Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling Decay Heat Removal and Containment Spray Systems Response to Extension Request (Tac Nos. MD7864, and MD7865)
ML081080509
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/28/2008
From: Lois James
NRC/NRR/ADRO/DORL/LPLIII-1
To: Rajiv Kundalkar
Florida Power & Light Energy Point Beach
Cushing, J S, NRR/DORL/LPLIII-1,415-1424
Shared Package
tnw List:
References
TAC MD7864, TAC MD7865
Download: ML081080509 (4)


Text

April 28, 2008 Mr. Rajiv S. Kundalkar Vice President, Nuclear Technical Services Florida Power and Light Company P. O. Box 14000 Juno Beach, FL 33408

SUBJECT:

POINT BEACH NUCLEAR PLANT UNITS 1 AND 2 - GENERIC LETTER 2008-01, MANAGING GAS ACCUMULATION IN EMERGENCY CORE COOLING, DECAY HEAT REMOVAL, AND CONTAINMENT SPRAY SYSTEMS, RESPONSE TO EXTENSION REQUEST (TAC NOS. MD7864 AND MD7865)

Dear Mr. Kundalkar:

Generic Letter (GL) 2008-01, Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, requests licensees to submit information to demonstrate that the emergency core cooling, decay heat removal, and containment spray systems are in compliance with the applicable regulatory requirements, and that suitable design, operational, and testing control measures are in place for maintaining this compliance. The GL 2008-01 states that each licensee is requested to submit a written response to the Nuclear Regulatory Commission (NRC) within 9-months to provide requested information and that if a licensee cannot meet the requested 9-month response date, a 3-month written response is required that describes the alternative course of action that it proposes to take, including the basis for the acceptability of the proposed alternative course of action.

By "L-2008-076, Extension Request Regarding the Three Month Response to NRC Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and [[system" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Systems|letter dated April 9, 2008]], (Agencywide Documents Access and Management System (ADAMS) Accession No. ML081050251) you stated, on behalf of the licensee, FPL Energy Point Beach LLC, that you had reached agreement in a telephone call on April 3, 2008, with the NRCs Division of Safety Systems (Jared Wermiel is the Deputy Director of the Division of Safety Systems, DSS) to extend the date for the 3-month response to May 11, 2008. You stated that your request for extension was to ensure a sound understanding of the alternative courses of actions, including those associated with performance of detailed piping walk downs.

This letter is to formally acknowledge the approval of the requested extension to the due date for submitting the 3-month response to GL 2008-01, and to document the telephone call with the NRC staff. Specifically, on April 3, 2008, you requested an extension for providing the above 3-month response for Point Beach Units 1 and 2, from April 11, 2008, to on or before May 11, 2008.

R. Kundalkar The NRC staff finds that your justification to extend the due date for the 3-month written response to GL 2008-01 to May 11, 2008, is acceptable, and your extension request is granted.

This letter does not alter or change the required 9-month response date of October 11, 2008.

The NRC staff will evaluate your alternate plans (3-month response) for responding to GL 2008-01 after receipt and will respond appropriately. If you have any questions regarding this issue, please feel free to contact the project manager, Jack Cushing at 301-415-1424.

Sincerely,

/RA/

Lois M. James, Chief Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: See next page

ML081080509 NRR-106 OFFICE LPL3-1/PM LPL3-1/LA DSS/DD PGCB/BC LPL3-1/BC NAME JCushing THarris JWermeil MMurphy LJames DATE 04 / 23 /08 04 / 25 /08 04 / 28 /08 04/ 28 /08 04 / 28 /08

Point Beach Nuclear Plant, Units 1 and 2 cc:

Licensing Manager FPL Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Mr. J. A. Stall Senior Vice President and Chief Nuclear Officer FPL Group P. O. Box 14000 Juno Beach, FL 33408-0420 Mr. Antonio Fernandez Senior Attorney FPL Energy, LLC P. O. Box 14000 Juno Beach, FL 33408-0420 Mr. Mano Nazar Senior Vice President and Nuclear Chief Operating Officer FPL Energy, LLC P. O. Box 14000 Juno Beach, FL 33408-0420 Mr. James H. McCarthy Site Vice President FPL Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241 J. Kitsembel Electric Division Public Service Commission of Wisconsin P. O. Box 7854 Madison, WI 53707-7854 Mr. M. S. Ross Managing Attorney FPL Energy, LLC P. O. Box 14000 Juno Beach, FL 33408-0420