MONTHYEARML23335A0832023-12-0707 December 2023 ADPCR3 - Crystal River LTP Public Mtg Slide Deck Final ML23335A0822023-12-0707 December 2023 NRC -Crystal River LTP Public Mtg Slide Deck Final ML20022A0262020-01-22022 January 2020 NEI Presentation Status Update for Ropte Short Term Action Plan: Removed Planned Unavailability for Mitigating Systems Performance Index ML17227A2362016-02-18018 February 2016 Presentation Slides from February 18, 2016, Meeting with Duke Energy Regarding Crystal River Unit 3, Cyber Security Plan Implementation Schedule Milestone 8 ML14024A2632014-01-16016 January 2014 Handouts for Post-Shutdown Decommissioning Activities Report Public Meeting, January 16, 2014 ML13308A0072013-11-0101 November 2013 Open Phase Resolution Update Meeting Duke Energy Entitled Open Phase Detection and Protection. ML13238A3072013-08-29029 August 2013 Slide for 08/29/13 Meeting CR-3 Decommissioning Submittals ML13134A1732013-05-13013 May 2013 Public Meeting Summary - Category 3 - Annual Assessment Meeting - Crystal River Unit 3 Nuclear Plant ML12305A2752012-11-0101 November 2012 11/1/12 Meeting Presentation - Regarding GSI-191 Strainer Fiber Bypass Test Plan on November 1, 2012 for Crystal River 3 Generating Plant ML12184A1382012-07-0202 July 2012 Public Meeting Summary of Category 3 - Annual Assessment Meeting Crystal River 2011 Annual Assessment Meeting Summary ML12132A3442012-05-11011 May 2012 NRC-AERB Bilateral Meeting Slide Presentation (Nro/De), Aerb, India - May 16-17, 2012 ML1204402842012-02-16016 February 2012 Public Meeting Construction Experiences - Evaluate Impact of Concrete Degradation ML12200A2492011-12-22022 December 2011 Presentation Slides on Shield Building /Containment Delamination ML11314A2552011-11-10010 November 2011 Summary of Pubic Meeting with Crystal River Nuclear Plant Docket No. 50-302 ML11307A4072011-11-0707 November 2011 Pp Presentation NRC Regulatory Conference Presentation 11/07/2011 ML11180A2752011-06-28028 June 2011 Preliminary Site-Specific Results of the License Renewal Environmental Review for Crystal River Unit 3 ML1116400592011-06-0707 June 2011 Meeting Summary - Crystal River Nuclear Plant - Presentation Slides ML11123A0422011-04-21021 April 2011 4/21/11 Crystal River Unit 3 Meeting Slides Regarding EPU Pre-Application ML11102A0052011-04-12012 April 2011 Progress Energy - Slides for NFPA 805 Pre-LAR Application Meeting April 12, 2011 ML1034806342010-12-16016 December 2010 Summary of Meeting with Florida Power Corporation Regarding Crystal River'S Proposed License Amendment Request to Support the Independent Spent Fuel Storage Facility Project ML1029201882010-10-19019 October 2010 Appendix Slides ML1029205162010-09-20020 September 2010 Photo ML1029200732010-09-20020 September 2010 Containment 40 Undated Delamination Investigation Report ML1025903962010-09-15015 September 2010 Summary of Public Meeting - Special Inspection Results Crystal River Nuclear Plant ML1025810962010-09-0202 September 2010 Unit #3 Containment Investigation and Repair ML1024402052010-09-0202 September 2010 NRC Special Inspection Team Exit Meeting for Crystal River - September 2, 2010 ML1019405242010-06-30030 June 2010 2010 June 30 NRC Technical Meeting ML1011803132010-03-19019 March 2010 E-Mail from Kuntz to Craver, Crystal River Containment Repair Plan Update ML1028710902010-03-0808 March 2010 Mar 8 Pnsc De Tensioning Briefing ML1028710912010-03-0303 March 2010 Mar 3 Pnsc De Tensioning Briefing P1 ML1028804582010-02-18018 February 2010 7.8 Excessive Water Jet Pressure Part 3 ML1028702742010-02-0606 February 2010 6.4 Rigid and Flexible Sleeves ML1029105792009-12-28028 December 2009 Email - from: Thomas, George to: Lake, Louis Cc: Khanna, Meena; Franke, Mark; Farzam, Farhad; Carrion, Robert; Masters, Anthony; Nausdj@Ornl.Gov Dated Monday, December 28, 2009 6:15 PM Subject: CR-3 Schedule and Root Cause Failure Modes Upd ML1011708192009-12-0303 December 2009 Root Cause Analysis - PII Metrics as of Dec 3rd 2009 ML16175A6062009-11-20020 November 2009 Unit #3, Containment Delamination Update ML1010603462009-11-20020 November 2009 Unit #3 Containment Delamination Update ML1029306172009-11-16016 November 2009 2009 Nov 16- Pnsc - Repair Update Final ML1029205092009-11-16016 November 2009 Presentation to Pnsc Containment Update & Discussion of Repair Options ML1029306522009-11-12012 November 2009 2009 Nov 12 - Containment Unfolded Graphics_Ir Mosaic.Pptx ML1029105542009-11-12012 November 2009 Email - from Orf, Tracy to: Lake, Louis Dated Thursday, November 12, 2009 7:05 Am Subject: FW: CR3 Information Update ML1029105772009-11-0606 November 2009 Containment Unfolded Buttress 2 to 5 ML1029105912009-11-0505 November 2009 Unit #3 Containment Update by Garry Miller ML1029105902009-11-0505 November 2009 2009 Nov 5 - NRC Telecon Briefing.Pdf ML1029105932009-11-0404 November 2009 Email - Subject: CR3 Status Meeting ML1029106712009-10-30030 October 2009 2009 Oct 30 - Root Cause Analysis Metrics.Pptx ML1029107232009-10-29029 October 2009 Condition Assessment (29Oct09).doc ML1029106722009-10-29029 October 2009 2009 Oct 29_NRC Copy_Containment Delamination.Pptx ML1007504252009-10-13013 October 2009 Email W/Briefing on CR3 Containment Project Overview ML1028804922009-10-0505 October 2009 10/6/09 Crystal River 3 Nuclear Safety Review Committee Handout Page ML0913201652009-05-12012 May 2009 Summary of Category 3 Public/Open House Meeting with Crystal River to Discuss Annual Assessment 2023-12-07
[Table view] |
Text
Crystal River Annual Assessment Meeting Reactor Oversight Program - CY 2007 Nuclear Regulatory Commission - Region II Crystal River Florida Enclosure April 8, 2008
Purpose of Todays Meeting A public forum for discussion of the licensees performance NRC will address the licensee performance issues identified in the annual assessment letter Licensee will be given the opportunity to respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance Enclosure
Agenda z Introduction z Review of Reactor Oversight Process z National Summary of Plant Performance z Discussion of Plant Performance Results z Licensee Response and Remarks z NRC Closing Remarks z Break z NRC available to address public questions Enclosure
Region II Organization Victor McCree Acting Regional Administrator Charles Casto Acting Deputy Regional Administrator Joseph Shea Kriss Kennedy Acting Director of Reactor Projects Acting Director of Reactor Safety Harold Christensen Davis Ayres Deputy Director Acting Deputy Director Marvin Sykes Regional Specialists Branch Chief Crystal River Resident Inspectors Project Engineers Thomas Morrissey Son Ninh Rogerio Reyes Jeffrey Hamman Enclosure
NRC Performance Goals z Safety: Ensure adequate protection of public health and safety and the environment z Security: Ensure adequate protection in the secure use and management of radioactive materials Enclosure
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response Enclosure
Examples of Baseline Inspections z Equipment Alignment ~80 hrs/yr z Triennial Fire Protection ~200 hrs every 3 yrs z Operator Response ~125 hrs/yr z Emergency Preparedness ~80 hrs/yr z Rad Release Controls ~110 hrs every 2 yrs z Worker Radiation Protection ~90 hrs/yr z Corrective Action Program ~250 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr Enclosure
Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very Low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Enclosure Red: High safety issue
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Enclosure Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2007 Licensee Response 87 Regulatory Response 8 Degraded Cornerstone 8 Multiple/Repetitive Degraded Cornerstone 1 Unacceptable 0 Total 104 Enclosure
National Summary z Performance Indicator Results (at end of CY 2007)
Green 1942 White 8 Yellow 2 Red 0 z Total Inspection Findings (CY 2007)
Green 759 White 9 Yellow 5 Red 0 Enclosure
Crystal River Inspection Activities (Jan 1 - Dec 31, 2007) 4100+ hours of inspection related activities Resident Inspector daily inspections Emergency Preparedness (EP) inspection Special Nuclear Material accountability and control inspection Radiation Protection (RP) and Inservice Inspections (ISI)
Component Design Basis Inspection PWR Containment Sump Inspection Fall 2007 refueling outage inspections: Daily Resident Inspector, Containment Sump, RP and ISI inspections Enclosure
Crystal River Assessment Results (Jan 1 - Dec 31, 2007) z Crystal Rivers performance was within the Licensee Response Column of the NRCs Action Matrix.
z All findings were of very low safety significance (Green).
z All Performance Indicators (PI) were Green Enclosure
Crystal Rivers Annual Assessment Summary Progress Energy operated Crystal River Unit 3 in a manner that preserved public health and safety.
All Cornerstone Objectives were met.
NRC plans only baseline inspections at Crystal River for CY2008.
Enclosure
Licensee Response and Remarks Dale Young Site Vice President Crystal River Unit 3 Enclosure
Contacting the NRC z Report an emergency (301) 816-5100 (call collect) z Report a safety concern:
(800) 695-7403 Allegation@nrc.gov z General information or questions www.nrc.gov Select What We Do for Public Affairs Enclosure
Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free)
Enclosure