audit

report.

D. Christian

- 2 -

The NRC staff appreciates the resources that were made available by Millstone station staff

during the audit. If you have any questions, please contact me at (301) 415-3204.

Sincerely,

/ra/

John D. Hughey, Project Manager

Plant Licensing Branch I-2

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation

Docket Nos. 50-336 and 50-423

Enclosure:

Audit Report

cc w/encl: See next page

D. Christian

- 2 -

The NRC staff appreciates the resources that were made available by Millstone station staff

during the audit. If you have any questions, please contact me at (301) 415-3204.

Sincerely,

/ra/

John D. Hughey, Project Manager

Plant Licensing Branch I-2

Division of Operating Reactor Licensing

Office of Nuclear Reactor Regulation

Docket Nos. 50-336 and 50-423

Enclosure:

Audit Report

cc w/encl: See next page

DISTRIBUTION:

PUBLIC

LPL 1-2 R/F

RidsNrrDorlLPL1-2 Resource

RidsNrrPMJHughey Resource

RidsNrrLAABaxter Resource

RidsOgcRp Resource

RidsAcrsAcnw_MailCTR Resource RidsRgn1MailCenter Resource

LRegner, NRR

Accession No.: ML082400045

  • via email

OFFICE

LPL1-2\\PM

LPL1-2\\LA

LPL1-2BC

NAME

JHughey

ABaxter*

HChernoff

DATE

08/28/08

08/28/08

08/29/08

OFFICIAL RECORD COPY

Millstone Power Station, Unit Nos. 2 and 3

cc:

Lillian M. Cuoco

Senior Counsel

Dominion Resources Services, Inc.

120 Tredegar Street, RS-2

Richmond, VA 23219

Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation

Department of Environmental

Protection

79 Elm Street

Hartford, CT 06106-5127

Regional Administrator, Region I

U.S. Nuclear Regulatory Commission

475 Allendale Road

King of Prussia, PA 19406

First Selectmen

Town of Waterford

15 Rope Ferry Road

Waterford, CT 06385

Charles Brinkman, Director

Washington Operations Nuclear Services

Westinghouse Electric Company

12300 Twinbrook Pkwy, Suite 330

Rockville, MD 20852

Senior Resident Inspector

Millstone Power Station

c/o U.S. Nuclear Regulatory Commission

P. O. Box 513

Niantic, CT 06357

Mr. J. W. "Bill" Sheehan

Co-Chair NEAC

19 Laurel Crest Drive

Waterford, CT 06385

Ms. Nancy Burton

147 Cross Highway

Redding Ridge, CT 00870

Mr. Evan W. Woollacott

Co-Chair

Nuclear Energy Advisory Council

128 Terrys Plain Road

Simsbury, CT 06070

Mr. Joseph Roy

Director of Operations

Massachusetts Municipal Wholesale

Electric Company

P.O. Box 426

Ludlow, MA 01056

Mr. J. Alan Price

Site Vice President

Dominion Nuclear Connecticut, Inc.

Millstone Power Station

Building 475, 5th Floor

Rope Ferry Road

Waterford, CT 06385

Mr. Chris L. Funderburk, Director

Nuclear Licensing &

Operations Support

Dominon Resource Services, Inc.

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060-6711

Mr. Robert T. Griffin, Director

Nuclear Safety & Licensing

Dominion Nuclear Connecticut, Inc.

Millstone Power Station

Building 475, 5th Floor

Rope Ferry Road

Waterford, CT 06385

Enclosure

AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION

LICENSEE MANAGEMENT OF REGULATORY COMMITMENTS

MILLSTONE POWER STATION, UNIT NOS. 2 AND 3

DOCKET NOS. 50-336 AND 50-423

1.0

INTRODUCTION AND BACKGROUND

The U.S. Nuclear Regulatory Commission (NRC) informed licensees in Regulatory Issue

Summary (RIS) 2000-17, AManaging Regulatory Commitments Made by Power Reactor

Licensees to the NRC Staff,@ dated September 21, 2000, that the Nuclear Energy Institute

document NEI 99-04, AGuidelines for Managing NRC Commitment Changes,@ contains

acceptable guidance for controlling regulatory commitments. RIS 2000-17 encouraged

licensees to use the NEI guidance or similar administrative controls to ensure that regulatory

commitments are implemented and that changes to the regulatory commitments are evaluated

and, when appropriate, reported to the NRC.

The NRC Office of Nuclear Reactor Regulation (NRR) has instructed its staff to perform a

periodic audit of licensees commitment management programs to determine whether the

licensees programs are consistent with the industry guidance in NEI 99-04, and that regulatory

commitments are being effectively implemented. The previous audit of the Dominion Nuclear

Connecticut, Inc. (DNC or, the licensee) commitment management program was performed at

the Millstone Power Station, Unit Nos. 2 and 3 (MPS) in Waterford, Connecticut on

October 7, 2004 (Agencywide Documents Access and Management Systems (ADAMS)

Accession No. ML043090370).

NEI-99-04 defines a Aregulatory commitment@ as an explicit statement to take a specific action

agreed to, or volunteered by, a licensee and submitted in writing on the docket to the NRC.

NRR guidelines direct the NRR Project Manager to perform a periodic audit of the licensee=s

commitment management program by assessing the adequacy of the licensee=s implementation

of a sample of commitments made to the NRC in past licensing actions (amendments, reliefs,

exemptions, etc.) and activities (bulletins, generic letters, etc.).

2.0

AUDIT PROCEDURE AND RESULTS

An audit was performed at MPS on May 20, 2008. The audit reviewed commitments made

since the previous audit which was conducted October 4, 2004. The audit consisted of two

parts: (1) verification of the licensee=s implementation of NRC commitments that have been

completed; and (2) verification of the licensee=s program for managing changes to NRC

commitments.

- 2 -

The NRC staff concludes that, based on the audit: (1) the licensee has an adequate program to

implement and manage regulatory commitments, or to track for future implementation of

regulatory commitments; and (2) the licensee has an adequate program to implement and

manage regulatory commitment changes.

2.1

Verification of Licensees Implementation of NRC Commitments

The primary focus of this part of the audit is to confirm that the licensee has implemented those

commitments made to the NRC as part of past licensing actions/activities. In general, the NRC

staff found that the licensees commitment tracking program had implemented the regulatory

commitments.

2.1.1 Audit Scope

Before the audit, the NRC staff searched ADAMS for the licensees licensing actions and

licensing activity submittals dated since the previous audit. The NRC staff requested that the

licensee provide a list of current open and closed regulatory commitments. From these lists, the

NRC staff chose a sample of items to review to ensure that the items had been captured in an

effective program for implementation. Criteria from the NRC staffs guidance documents were

used to select a sample of regulatory commitments. The commitments selected for the audit

are shown in Table 1 entitled, Audited Commitments.

2.1.2 Commitment Tracking Database Program

The licensees commitments are tracked in a computer database named the Commitment

Tracking System (CTS). CTS is defined as a repository for information associated with specific

commitments and actions taken to implement each commitment.

DNCs Administrative Procedure number LI-AA-110, Commitment Management, describes the

licensees regulatory commitment management process. The procedure defines how written

commitments to regulatory agencies are to be made only by those individuals with signature

authority for correspondence addressed to regulatory agencies.

Once commitments are identified, items are assigned a commitment type and entered into the

CTS. As described in LI-AA-110, only regulatory commitments are tracked in the system.

Following identification, the licensee enters committed due dates (i.e., those committed in formal

documentation) or establishes a due date as appropriate. These items are then assigned to the

appropriate functional area manager for implementation. The CTS maintains a record of the

required action(s), responsible party, status, due dates, and comments.

The NRC staff found that CTS: (1) adequately tracks commitments; and (2) provides an

adequate method of linking together a summary of the issue, action type, the lead department,

the responsible individual, due date, and extensions when used in accordance with the

procedure. The NRC staff also found that the CTS had captured the regulatory commitments

that were identified by the NRC staff.

- 3 -

Table 1 - Audited Commitments

Commitment

Tracking

Number

Dominion

Nuclear

Connecticut

Inc.

Submittal

Date

Commitment

Summary/Description

Licensee

Implementation

Status

RCR-42915

RCR-42916

09/08/2004

Maintain the hydrogen

recombiners in the

Technical Requirements

Manual (TRM).

Closed

RCR-42920

RCR-42921

RCR-42922

RCR-42923

RCR-42924

RCR-42925

11/05/2004

Independent Spent Fuel

Storage Installation

(ISFSI) commitments.

Open

RCR-42928

12/24/2004

Replace MPS2

pressurizer.

Closed

RCR-42944

RCR-42045

12/21/2004

Provide periodic dose

information to the NRC

via an industry database.

Closed

RCR-42947

RCR-42948

RCR-42949

RCR-42950

09/01/2005

Commitments associated

with Generic Letter (GL) 2004-02, PWR

Containment Sumps.

Working

RCR-42951

09/01/2005

Submit licensee

amendment request to

change the actuation

method and start time of

the MPS3 recirculation

spray system pumps. (GL 2004-02)

Closed

RCR-42967

05/16/2006

Submit structural

evaluation report to NRC

for MPS3 core exit

thermocouple nozzles.

Closed

RCR-42983

RCR-42984

RCR-42985

RCR-42986

01/31/2007

Commitments related to

mitigation activities

associated with Alloy

600-82-182 pressurizer

butt welds.

Closed

RCR-42987

10/04/2007

Commitments related to

Relief Request RR-89-61

weld overlays.

Closed

- 4 -

2.1.3 Audit Results

The NRC staff reviewed reports generated by the tracking programs and closure documentation

to evaluate the status of commitments as reported in the CTS. The NRC staff confirmed that

the commitments selected for the sample had been appropriately implemented in station

procedures, design change programs and other station administrative processes as appropriate.

2.2

Verification of the Licensees Program for Managing NRC Commitment Changes

2.2.1 Audit Scope

The primary focus of this part of the audit is to verify that the licensee has established

administrative controls for modifying or deleting commitments made to the NRC. The NRC staff

compared the licensee=s process for controlling regulatory commitments to the guidelines in

NEI-99-04, which the NRC has found to be an acceptable guide for licensees to follow for

managing and changing commitments. The process used at MPS is contained in LI-AA-110,

Revision 0, Commitment Management. The audit also verifies that the licensee=s commitment

management system includes a mechanism to ensure traceability of commitments following

initial implementation. This ensures that licensee personnel are able to recognize that future

proposed changes to the affected design features or operating practices require evaluation in

accordance with the commitment change control process. The licensee had not reported any

commitment changes to the NRC since the previous audit conducted on October 7, 2004.

The NRC staff reviewed the licensees commitment change process to: (1) evaluate the

licensees methodology for proposed changes to regulatory commitments with particular

consideration given to the intent of the original commitment and the safety and regulatory

significance of the proposed change; and (2) evaluate the licensees method of communicating

commitment changes to the NRC when reports are warranted due to either safety or regulatory

considerations. The NRC staff also evaluated the licensees administrative controls for

maintaining commitment traceability (e.g., markings or notations within procedures) to ensure

that licensee personnel are able to recognize that future changes to the affected design features

or operating practices require evaluation of the proposed change in accordance with the

commitment change control process.

2.2.2 Audit Results

The NRC staff reviewed the licensees procedure LI-AA-110, Revision 0, Commitment

Management, against NEI 99-04. In particular, Section 5.4 of the procedure lists NEI 99-04 as

a source reference. In general, the NRC staff found that LI-AA-110, Revision 0, follows closely

the guidance of NEI 99-04, as it sets forth the need for identifying, tracking and reporting

commitments, and it provides a mechanism for changing commitments. Attachment 2 of

LI-AA-110, Revision 0, provides detailed instructions regarding making changes to a

commitment.

LI-AA-110, Revision 0, provides instructions for modification, revision or deletion of a regulatory

commitment. A Regulatory Commitment Change Evaluation form is used to perform an

applicability determination for any proposed commitment change. This evaluation process will

determine if the proposed commitment change is covered by another codified process

(e.g., 10 CFR 50.59, Changes, tests and experiments, 10 CFR 50.92, Issuance of

amendment, or 10 CFR 50.54, Conditions of licenses).

- 5 -

Once commitment changes are identified, a Regulatory Commitment Change Evaluation form is

completed and reviewed. Some differences exist with respect to the NEI 99-04 guidance

regarding reporting of changed commitments in order to conform to the MPS Corrective Action

Program. However, in general, NRC notification is provided as necessary, as determined by the

commitment change evaluation process.

For changes that do not require immediate NRC notification, notification is provided with the

licensees biannual submittal of the revision to the Updated Final Safety Analysis Report. CTS

items tracking the commitment are then updated, as appropriate, to document the regulatory

commitment change.

The NRC staff concludes that the procedure used by the licensee to manage commitments is

appropriate and effective.

3.0

CONCLUSION

The NRC staff concludes, based on the above audit, that: (1) the licensee has implemented

NRC commitments on a timely basis; and (2) the licensee has implemented an effective

program for managing NRC commitment changes.

4.0

LICENSEE PERSONNEL CONTACTED FOR THIS AUDIT

W. Brown, Nuclear Technical Specialist III, Licensing Department

R. McIntosh, Nuclear Engineer III, Licensing Department

W. Bartron, Licensing Supervisor, Licensing Department

Principal Contributor: J. Hughey

Date: August 29, 2008