November 2, 2007 The Honorable Mayor Michael Clancy Shippingport Borough P.O. Box 76 Shippingport, PA 15077

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW

Dear Mayor Clancy:

The U.S. Nuclear Regulatory Commission (NRC) is reviewing an application, submitted by FirstEnergy Nuclear Operating Company (FENOC), for the renewal of the operating licenses for Beaver Valley Power Station (BVPS), Units 1 & 2, located near the town of Shippingport, Beaver County, Pennsylvania. As part of the review of the license renewal application (LRA),

the NRC is preparing a Supplemental Environmental Impact Statement (SEIS) under the provisions of Title 10 of the Code of Federal Regulations Part 51 (10 CFR Part 51), the NRCs regulation that implements the National Environmental Policy Act (NEPA) of 1969.

BVPS is requesting the renewal of its operating licenses for Units 1 and 2 for a period of 20 years beyond the expiration of the current license term, renewing the licenses until July 2036 and March 2047, respectively. The proposed action would include the use and continued maintenance of existing plant facilities and transmission lines; BVPS does not plan to construct or alter any facilities associated with the plant during the period of extended operation.

The NRC staff plans to hold two identical public meetings covering the license renewal review process and NEPA scoping on November 27, 2007, at the Embassy Suites Pittsburgh -

International Airport, 550 Cherrington Parkway, Pittsburgh, PA 15108. The first meeting will convene at 1:30 p.m., and will continue until 4:30 p.m., as necessary. The second meeting will convene at 7:00 p.m., and will continue until 10:00 p.m., as necessary. From November 13 -

16, 2007, the NRC plans to conduct a site audit. You and your staff are invited to attend the public meetings. Your office will receive a copy of the draft SEIS along with a request for comments. The anticipated publication date for the draft SEIS is September 2008.

The Honorable M. Clancy If you have any questions concerning the NRC staffs review of this LRA, please contact the Safety/Environmental Project Manager, Mr. Kent Howard, at 301-415-2989 or by e-mail at KLH1@nrc.gov.

Sincerely,

/RA by Bo Pham for/

Rani Franovich, Branch Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 cc: See next page

ML072920359 OFFICE: LA:DLR PM:DLR:RPB2 PM:DLR:RPB2 BC:DLR:RPB2 NAME: SFigueroa ESayoc KHoward RFranovich (BPham for)

DATE: 11/02/07 11/02/07 11/02/07 11/02/07 Letter to M. Clancey from R. Franovich Dated November 2, 2007

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW DISTRIBUTION:

HARD COPY DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc PBuckberg NMorgan MModes, RI PCataldo, RI DWerkheiser, RI RBellamy, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan Peter P. Sena III President and Chief Nuclear Officer Site Vice President FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 Beaver Valley Power Station 76 South Main Street Mail Stop A-BV-SEB-1 Akron, OH 44308 P.O. Box 4, Route 168 Shippingport, PA 15077 James H. Lash Senior Vice President of Operations Director, Fleet Regulatory Affairs and Chief Operating Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Mail Stop A-GO-14 76 South Main Street 76 South Main Street Akron, OH 44308 Akron, OH 44308 Manager, Site Regulatory Compliance Danny L. Pace FirstEnergy Nuclear Operating Company Senior Vice President, Fleet Engineering Beaver Valley Power Station FirstEnergy Nuclear Operating Company Mail Stop A-BV-A Mail Stop A-GO-14 P.O. Box 4, Route 168 76 South Main Street Shippingport, PA 15077 Akron, OH 44308 Commissioner James R. Lewis Jeannie M. Rinckel West Virginia Division of Labor Vice President, Fleet Oversight 749-B, Building No. 6 FirstEnergy Nuclear Operating Company Capitol Complex Mail Stop A-GO-14 Charleston, WV 25305 76 South Main Street Akron, OH 44308 Director, Utilities Department Public Utilities Commission David W. Jenkins, Attorney 180 East Broad Street FirstEnergy Nuclear Operating Company Columbus, OH 43266-0573 Mail Stop A-GO-15 76 South Main Street Director, Pennsylvania Emergency Akron, OH 44308 Management Agency 2605 Interstate Dr.

Manager, Fleet Licensing Harrisburg, PA 17110-9364 FirstEnergy Nuclear Operating Company Mail Stop A-GO-2 Dr. Judith Johnsrud 76 South Main Street Environmental Coalition on Nuclear Power Akron, OH 44308 Sierra Club 433 Orlando Avenue Ohio EPA-DERR State College, PA 16803 ATTN: Zack A. Clayton P.O. Box 1049 Columbus, OH 43266-0149

Beaver Valley Power Station, Units 1 and 2 cc:

Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mr. William Green Secretary, Shippingport Borough Shippingport Borough P.O. Box 76 Shippingport, PA 15007