Letter to C. Pardee Correction of Administrative Error in Amendment - the Consistency of TSs to Exelon Generation Company Quality Assurance TR (Tac. MD3937 Thru MD3940 and MD3943 Thru MD3948). - Rplacement Pages
ML073540049
Person / Time
Site: Peach Bottom, Byron, Braidwood, Quad Cities  Constellation icon.png
Issue date: 12/19/2007
From:
NRC/NRR/ADRO/DORL/LPLIII-2
To:
Gratton C, NRR, DORL, 415-1055
Shared Package
ml073400651 List:
References
TAC MD3937, TAC MD3940, TAC MD3943, TAC MD3944, TAC MD3945, TAC MD3946, TAC MD3947, TAC MD3948
Download: ML073540049 (10)


Text

(3)

Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectorsin amounts as required; (4)

Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)

Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C.

The license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1)

Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels is not in excess of 3586.6 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein and other items identified in Attachment 1 to this license. The items identified in to this license shall be completed as specified. is hereby incorporated into this license.

(2)

Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 47, and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

(3)

Emergency Planning In the event that the NRC finds that the lack of progress in completion of the procedures in the, Federal Emergency Management Agency's final rule, 44 CFR Part 350, is an indication that a major substantive problem exists in achieving or maintaining an adequate state of emergency preparedness, the provisions of 10 CFR Section 50.54(s)(2) will apply.

Amendment No. 147 (4)

Initial Startup Test Program Any changes to the Initial Test Program described in Section 14 of the FSAR made in accordance with the provisions of 10 CFR 50.59 shall be reported aco'rd.ance with 50.59(b) wihi one month ch change.

(5)

Regulatory Guide 1.97, Revision 2 Compliance The licensee shall submit the final report and a schedule for implementation within six months of NRC approval of the DCRDR.

(6)

Deleted.

(7)

Additional Conditions The Additional Conditions contained in Appendix C, as revised through Amendment No. 146, are hereby incorporated Into this license. The licensee shall operate the facility in accordance with the Additional Conditions.

(8)

Exelon Generation Company shall provide to the Director of the Office of Nuclear Reactor Regulation a copy of any application, at the time it is filed, to transfer (excluding grants of security interests or liens) from Exelon Generation Company to its direct or indirect parent, or to any other affiliated company, facilities for the production, transmission, or distribution of electric energy having a depreciated book value exceeding ten percent (10%) of Exelon Generation Company's consolidated net utility plant, as recorded on Exelon Generation Company's books of account.

(9)

Exelon Generation Company shall have decommissioning trust funds for Braidwood, Unit 1, in the following minimum amount, when Braidwood, Unit 1, is transferred to Exelon Generation Company:

Braidwood Unit 1

$154,273,345 (10)

The decommissioning trust agreement for Braidwood, Unit 1. at the time the transfer of the unit to Exelon Generation Company is effected and thereafter, is subject to the following:

(a)

The decommissioning trust agreement must be in a form acceptable to the NRC.

AMENDMENT NO.

146 material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)

Exelon Generation Company, LLC pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts are required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)

Exelon Generation Company, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by' the operation of the facility.

C.

The license shall be deemed to contain and is subject to the conditions specified in the Commission's regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1)

Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels is not in excess of 3586.6 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein and other items identified in Attachment 1 to this license. The items identified in to this license shall be completed as specified. is hereby incorporated into this license.

(2)

Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 147, and the Environmental Protection Plan contained in Appendix B, both of which are attached to License No. NPF-72, dated

'July 2, 1987, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.

(3)

Emergency Planning In the event that the NRC finds that the-lack of progress in completion of the procedures in the Federal Emergency Management Agency's final rule, 44 CFR Part 350, is an indication that a major substantive problem exists in achieving or maintaining an adequate state of emergency preparedness, the provisions of 10 CFR Section 50.54(s)(2) will apply.

Amendment No. - 147 (4)

Initial Startup Test Program Any changes to the Initial Test Program described in Section 14 of the FSAR made in accordance with the provisions of 10 CFR 50.59 shall be reported in accordance with 50.59(b) within one month of such change.

(5)

Deleted.

(6)

Additional Conditions The Additional Conditions contained in Appendix C, as revised through Amendment No. 146, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Additional Conditions.

(7)

Exelon Genei'ation Company, LLC, shall pi-ovide the Director of the Office of Nuclear Reactor Regulation, a copy of any application, at the time it is filed, to transfer (excluding grants of security interests or liens) from Exelon Generation Company, LLC to its direct or indirect parent, or to any other affiliated company, facilities for the production, transmission, or distribution of electric energy having a depreciated book value exceeding ten percent (10%) of Exelon Generation Company, LLC's consolidated net utility plant, as recorded on Exelon Generation Company, LLC's books of account.

(8)

Exelon Generation Company, LLC, shall have decommissioning trust funds for Braidwood, Unit 2, in the following minimum amount, when Braldwood, Unit 2, is transferred to Exelon Generation Company, LLC:

Braidwood Unit 2

$154,448,967 (9)

The decommissioning trust agreement for Braidwood, Unit 2, at the time the transfer of the unit to Exelon Generation Company, LLC is effected and thereafter, is subject to the following:

(a)

The decommissioning trust agreement must be in a form acceptable to the NRC.

(b)

With respect to the decommissioning trust fund, investments in the securities or other obligations of Exelon Corporation or affiliates thereof, or their successors or assigns are prohibited.

Except for investments tied to market indexes or other non-nuclear sector mutual funds, Investments in any entity owning one or more nuclear power plants are prohibited.

AMENDMENT NO. 146 (3)

Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fiscion detectors in amounts as required; (4)

Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive,,possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)

Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to-possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.

C.

This license shall be deemed to contain and issubject to the conditions specified in the Commission's regulation set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:

(1)

Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of 3586.6 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.

(2)

Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A (NUREG-1 113), as revised through Amendment No 1 52, and the Environmental Protection Plan contained in Appendix B, both of which were-attached to License No. NPF-37, dated February 14, 1985, are hereby incorporated into this license. The licensee shall operate the facility in accbrdance with the Technical Specifications and the. Environmental Protection Plan.

(3)

Deleted.

(4)

Deleted.

(5)

Deleted.

Amendment No..152 (6)

Additional Conditions The Additional Conditions contained in Appendix C, as revised through Amendment No. 151, are hereby incorporated into this license. The licensee shall operate the facility in accordance with the Additional Conditions.

(7)

Exelon Generation Company, LLC shall provide the Director of the Office of Nuclear Reactor Regulation, a copy of any application, at the time it is filed, to transfer (excluding grants of security interests or liens) from Exelon Generation Company, LLC to its direct or indirect parent, or to any other affiliated company, facilities for the production, transmission, or distribution of electric energy having a depreciated book value exceeding ten percent (10%) of Exelon Generation Company, LLC's consolidated net utility plant, as recorded on Exelon Generation Company, LLC's books of account.

(8)

Exelon Generation Company, LLC shall have decommissioning trust funds for Byron, Unit 2, In the following minimum amount, when Byron, Unit 2, is transferred to Exelon Generation Company, LLC:

Byron Unit 2

$156,560,489 (9)

The decommissioning trust agreement for Byron, Unit 2, at the time the transfer of the unit to Exelon Generation Company, LLC is effected and thereafter, is subject to the following:

(a)

The decommissioning trust agreement must be in a form acceptable to the NRC.

(b)

With respect to the decommissioning trust fund, investments in the securities or other obligations of Exelon Corporation or affiliates thereof, or their successors or assigns are prohibited.

Except for investments tied to market indexes or other non-nuclear sector mutual funds, investments in any entity owning one or more nuclear power plants are prohibited.

AMENDMENT NO.

151

(5)

Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not to separate, such byproduct and special nuclear material as may be produced by operation of the facility.

C.

This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter l: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Section 50.54 of Part 50, and Section 70.32 of Part 70; all applicable provisions of the Act and-the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:

(1)

Maximum Power Level Exelon Generation Company is authorized to operate the Peach Bottom Atomic Power Station, Unit 2, at steady state reactor core power levels not in excess of 3514 megawatts thermal.

(2)

Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No.265 are hereby incorporated in the license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications.

(3)

Physical Protection Exelon Generation Company shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification,.and safeguards contingency plans, including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans', submitted by letter dated May 17, 2006, is entitled: "Peach Bottom Atomic Power Station Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 3." The set contains Safeguards Information protected under 10 CFR 73.21.

.(4)

Fire Protection.

The Exelon Generation Company shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility, and as approved in the NRC Safety Evaluation Report (SER) dated May 23, 1979, and Supplements dated August 14, September 15, October 10 and November 24, 1980, and in the NRC SERs dated September 16, 1993, and August 24, 1994, subject to the following provision:

The Exelon Generation Company may make changes to the approved 1The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.

Renewed License Ne..).R 44 Rlevised by letter dated Oceteber 20, 2004 Revised by, letter dated May 29, 2007 Amendment No. 265 Page 3 t

(5)

Exelon Generation Company, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not to separate, such byproduct and special nuclear material as may be produced by operation of the facility.

C.

This renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Section 50.54 of Part 50, and Section 70.32 of Part 70; all applicable provisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:

(1)

Maximum Power Level Exelon Generation Company is authorized to operate the Peach Bottom Atomic Power Station, Unit No. 3, at steady state reactor core power levels not in excess of 3514 megawatts thermal.

(2)

Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 269, are hereby incorporated in the license. Exelon Generation Company shall operate the facility in accordance with the Technical Specifications.'

(3)

Physical Protection Exelon Generation Company shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans, including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans 2, submitted by letter dated May 17, 2006, is entitled: "Peach Bottom Atomic Power Station Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 3." The set

.contains Safeguards Information protected under 10 CFR 73.21.

(4)

Fire Protection The Exelon Generation Company shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility, and as approved in 1Licensed power level was revised by Amendment No. 250, dated November 22, 2002, and will be implemented following the 14' refueling outage currently scheduled for Fall 2003.

2The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.

Renv..d LAendme No. 2)PR-56 Revised by lettep dated Oeteber 28, 2004 Revisýed by letter dated No~vember 5, 200 rýeyis~d by letter dated May 29, 2007 Amendment No. 269 Page 3 B.

Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 236, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.

C.

The licensee shall maintain the commitments made in response to the March 14, 1983, NUREG-0737 Order, subject to the following provision:

The licensee may make changes to commitments made in response to the March 14, 1983, NUREG-0737 Oder without prior approval of the Commission as long as the change would be permitted without NRC approval, pursuant to the requirements of 10 CFR 50.59. Consistent with this regulation, if the change results in an Unreviewed Safety Question, a license amendment shall be submitted to the NRC staff for review and approval prior to implementation of the change.

D.

Equalizer Valve Restriction Three of the four valves in the equalizer piping between the recirculation loops shall be closed at all times during reactor operation with one bypass valve

'open to allow for thermal expansion of water.

E.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined sets of plans', which contain Safeguards Information protected under 10 CFR 73.21, is entitled: "Quad Cities Nuclear Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 2," submitted by letter dated

'May 17, 2006.

F.

The licensee shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility and as approved in the Safety Evaluation Reports dated July 27, 1979 with supplements dated November 5, 1980, and 1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.

Renewed License No. DPR-29 Amendment No. 236 ovied by lcfer

,itd ma*_ Li20O7 B.

Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 231, are hereby incorporated into this renewed operating 'lc nse IT......

ies I shall eate t

lii with the Technical Specifications.

C.

The license shall maintain the commitments made in response to the March 14, 1983, NUREG-0737 Order, subject to the following provision:

The licensee may make changes to commitments made in response to the March 14, 1983, NUREG-0737 Order without prior approval of the Commission as long as the change would be permitted without NRC approval, pursuant to the requirements of 10 CFR 50.59. Consistent with this regulation, if the change results in an Unreviewed Safety Question, a license amendment shall be submitted to the NRC staff for review and approval prior to implementation of the change.

D.

Equalizer Valve Restriction.

Three of the four valves in the equalizer piping between the recirculation loops shall be closed at all times during reactor operation with one bypass valve open to allow for thermal expansion of water.

E.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans', which contain Safeguards Information protected under 10 CFR 73.21, is entitled:

"Quad Cities Nuclear Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 2,"

submitted by letter dated May 17, 2006.

I F.

The licensee shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility and as approved in the Safety Evaluation Reports dated July 27, 1979 with supplements dated

'The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.

'Renewed License No. DPR-3C Amendment No.

Re.ised by lettc r..ated May,.

., 200:7-231