ML080510384

From kanterella
Jump to navigation Jump to search

Slides of September 14, 2007, Meeting with Progress Energy Florida, Inc., to Discuss Power Uprates at Crystal River, Unit 3
ML080510384
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 02/15/2008
From:
Progress Energy Florida
To:
Office of Nuclear Reactor Regulation
Bailey S , NRR/ADRO/DORL, 415-1321
References
TAC MD6750
Download: ML080510384 (28)


Text

m -

m m

m m

m m

m m

m m

m m

m m

m m

m SEPTEMBER 14, 2007 Progress Energy

mrm m

m m

nARmA Atten dee Progress Energy G

0 0

0 Danny Roderick Dave Varner Ted Williams Ken Wilson Phil Rose Lewis Wells Bill Peavyhouse Vice President, Nuclear Projects & Construction Manager, Project Support Services Superintendent, Power Uprates Supervisor, Licensing and Regulatory Affairs Senior Engineer, CR3 Licensing Senior Engineer, Nuclear Fuels/Safety Analysis Lead Engineer, Nuclear Engineering Services AREVA

  • Ed Kane
  • Jeff Seals Power Uprate Technical Manager Manager, Reactor Ops and Accident Analysis 2

0 Progress Energy

a Intrnrdlmntinn I'l*nnv, RnrIrirnk II iml V

.*IiA

~

ml I

I

  • Conclusion Danny Roderick C Progress Energy 3

Majo Prjet Organzatio

  • Purpose and Vision P Allow Line Management to Retain Operational Focus P Key Projects
  • Power Level Upgrades
  • Dry Cask Storage
  • Levy County o Critical Skill Sets

" Project Management

" Construction Management S4 A

Progress Energy

M M

M M

M M

M M

n M

M M

M MUR 1.6% Increase 2609 MWt 12MWe A

7 Requested Approval 11/15/07 License Renewal Submittal Requested Approval SG Replacement Design Install A

A 0ITS Changes and A

A\\

Relief Requests Submittal Requested Approval BOP Efficiencies Design Install Low Turbines \\ Generator \\ Heat Exchangers Gain approximately 28 MWe EPU Design Major Pumps \\ Heat Exchangers 8

Increase to A

High Pressure Turbine Retrofit Submittal approximately Requested

[7

-*-07I 3014 MWt Approval 5

N Progress Energy

Level-U-grades

M 40 2007 QProgress Energy 6

n M

M M

M M

M M

M M

M M

M M

M m

M M

o Typical 'Appendix K' Increase of 1.6% to 2609 MWt o Relatively Recent (2002) Uprate to 2568 MW D Appendix K Analyses and Other Reviews Done to 102% of 2568 MWt (2619 MWt)

D MUR Remains Within that Value 100.4% of 2609 (2619 MWt)

D With Exception of Containment Analysis, the Previous Review and Approval is Bounding 7

0 Progress Energy

e The Only Significant New Analytical Effort was Associated with Containment Analysis o

Utilized Current LOCA Evaluation Model (RELAP) to Calculate Mass and Energy Release for LOCA and Approved GOTHIC Model to evaluate limiting Reactor Building Response (Previous Analysis used CRAFT/CONTEMPT) o Condensing Surface Area Input was Increased from Value in FSAR but Large Margin Retained o

Initially Submitted as Revision 0 of the LAR.

Ultimately Reviewed and Approved Under 50.59 1

C Progress Energy 0

Unncert-a-imnt-*Reductonm CALDON Check-Plus LEFM System for Highly Accurate Feedwater Flow and Temperature Measurement o

Significantly Improved Feedwater Pressure, and Main Steam Pressure and Temperature Measurements o

Rigorous Input Calculations to CR-3 Standards o

Rigorous Heat Balance Uncertainty Calculation o

Consistent Treatment Within Fixed Incore Detector Monitoring System and Automated Unit Load Demand.

CR-3 Uses the Secondary Heat Balance to:

D Calibrate the NI's (FIDMS)

D Automatically Control Output to RTP (AULD) tu Progress Energy

  • UUI []

Changes

  • Original Design had LEFM Immediately Downstream of Installed Flow Straighteners
  • Alden Testing Results P Flow Straightener Adversely Impacted LEFM
  • Tested With and Without Flow Straighteners
  • Reconfiguring 'A' Train Without Straightener and 'B' with Straightener Downstream 10 Progress Energy i

m m

m m

m m

m m

m m

m m

m m

m m

m m

m 11%,0-Nq p en m m. Im e I

PROGRESS ENERGY vCITlrM.

LOU M Pipe Confiigurnatlan -

LODP A Sketch P~w CorfurtlmU-oa~p A 1 1 1 A

.CrTmrH Nn.

lI3H[TI

-V)

SKETCH NO.

ISHEETI NEW (

0-200071 K Progress Energy 11

m m

m m

m m

m m

m m

m m

m m

m m

m m

m

--Oý p.p"

'0OF "Wv-f I Mz Ia I

PREKiRESS ENERGY RMmL mvm Wmar m Pipe ConfIguor*lan Skotch Pipe Canflgur*tbn 1

A mETCIH NO.

ISHEETI WV U 00 C Progress Energy 12

m m mm m

m mmmmm e MUR Does NOT Result in Significant Changes P Constant RCS T avg of 579 F P RCS T hot and T cold changes < -0.4 F D FW/MS Flow Changes of -1.6 %

0 Instrument Changes are Additions Not Replacement e Unique Interface with Grid Limits Impact of MUR/EPU 0-20071 13 Progress Energy

RSIC ARDINTRACE 7

  • -200701 0Progress Energy 14

-M M

M M

M M

M M

M m

m

  • Electrical o Recall that CR3 Output is to 500 kV grid and Offsite Power Sources are the 230 kV grid D Re-ran Transmission Calculations (Capacity, Stability, etc) for Uprates D MUR (nor EPU) Adversely Impacts Grid Stability
  • Operations/Human Factors D Thorough Review of All EP/AP Actions D No Significant Impacts Identified D Testing, Training and Simulator Impacts All Addressed through our normal Engineering Change processes U

15 Progress Energy

m m

M-m M

Mn M

Mm---

M M-MMM Mm M

M m

M

  • Fire Protection P No Changes in Mitigation Systems P No New SSC's Which Require Protection o Minor Increase in IB Combustibles / Time to Shutdown
  • Systems D Changes in System Flow and Pressures Not Expected to Impact IST Results
  • Programs D FAC Model Conservatively Updated to Screen for Major Impacts D FAC Model Being Fully Updated for MUR and EPU M

2007 16 Progress Energy

m m

m

-mm-mm

-m Reactor Vessel Materials Program 32 EFPY Calculations Retained 7 % Fluence Margin.

2002 and MUR Uprates < 7 % Impact o All Other Details Handled As Part of Robust Owners Group Program 17 J Progress Energy

M n

m M

M

-M M

M M

MM

ý M

M Abnra Ope0.tion o

Loss of LEFM (and Associated Equipment) will be Controlled by Minor Revision to RPS Technical Specifications.

o Working with NRC and FENOC/Davis Besse for Consistency o

Alarms will Alert Operator about Losses of Required Equipment o

12 Hours to Reduce Power (Prompt, but with Time to Properly Manage Reactivity Change) o 48 Hours to Reduce RPS Overpower Trip Set-point from 104.9 to 103.3 (Allows Reasonable Time to Schedule)

Progress Energy Iý 1'U

m m

M M

M M

M M

M MMM Tehia Seciiato Changes

  • ITS Changes are Due to Required LSSS Change.
  • Do Not Consider it Necessary to Modify SR.

P Existing Secondary Heat Balance Adequate Mw.

up to 2568 P Improved Secondary Heat Balance Needed above 2568 Mw.

e Completion Times Appropriate.

e CR3 Operated Consistent with RIS 2007-21.

1 2007 0Progress Energy 19

  • CR3 Installing All MUR Related Modifications and Implementing Procedure Changes to Support Operation at 2609 MWt Upon Restart from Fall Outage (early December).

o By Mid-October We Need to Know When the NRC Expects to Issue SER.

20 Progress Energy

n 0

0 0

0 Will Follow.NRC Guidance Will Extensively Utilize Industry Experience Expect 3014 MWt RTP Some Changes will have been Accomplished Through Other Projects D Step-up Transformers Replaced in 2007 D Turbines and Generator Modified in 2009 D Steam Generator Replacement Completed in 2009 CProgress Energy 21

Exene Pow er Upra BOP Evaluation Completed (AREVA/Progress Energy).

Identified Needed Major Components and System Changes o

Selecting Vendor to Complete Component Specifications, Conceptual and Final Designs o

NSSS Evaluation Underway (AREVA)

D Complete Accident and Transient Reanalysis D Any New Methods Will be Pursued Separately D Preliminary Fuel Cycle Designs for Next Four Cycles SProgress Energy M

44

0 FOCUS AR EA

  • As Requested, We Are Evaluating Separable Parallel. These Include:

o Boron Precipitation 0 Small and Intermediate LOCAs

  • Secondary Depressurization
  • Core Flood Line Break P LOCA Mass and Energy
  • Input Validation s Impacts on Interfacing Systems NsP-e=

CProgress Energy 23

  • CR3 Has a Clear and Current Licensing Basis EPU Raises Decay Heat Load and Impacts Effectiveness of Active Measures RB Sump Modifications Improved Structural Limits which Expands Dump-to-Sump Range SMonitoring Industry OE and Regulatory Feedback
  • Expect Continued Compliance with Current CR3 Licensing Basis Through Minor Modifications and Adjustments to Limits on Various Active Means of Dilution
  • 2007 24 C Progress Energy
  • SBLOCA CLPD Results Within Appendix K Limits
  • Crediting Manual Depressurization Improves PCT Results.

" Improvement Sufficient to Keep All SBLOCA Well Within Appropriate Limits.

" Atmospheric Dump Valves Will be Enlarged.

3CR3 and AREVA Continuing to Evaluate Design Details.

20107 CProgress Energy 25

M M

M

ý M

M M

M M

M M

M M

M

ý

ý e Core Flood Line Break, With Off Site Power and Concurrent Single Failures of Other Train Components.

Produces Unacceptable Results o Cross Ties of DH Trains Would Resolve but Entails Piping Modification Within RB With Multiple New Components and Potential Leak Sites.

a CR3 Exploring Potential Applicability of Licensing Options D Leak-Before-Break D Eliminate Single Failure Based Upon Risk-Informed LOCA Concepts or Other Means e Further Evaluation and Dialogue Required

(*2007_

26 Progress Energy

m m

M M

Mmn M M

m

-M M

M M

  • CA Mas an Enrg
  • EPU Will Result in Higher Energy Release to RB RCS T avg and thus Higher
  • Preliminary Results Acceptable
  • Field Validating Certain Critical Inputs This Outage a Accurate Results Needed to Properly Systems (RB Cooling, RB Spray, and Interface with Other Service Water)

SProgress Energy 7

  • -20071 27

mm-n


nnCncluon mm s

o MUR Proceeding on Schedule o EPU Efforts Well Underway D Using Staff Feedback from Last Meeting D Establishing More Frequent and Communications Regular o Comments or Questions?

2AO07

& Progress Energy 28