March 18, 2008 Mr. Randall K. Edington Executive Vice President Nuclear/CNO Mail Station 7602 Arizona Public Service Company P.O. Box 52034 Phoenix, AZ 85072-2034
SUBJECT:
PALO VERDE NUCLEAR GENERATING STATION, UNIT 3 - COMPLETION OF ACTIONS FOR CONFIRMATORY ACTION LETTER NRR-07-004 (TAC NO. MD4171)
Dear Mr. Edington:
On March 15, 2007, the U.S. Nuclear Regulatory Commission (NRC) issued Confirmatory Action Letter (CAL) No. NRR-07-004 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML070660298) regarding dissimilar metal welds in the pressurizer surge, spray, and safety/relief nozzle-to-safe-end welds at Palo Verde Nuclear Generating Station (Palo Verde), Units 1, 2, and 3. This letter acknowledges receipt of the Arizona Public Service Company (APS) letter dated January 31, 2008 (ADAMS Accession No. ML080390314) informing the NRC of actions taken at Palo Verde, Unit 3, in response to the CAL.
The APS letter dated January 31, 2008, notifies the NRC that the commitment made in APS letter 102-05640, dated January 31, 2007 (ADAMS Accession No. ML070430378), regarding the mitigation of the Palo Verde, Unit 3, pressurizer Alloy 82/182 butt welds was completed during refueling outage U3R13 and post-mitigation inspections were performed. The letter states that, as a result of the completion of the mitigation of the Palo Verde, Unit 3, pressurizer Alloy 82/182 butt welds, APS has satisfied the commitment to mitigate these welds and is no longer performing enhanced reactor coolant system leakage monitoring at Palo Verde, Unit 3.
Based on the APS letter, the NRC staff concluded that all the commitments listed in the CAL and the supporting commitment letters (ADAMS Accession Nos. ML070430378 and ML070590212) have been met for Palo Verde, Unit 3. With respect to Palo Verde, Unit 3, no further response is required regarding the CAL and it is no longer necessary to implement enhanced inspection and leakage monitoring requirements for the reactor coolant system. This action closes TAC No. MD4171.
Thank you for informing us of the actions documented in your letter. These actions may be examined during a future NRC inspection of your facility.
Since the CAL addressed all Palo Verde units, it will remain open until all CAL commitments pertaining to Palo Verde, Unit 2, are complete. APS satisfied the CAL for Unit 1 in 2007.
Current NRC guidance regarding CALs is contained in the NRC Enforcement Policy and the NRC Enforcement Manual, which are available at the NRC web site at http://www.nrc.gov/about-nrc/regulatory/enforcement.html (click on Enforcement Policy or Enforcement Guidance) or by contacting the Government Printing Office (GPO) toll-free at 1-888-293-6498. The GPO is open from 7:00 a.m. to 9:00 p.m. EST, Monday through Friday (except Federal holidays).
In accordance with Title 10 of the Code of Federal Regulations, Part 2, Section 390, of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),
accessible from the NRC Web site at http://www.nrc.gov/reading-rm.html.
Sincerely,
/RA/
Catherine Haney, Director Division of Operating Reactor Licensing Docket No. 50-530 cc: See next page
Current NRC guidance regarding CALs is contained in the NRC Enforcement Policy and the NRC Enforcement Manual, which are available at the NRC web site at http://www.nrc.gov/about-nrc/regulatory/enforcement.html (click on Enforcement Policy or Enforcement Guidance) or by contacting the Government Printing Office (GPO) toll-free at 1-888-293-6498. The GPO is open from 7:00 a.m. to 9:00 p.m. EST, Monday through Friday (except Federal holidays).
In accordance with Title 10 of the Code of Federal Regulations, Part 2, Section 390, of the NRC's "Rules of Practice," a copy of this letter will be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system (ADAMS),
accessible from the NRC Web site at http://www.nrc.gov/reading-rm.html.
Sincerely,
/RA/
Catherine Haney, Director Division of Operating Reactor Licensing Docket No. 50-530 cc: See next page DISTRIBUTION:
PUBLIC LPLIV R/F RidsAcrsAcnwMailCenter RidsEdoMailCenter RidsNrrDci RidsNrrDciCpnb RidsNrrDirs RidsNrrDorl RidsNrrDorlLpl4 RidsNrrOd RidsNrrLAJBurkhardt RidsNrrPMMMarkley RidsOEMailCenter RidsOgcRp RidsRgn4MailCenter DPelton, EDO RIV VDricks, OPA, RIV WMaier, SLO RIV TPruett, RIV/DRP/RPB-D JCollins, NRR/DCI TSullivan, NRR ADAMS Accession No. ML080520180
(*) See previous concurrence, (**) Concurrence via e-mail OFFICE DCI/CPNB DCI/CPNB/BC LPL4/PM LPL4/LA LPL4/BC NAME JCollins (*)
TChan (*)
MMarkley (*)
JBurkhardt THiltz, JND for DATE 2/19/08 2/19/08 02/14/2008 2/21/08 2/21/08 OFFICE DCI/D DRP/D, RIV DORL/D NAME MEvans (*)
TVegel, DC for CHaney DATE 2/20/08 3/18/08(**)
3/18/08 OFFICIAL AGENCY RECORD
Palo Verde Nuclear Generating Station 10/19/2007 cc:
Mr. Steve Olea Arizona Corporation Commission 1200 W. Washington Street Phoenix, AZ 85007 Mr. Douglas Kent Porter Senior Counsel Southern California Edison Company Law Department, Generation Resources P.O. Box 800 Rosemead, CA 91770 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 40 Buckeye, AZ 85326 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavillion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Chairman Maricopa County Board of Supervisors 301 W. Jefferson, 10th Floor Phoenix, AZ 85003 Mr. Aubrey V. Godwin, Director Arizona Radiation Regulatory Agency 4814 South 40 Street Phoenix, AZ 85040 Mr. Scott Bauer, Director Regulatory Affairs Palo Verde Nuclear Generating Station Mail Station 7636 P.O. Box 52034 Phoenix, AZ 85072-2034 Mr. Dwight C. Mims Vice President Regulatory Affairs and Plant Improvement Palo Verde Nuclear Generating Station Mail Station 7605 P.O. Box 52034 Phoenix, AZ 85072-2034 Mr. Matthew Benac Assistant Vice President Nuclear & Generation Services El Paso Electric Company 340 East Palm Lane, Suite 310 Phoenix, AZ 85004 Mr. John Taylor Public Service Company of New Mexico 2401 Aztec NE, MS Z110 Albuquerque, NM 87107-4224 Mr. Geoffrey M. Cook Southern California Edison Company 5000 Pacific Coast Hwy Bldg D21 San Clemente, CA 92672 Mr. Robert Henry Salt River Project 6504 East Thomas Road Scottsdale, AZ 85251 Mr. Jeffrey T. Weikert Assistant General Counsel El Paso Electric Company Mail Location 167 123 W. Mills El Paso, TX 79901 Mr. John Schumann Los Angeles Department of Water & Power Southern California Public Power Authority P.O. Box 51111, Room 1255-C Los Angeles, CA 90051-0100 Mr. Brian Almon Public Utility Commission William B. Travis Building P.O. Box 13326 1701 North Congress Avenue Austin, TX 78701-3326 Ms. Karen O'Regan Environmental Program Manager City of Phoenix Office of Environmental Programs 200 West Washington Street Phoenix AZ 85003