MONTHYEARML0727506332007-10-31031 October 2007 (MNGP) - Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0807905152008-03-18018 March 2008 Draft RAI on Proposed Amendment Re Recirculation Riser Differential Pressure Project stage: Draft RAI ML0808804752008-03-27027 March 2008 Additional Question on the Proposed Recirculation Riser Differential Pressure Amendment Project stage: Other ML0819302482008-07-10010 July 2008 Draft RAI Questions Recirculation Riser Differential Pressure Amendment, Instrumentation Project stage: Draft RAI L-HU-08-019, Request for Continuation of NRC Reviews for Nuclear Management Co. Submittals on the Docket as of September 22, 20082008-09-0303 September 2008 Request for Continuation of NRC Reviews for Nuclear Management Co. Submittals on the Docket as of September 22, 2008 Project stage: Request L-MT-08-045, Response to Requests for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function2008-09-0808 September 2008 Response to Requests for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function Project stage: Response to RAI L-MT-08-061, Response to 09/26/2008, Request for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function2008-11-0606 November 2008 Response to 09/26/2008, Request for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function Project stage: Request ML0830106242008-11-12012 November 2008 Letter to Determine Withholding Proprietary Information from Public Disclosure Project stage: Other ML0902800532009-01-20020 January 2009 Monticello, Response to November 14, 2008, Request for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - H Project stage: Request L-MT-09-007, Response to November 14, 2008, Request for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Funct2009-01-20020 January 2009 Response to November 14, 2008, Request for Additional Information for License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function Project stage: Request ML0905002592009-03-0303 March 2009 Letter to Approve Request to Withhold Document Containing Proprietary Information from Public Disclosure Project stage: Other L-MT-09-041, Supplement to License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function2009-04-0202 April 2009 Supplement to License Amendment Request: Revision to the Allowable Value and Channel Calibration Surveillance Interval for the Recirculation Riser Differential Pressure - High Function Project stage: Supplement ML0830406082009-04-0707 April 2009 Issuance of Amendment No. 161 Regarding Recirculation Riser Differential Pressure Project stage: Approval 2008-07-10
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24284A2822024-10-0707 October 2024 Cover Email Re Monticello SLRA-3rd Round Request for Additional Information ML24254A3932024-08-26026 August 2024 SLRA - 2nd Round Request for Additional Information ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24131A0802024-05-10010 May 2024 Final RAI for LAR to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24036A2462024-04-24024 April 2024 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for Monticello Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML24092A2152024-03-27027 March 2024 Email: Requests for Information to Support Deis ML24068A0612024-03-0707 March 2024 Extension of Audit for License Amendment Request to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24064A1802024-03-0404 March 2024 Acceptance of Relief Request RR-017, Inservice Inspection (ISI) Impracticality During the Fifth Ten-Year Interval ML24036A0932024-02-0202 February 2024 Acceptance of License Amendment Request to Revise TS 5.6.5 and Update PTLR Neutron Fluence Methodology and Incorporate New Surveillance Capsule Data ML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML23353A0742023-12-19019 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Proposed Alternative VR-09, Modifications to OMN-17 ML23348A3462023-12-14014 December 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of License Amendment Request to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML23268A0292023-09-20020 September 2023 SLRA - Requests for Confirmation of Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23249A2092023-09-0606 September 2023 NRR E-mail Capture - Action: Opportunity to Review and Comment on a New NRC Information Collection, 10 CFR Part 50.55a, Codes and Standards (3150-XXXX) ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23237A4822023-08-25025 August 2023 SLRA - Request for Additional Information - Set 3 - Email from Marieliz Johnson to Shawn Hafen ML23228A1212023-08-16016 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request VR-11 for MO-2397 ML23227A2182023-08-15015 August 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Request RR-002 to Use IWB-2500(f) ML23219A1072023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23200A3502023-07-19019 July 2023 SLRA - Requests for Additional Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23172A1122023-06-21021 June 2023 SLRA - Requests for Confirmation of Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23054A3322023-02-23023 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for ISI Program Code of Record ML23053A1362023-02-13013 February 2023 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Relief Request to Use Later Edition of ASME BPV Code, Section XI, for Cisi Program ML23017A2222023-01-13013 January 2023 Verbal Authorization of Proposed Alternative PR-08 Regarding Inservice Testing Requirements of Certain High Pressure Coolant Injection System Components (EPID L-2022-LLR-0088) (Email) ML23004A1982023-01-0404 January 2023 NRR E-mail Capture - Draft Request for Additional Information Monticello Nuclear Generating Plant Request Pr 08, HPCI Pump Quarterly Testing ML23012A2102022-07-26026 July 2022 Letter Submitting Monticello Outline Package ML22175A1602022-06-24024 June 2022 NRR E-mail Capture - RAI Monticello Fuel Oil Storage Tank Inspection ML22181A1962022-06-24024 June 2022 NRR E-mail Capture - Draft RAI Monticello Alternative VR-08 ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22123A2822022-05-0303 May 2022 NRR E-mail Capture - Request for Additional Information Monticello Alternative VR-10, EFCV Testing Frequency ML22101A0712022-04-11011 April 2022 NRR E-mail Capture - Monticello - Acceptance of Requested Licensing Action License Amendment Request to Revise TS 3.6.1.8 Residual Heat Removal (RHR) Drywell Spray Header and Nozzle Surveillance Frequency ML22089A1302022-03-30030 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Alternative Related Excess Flow Check Valve Testing Frequency ML22082A1812022-03-23023 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-08 Alternative to Adopt ASME OM Code Case OMN-28 ML22075A2612022-03-16016 March 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of VR-07 Alternative Related to MOV Testing Per ASME OM Code Case OMN-26 ML22067A2032022-03-0808 March 2022 Audit Plan to Support Review of an Amendment to Transition to Atrium 11 Fuel (Redacted) ML22011A0642022-01-11011 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Support Diesel Generator Fuel Oil Storage Tank Inspection ML22005A3612022-01-0505 January 2022 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pump Vibration Testing Per ASME OM Code Case OMN-22 ML21347A0082021-12-10010 December 2021 NRR E-mail Capture - Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Acceptance of Requested License Amendment Standard Emergency Plan and Consolidated Emergency Operations Facility ML21330A0382021-11-18018 November 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related RHR and RHRSW Pump Testing ML21286A7882021-10-0606 October 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Residual Heat Removal Heat Exchanger Flow Control Valve Stroke Timing ML21256A1862021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to HPCI and RCIC Pump Testing ML21256A1892021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Testing the Control Rod Drive Scram Discharge Header Check Valves ML21256A1882021-09-13013 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Vibration Testing Range for the Sblc Pumps ML21253A2002021-09-10010 September 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Relief Request Alternative Related to Pressure Isolation Valve Testing ML21252A0132021-08-31031 August 2021 NRR E-mail Capture - Monticello Nuclear Generating Plant - Acceptance of Requested Licensing Action License Amendment Request to Adopt Advanced Framatome Methodologies ML21130A3022021-05-0707 May 2021 Initial and Final Written 10 CFR 21 Notification for GE Hitachi Numac Prnm System ML21110A7042021-04-20020 April 2021 Response: Monticello Nuclear Plant Outage - Covid Risk to On-Site Employees ML21084A2522021-03-24024 March 2021 NRR E-mail Capture - Revised Review Schedule for Monticello TSTF-505 (EPID L-20200LLA-0062) ML21068A2772021-03-0909 March 2021 NRR E-mail Capture - Monticello TSTF-505, Request for Additional Information ML20343A1292020-12-0808 December 2020 NRR E-mail Capture - Request for Additional Information 2024-08-05
[Table view] |
Text
From: Peter Tam Accession No. ML080790515 To: Arias, Jesus; Loeffler, Rick; Blake, Timothy Date: 03/18/2008 4:29:11 PM
Subject:
Monticello - Draft RAI re. proposed amendment on recirculation riser diff.
pressure (TAC MD6864)
Rick:
We are reviewing your application dated 9/25/07 for the subject amendment. Our reviewer, Leonard Ward, has written the following draft RAI questions on the thermal hydraulic aspects of the proposed amendment. Please set up a conference call with me to discuss these draft questions. We plan to issue these questions formally around 4/4/08:
(1) For the LPCI system in the residual heat removal operating mode, please address the potential for a LOCA with certain postulated single failures in electrical distribution that could leave the plant vulnerable regardless of offsite power status. For loop select logic plants operating in this mode, for example, the loop select logic mechanism could allow a single active failure (i.e., an LPCI injection valve in the path to the intact recirculation loop) to disable the entire LPCI system, placing dependence on the core spray system to accomplish the low pressure core cooling function. Please explain.
(2) Please provide the axial power shape used in the SBLOCA re-analysis for the limiting break. What is the PLHGR applied to the peak power position for this shape?
(3) For the limiting SBLOCA, does the PCT terminate due to top down cooling (i.e.,
counter-current flow) into the hot bundle and hot rod from the core spray? Please explain.
The solely purpose of this e-mail is to prepare you and others for the proposed conference call.
This e-mail does not convey an NRC staff position, and does not formally request for additional information.
Peter S. Tam, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation e-mail: pst@nrc.gov Tel.: 301-415-1451 CC: Anthony Mendiola; Leonard Ward Mail Envelope Properties (47E02617.E7C : 12 : 35330)
Subject:
Monticello - Draft RAI re. proposed amendment on recirculation riser diff. pressure (TAC MD6864)
Creation Date 03/18/2008 4:29:11 PM From: Peter Tam
Created By: PST@nrc.gov Recipients Action Date & Time nmcco.com Transferred 03/18/2008 4:29:49 PM Jesus.Arias (Jesus Arias)
Richard.Loeffler (Rick Loeffler) tmblake (Timothy Blake) nrc.gov TWGWPO01.HQGWDO01 Delivered 03/18/2008 4:29:21 PM AJM CC (Anthony Mendiola) Opened 03/19/2008 7:17:27 AM nrc.gov TWGWPO04.HQGWDO01 Delivered 03/18/2008 4:29:20 PM LWW CC (Leonard Ward)
Post Office Delivered Route nmcco.com TWGWPO01.HQGWDO01 03/18/2008 4:29:21 PM nrc.gov TWGWPO04.HQGWDO01 03/18/2008 4:29:20 PM nrc.gov Files Size Date & Time MESSAGE 2676 03/18/2008 4:29:11 PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification: None Concealed
Subject:
No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened