Letter Sequence Withholding Request Acceptance |
---|
|
|
|
|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] Category:Proprietary Information Review
MONTHYEARML13032A5402013-02-14014 February 2013 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report ML12262A3852012-10-10010 October 2012 Request for Withholding Proprietary Information from Public Disclosure Relate to Extended Power Uprate ML12240A1192012-09-20020 September 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate ML12255A4092012-09-13013 September 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report ML12202A7342012-08-0101 August 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report ML12031A0322012-03-26026 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related to Extended Power Uprate Technical Report ML12053A2312012-03-0202 March 2012 Request for Withholding Proprietary Information from Public Disclosure Related Extended Power Uprate Technical Report ML11265A2632011-10-12012 October 2011 ISFSI, Shearon Harris Unit 1, H. B. Robinson, Unit 2, H. B. Robinson ISFSI, Crystal River, Unit 3, Request for Withholding Information from Public Disclosure ML11172A3432011-06-22022 June 2011 Request for Withholding Proprietary Information from Public Disclosure Related to the Development of Confirmatory Loss-of-Coolant and Non-LOCA Models in Support of Its Upcoming Extended Power Uprate ML0932704962009-12-10010 December 2009 Areva Np, Inc. - Request for Withholding Information from Public Disclosure for Crystal River Unit 3 Nuclear Generating Plant ML0922300132009-08-12012 August 2009 NRC Response to Crystal River Nuclear Plant, Unit No. 3 - Request for Withholding Information from Public Disclosure ML0725701222007-11-0909 November 2007 Progress Energy Florida, Inc. - Request for Withholding of Proprietary Information from Public Disclosure for Crystal River Nuclear Plant, Unit No. 3 ML0725700792007-11-0909 November 2007 Progress Energy Florida, Inc. - Request for Withholding of Proprietary Information from Public Disclosure for Crystal River Nuclear Plant, Unit No. 3 ML0330700492003-11-0303 November 2003 Framatome Anp, Inc. Request for Withholding Information from Public Disclosure ML0233802912002-12-0404 December 2002 Proprietary Information Review, Framatome Anp Request for Withholding Information from Public Disclosure ML0233802582002-12-0404 December 2002 Proprietary Information Review, Framatome Anp Request for Withholding Information from Public Disclosure 2013-02-14
[Table view] |
Text
November 9, 2007 Mr. Dale E. Young, Vice President Crystal River Nuclear Plant (NA1B)
ATTN: Supervisor, Licensing & Regulatory Programs 15760 W. Power Line Street Crystal River, Florida 34428-6708
SUBJECT:
PROGRESS ENERGY FLORIDA, INC. - REQUEST FOR WITHHOLDING OF PROPRIETARY INFORMATION FROM PUBLIC DISCLOSURE FOR CRYSTAL RIVER NUCLEAR PLANT, UNIT NO. 3 (TAC NO. MD3308)
Dear Mr. Young:
By letter dated April 4, 2007, you submitted an affidavit dated April 2, 2007, executed by Debabrata Mitra-Majumdar, Holtec International Project Manager for the Crystal River Criticality Analysis for Additional Storage Patterns Project (Holtec Project 1566), requesting that the information contained in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 2, Section 2.390:
Holtec Report No. HI-2063579: Licensing Report for Additional Loading Patterns in Crystal River Unit 3 Pools A and B (Proprietary), dated September 20, 2006.
A nonproprietary copy of this document has been placed in the U.S. Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
(a) The information discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by Holtec's competitors without license from Holtec International constitutes a competitive economic advantage over other companies.
(b) The information is such that, if used by a competitor, it would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.
D. Young Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future; for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1321.
Sincerely,
/RA/
Stewart N. Bailey, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-302 cc: See next page
November 9, 2007 D. Young Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.
If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future; for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.
If you have any questions regarding this matter, I may be reached at 301-415-1321.
Sincerely,
/RA/
Stewart N. Bailey, Senior Project Manager Plant Licensing Branch II-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-302 cc: See next page DISTRIBUTION:
PUBLIC LPL2-2 R/F RidsNrrPMSBailey RidsNrrLABClayton RidsNrrDorlLpl2-2 RidsNrrDssSrsb RidsOgcRp RidsAcrsAcnwMailCenter RidsRgn2MailCenter MVaaler ADAMS Accession Number: ML072570079 NRR-084 OFFICE LPL2-2 LPL2-2/PM LPL2-2/LA SRSB/BC LPL2-2/BC NAME MVaaler SBailey BClayton GCranston EMarions for TBoyce DATE 09/14/07 11/09/07 09/14/07 10/22/07 11/09/07 OFFICIAL RECORD COPY
Mr. Dale E. Young Crystal River Nuclear Plant, Unit 3 Florida Power Corporation cc:
Mr. R. Alexander Glenn Mr. Jon A. Franke Associate General Counsel (MAC-BT15A) Director Site Operations Florida Power Corporation Crystal River Nuclear Plant (NA2C)
P.O. Box 14042 15760 W. Power Line Street St. Petersburg, Florida 33733-4042 Crystal River, Florida 34428-6708 Mr. Michael J. Annacone Senior Resident Inspector Plant General Manager Crystal River Unit 3 Crystal River Nuclear Plant (NA2C) U.S. Nuclear Regulatory Commission 15760 W. Power Line Street 6745 N. Tallahassee Road Crystal River, Florida 34428-6708 Crystal River, Florida 34428 Mr. Jim Mallay Ms. Phyllis Dixon Framatome ANP Manager, Nuclear Assessment 1911 North Ft. Myer Drive, Suite 705 Crystal River Nuclear Plant (NA2C)
Rosslyn, Virginia 22209 15760 W. Power Line Street Crystal River, Florida 34428-6708 Mr. William A. Passetti, Chief Department of Health David T. Conley Bureau of Radiation Control Associate General Counsel II - Legal Dept.
2020 Capital Circle, SE, Bin #C21 Progress Energy Service Company, LLC Tallahassee, Florida 32399-1741 Post Office Box 1551 Raleigh, North Carolina 27602-1551 Attorney General Department of Legal Affairs Mr. Daniel L. Roderick The Capitol Vice President, Nuclear Projects &
Tallahassee, Florida 32304 Construction Crystal River Nuclear Plant (SA2C)
Mr. Craig Fugate, Director 15760 W. Power Line Street Division of Emergency Preparedness Crystal River, Florida 34428-6708 Department of Community Affairs 2740 Centerview Drive Mr. David Varner Tallahassee, Florida 32399-2100 Manager, Support Services - Nuclear Crystal River Nuclear Plant (SA2C)
Chairman 15760 W. Power Line Street Board of County Commissioners Crystal River, Florida 34428-6708 Citrus County 110 North Apopka Avenue Inverness, Florida 34450-4245 Mr. Stephen J. Cahill (Acting)
Engineering Manager Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, Florida 34428-6708