Tech Spec Pages for Amendment No. 185 Technical Specification 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air.
ML082190727
Person / Time
Site: Callaway Ameren icon.png
Issue date: 08/27/2008
From:
Plant Licensing Branch IV
To:
Thadani, M C, NRR/DORL/LP4, 415-1476
Shared Package
ML082190587 List:
References
TAC MD6549
Download: ML082190727 (3)


Text

-3 (4) UE, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source of special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5) UE, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C. This license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1) Maximum Power Level UE is authorized to operate the facility at reactor core power levels not in excess of 3565 megawatts thermal (100% power) in accordance with the conditions specified herein.

(2) Technical Specifications and Environmental Protection Plan*

The Technical Specifications contained in Appendix A, as revised through Amendment No. 185 and the Environmental Protection Plan contained in Appendix 8, are hereby incorporated in the license.

The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

(3) Environmental Qualification (Section 3.11, SSER #3)**

Deleted per Amendment No. 169

. Amendments 133, 134, & 135 were effective as of April 30, 2000 however these amendments were implemented on April 1, 2000.

    • The parenthetical notation following the title of many license conditions denotes the section of the Safety Evaluation Report and/or its supplements wherein the license condition is discussed.

Amendment No. 185

Diesel Fuel Oil, Lube Oil, and Starting Air 3.8.3 3.8 ELECTRICAL POWER SYSTEMS 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting Air LCO 3.8.3 The stored diesel fuel oil, lube oil, and starting air sUbsystem shall be within limits for each required diesel generator (DG).

APPLICABILITY: When associated DG is required to be OPERABLE.

ACTIONS


NOTE ----------------------------------------------------------.

Separate Condition entry is allowed for each DG.

COMPLETION CONDITION REQUIRED ACTION TIME A. One or more DGs with fuel A.1 Restore fuel oil level to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> level < 80,900 gal and within limits.

> 69,800 gal in storage tank.

B. One or more DGs with lube B.1 Restore lube oil 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> oil inventory < 750 gal and inventory to within limits.

> 686 gal.

C. One or more DGs with C.1 Restore fuel oil total 7 days stored fuel oil total particulates within limit.

particulates not within limit.

D. One or more DGs with new D.1 Restore stored fuel oil 30 days fuel oil properties not within properties to within limits. limits.

(continued)

CALLAWAY PLANT 3.8-19 Amendment No. 185

Diesel Fuel Oil, Lube Oil, and Starting Air 3.8.3 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.3.1 Verify each fuel oil storage tank contains ~ 80,900 gal 31 days of fuel.

SR 3.8.3.2 Verify lUbricating oil inventory is ~ 750 gal. 31 days SR 3.8.3.3 Verify fuel oil properties of new and stored fuel oil are In accordance with tested in accordance with, and maintained within the the Diesel Fuel Oil limits of, the Diesel Fuel Oil Testing Program. Testing Program SR 3.8.3.4 Verify pressure in two starting air receivers is ~ 435 31 days psig or pressure in one starting air receiver is ~ 610 psig, for each DG starting air subsystem.

SR 3.8.3.5 Check for and remove accumulated water from each 31 days fuel oil storage tank.

SR 3.8.3.6 Not used.

CALLAWAY PLANT 3.8-21 Amendment No. 185