Letter Sequence Acceptance Review |
---|
|
|
|
|
---|
Category:Letter
MONTHYEARML24264A0232024-09-20020 September 2024 RAI TSTF-600, Rev. 0, Revise the Reactor Coolant System (RCS) Pressure Isolation Valve (PIV) Leakage Testing Frequency ML24249A1482024-09-11011 September 2024 Cover Letter for Final Traveler SE of TSTF 576, Revision 3, Revise Safety/Relief Valve Requirements ML24247A3162024-09-0606 September 2024 Cover Letter for Final Model SE of Traveler TSTF 592, Rev 2, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24222A4002024-08-14014 August 2024 TSTF-602, Revise the Ventilation Filter Testing Program to Permit Alternate Challenge Agents, Acceptance Review Letter ML24106A2762024-08-0101 August 2024 Draft Safety Evaluation of Technical Specifications Task Force Traveler TSTF-576, Revision 3, Revise Safety/Relief Valve Requirements (EPID L -2019-PMP-0207) ML24207A1822024-07-25025 July 2024 TSTF-601, Extend Shield Building Completion Time After Refueling, Acceptance Review Letter ML24114A2572024-04-24024 April 2024 TSTF-599 Acceptance Review Letter ML24114A2652024-04-24024 April 2024 TSTF-597 Acceptance Review Letter ML23325A2132023-12-18018 December 2023 Cover Letter for Final Model SE of TSTF-591, Revise Risk Informed Completion Time (RICT) Program ML23262B2292023-09-21021 September 2023 Cover Letter Transmitting Final SE of TSTF-591, Revision 0, Revise Risk-Informed Completion Time (RICT) Program ML23124A2212023-09-11011 September 2023 Cover Letter for Final SEs of TSTF-589, Eliminate Automatic Diesel Generator (DG) Start During Shutdown ML23206A1242023-07-31031 July 2023 TSTF-584 Cover Letter for Final SE ML23205A2342023-07-0606 July 2023 Draft TSTF-601, Extend Shield Building Completion Time After Refueling ML23012A2812023-03-13013 March 2023 Draft SEs of TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation ML23059A3342023-02-28028 February 2023 TSTF-576 Open Issues Letter ML23010A2592023-01-11011 January 2023 Request for Additional Information Traveler TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22272A5542022-10-0707 October 2022 Request for Additional Information Traveler TSTF-591, Revise Risk Informed Completion Time (RICT) Program TSTF-22-07, Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2022-07-19019 July 2022 Transmittal of TSTF-592, Revision 0, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML22193A2372022-07-12012 July 2022 Request for Additional Information TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown TSTF-22-06, Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability2022-07-0808 July 2022 Technical Specifications Task Force - Request for a Workshop to Discuss the Interaction of Natural Phenomena Protection Design Features and Operability ML22110A1712022-04-26026 April 2022 Acceptance for Review Regarding Traveler Tstf-584, Rev 0, Eliminate Automatic RWCU System Isolation on SLC Initiation TSTF-22-04, Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program2022-03-22022 March 2022 Technical Specifications Task Force - Transmittal of TSTF-591, Revision 0, Revise Risk Informed Completion Time (RICT) Program ML21188A2782021-07-11011 July 2021 Cover Letter Transmitting Final SEs of CLIIP TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR (Residual Heat Removal) Shutdown Cooling TSTF-21-03, TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 12021-06-23023 June 2021 TSTF Response to NRC Questions on TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements and Submittal of Revision 1 ML21054A2512021-05-26026 May 2021 Cover Letter Transmitting Draft SEs of CLIIP TSTF-580, RHR Shutdown Cooling System - Hot Shutdown ML21106A2452021-04-20020 April 2021 Cover Letter Transmitting Final Model SE of TSTF 554, Revision 1, Revise Reactor Coolant Leakage Requirements ML21098A2422021-04-14014 April 2021 Cover Letter for Final SEs of TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections ML21068A4012021-03-24024 March 2021 Cover Letter for Draft SEs TSTF 577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections TSTF-21-01, Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2021-01-26026 January 2021 Transmittal of TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML20322A3612020-12-18018 December 2020 TSTF-554 Cover Letter for Final SE ML20308A6562020-11-0606 November 2020 Request for Additional Information Traveler TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20168A3962020-10-30030 October 2020 Cover Letter Transmitting Draft SE of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements ML20265A1152020-10-0909 October 2020 Cover Letter Transmitting Model SE of TSTF-582 and TSTF-583-T ML20133J8832020-07-29029 July 2020 Letter Transmitting Draft SE of Traveler TSTF-582, Revision 0, RPV WIC Enhancements TSTF-20-04, Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections2020-06-0808 June 2020 Technical Specifications Task Force - Transmittal of TSTF-577, Revision 0, Revised Frequencies for Steam Generator Tube Inspections ML20133J8152020-05-13013 May 2020 Letter Transmitting Revised Final SE of Traveler TSTF-564, Revision 2, Safety Limit MCPR, Using the Consolidated Line Item Improvement Process ML20132A1832020-05-11011 May 2020 Request for Additional Information TSTF-576, Revision 0, Revised Safety/Relief Valve Requirement TSTF-20-01, Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP)2020-04-0909 April 2020 Transmittal of TSTF-IG-20-02, Guidance on Evaluating One-Time Surveillance Frequency Changes Under the Surveillance Frequency Control Program (TSTF-425M SFCP) TSTF-19-14, Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements2020-02-12012 February 2020 Technical Specifications Task Force - TSTF Response to NRC Questions on TSTF-582, RPV WIC Enhancements TSTF-19-11, TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements2020-01-16016 January 2020 TSTF Response to NRC Questions on TSTF-554, Revise Reactor Coolant Leakage Requirements ML19325C4362019-12-17017 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-568, Revision 2, Revise Applicability of BWR/4 TS 3.6.2.5 and TS 3.6.3.2 TSTF-19-09, Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements2019-12-13013 December 2019 Technical Specifications Task Force - Transmittal of TSTF-576, Revision 0, Revise Safety/Relief Valve Requirements ML19323E9282019-12-10010 December 2019 Cover Letter Transmitting Final SEs of Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position TSTF-19-13, Technical Specifications Task Force - Updated TSTF Membership and Distribution2019-12-0303 December 2019 Technical Specifications Task Force - Updated TSTF Membership and Distribution TSTF-19-12, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position.2019-11-0505 November 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position. TSTF-19-10, Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2019-08-28028 August 2019 Transmittal of Errata Changes to TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML19176A1892019-08-14014 August 2019 Cover Letter Transmitting Final Safety Evaluations of Traveler TSTF-569, Revision 2, Revise Response Time Testing Definition TSTF-19-03, Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter2019-07-0808 July 2019 Request for Fee Exemption for TSTF-554, Revision 0, Revise Reactor Coolant Leakage Requirements - Letter TSTF-19-08, Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements.2019-07-0303 July 2019 Draft of Traveler TSTF-582, Revision 0, RPV WIC Enhancements. TSTF-19-06, TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition2019-06-25025 June 2019 TSTF Comments on Draft Safety Evaluations for Traveler TSTF-569, Revision 1, Revise Response Time Testing Definition 2024-09-06
[Table view] Category:Schedule and Calendars
MONTHYEARML0812300832008-05-0202 May 2008 Initial Schedule for Review of TSTF-506 ML0724706932007-09-14014 September 2007 Acceptance for Review and Establishment of Milestone Schedule for TSTF Traveler 446, Revision 2, Risk Informed Eval. of Extensions to Containment Isolation Valve Completion Times (WCAP-15791) Docket No: PROJ0753 ML0706801202007-03-16016 March 2007 TSTF Status Spreadsheet ML0632003862006-11-16016 November 2006 TSTF Traveler Milestone Schedule (11-16-06 R1 Snapshot) 2008-05-02
[Table view] |
Text
September 14, 2007 Technical Specifications Task Force (TSTF) 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
ACCEPTANCE FOR REVIEW AND ESTABLISHMENT OF MILESTONE SCHEDULE FOR TSTF TRAVELER 446, REVISION 2, RISK INFORMED EVAL.
OF EXTENSIONS TO CONTAINMENT ISOLATION VALVE COMPLETION TIMES (WCAP-15791) DOCKET NO: PROJ0753 (TAC MD6031)
Dear Members of the TSTF:
By letter (ADAMS Accession Number ML071630408), dated June 12, 2007, you requested the Nuclear Regulatory Commission (NRC) to review, approve, and make available under the Consolidated Line Item Improvement Process (CLIIP), TSTF Traveler 446, Revision 2, Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791).
Technical staff have completed a preliminary review of your submission and determined it to be sufficiently complete and an appropriate submission to initiate a more comprehensive review, consistent with your request. The scheduled milestones to make TSTF Traveler 446, Revision 2, available under the CLIIP are attached as an enclosure.
Should circumstances lead to anticipated or actual schedule slippage, the causing party should promptly inform and coordinate with the impacted party to reach a new agreement and publish an appropriately revised schedule. This is of particular importance in connection with TSTF response to NRC staff requests for additional information (RAIs) as failure to provide a timely responsive reply, in accordance with the agreed schedule, or to successfully negotiate a revised schedule, may result in termination of the review process and closure of the TAC. Early completion of any activity will not necessitate schedule revision. Schedule revisions will be published by letter similar to this and will remain in effect unless superseded by another published schedule. The current published schedule will be posted to the NRC Inspection Technical Specifications Branch (ITSB) web page.
Tim Kolb (301-415-1428; Email: tck@nrc.gov has been assigned as the Technical Specifications Branch (ITSB) project lead. Please contact Mr. Kolb in coordinating activities specific to this review. Matthew Hamm may also be contacted at (301) 415-1472 or meh1@nrc.gov in the event Mr. Kolb is unavailable or should you have questions or need further information in connection with the TSTF traveler review process or other ongoing TSTF traveler reviews.
Sincerely,
/RA/
Timothy J. Kobetz, Chief Technical Specifications Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: See attached list
Technical Specifications Task Force (TSTF) September 14, 2007 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
ACCEPTANCE FOR REVIEW AND ESTABLISHMENT OF MILESTONE SCHEDULE FOR TSTF TRAVELER 446, REVISION 2, RISK INFORMED EVAL.
OF EXTENSIONS TO CONTAINMENT ISOLATION VALVE COMPLETION TIMES (WCAP-15791) DOCKET NO: PROJ0753 (TAC MD6031)
Dear Members of the TSTF:
By letter (ADAMS Accession Number ML071630408), dated June 12, 2007, you requested the Nuclear Regulatory Commission (NRC) to review, approve, and make available under the Consolidated Line Item Improvement Process (CLIIP), TSTF Traveler 446, Revision 2, Risk Informed Evaluation of Extensions to Containment Isolation Valve Completion Times (WCAP-15791).
Technical staff have completed a preliminary review of your submission and determined it to be sufficiently complete and an appropriate submission to initiate a more comprehensive review, consistent with your request. The scheduled milestones to make TSTF Traveler 446, Revision 2, available under the CLIIP are attached as an enclosure.
Should circumstances lead to anticipated or actual schedule slippage, the causing party should promptly inform and coordinate with the impacted party to reach a new agreement and publish an appropriately revised schedule. This is of particular importance in connection with TSTF response to NRC staff requests for additional information (RAIs) as failure to provide a timely responsive reply, in accordance with the agreed schedule, or to successfully negotiate a revised schedule, may result in termination of the review process and closure of the TAC. Early completion of any activity will not necessitate schedule revision. Schedule revisions will be published by letter similar to this and will remain in effect unless superseded by another published schedule. The current published schedule will be posted to the NRC Inspection Technical Specifications Branch (ITSB) web page.
Tim Kolb (301-415-1428; Email: tck@nrc.gov has been assigned as the Technical Specifications Branch (ITSB) project lead. Please contact Mr. Kolb in coordinating activities specific to this review. Matthew Hamm may also be contacted at (301) 415-1472 or meh1@nrc.gov in the event Mr. Kolb is unavailable or should you have questions or need further information in connection with the TSTF traveler review process or other ongoing TSTF traveler reviews.
Sincerely,
/RA/
Timothy J. Kobetz, Chief Technical Specifications Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
Enclosure:
As stated cc: See attached list DISTRIBUTION:
ITSB r/f NRR_Dirs_Itsb staff RidsNrrAdro RidsNrrDirsItsb ADAMS ACCESSION NO: ML071440183 OFFICE ITSB:DIRS ITSB:DIRS ITSB:DIRS NAME MEHamm TCKolb TJKobetz DATE 09/6/07 09/7/07 09/14/07 OFFICIAL RECORD COPY
Technical Specifications Task Force Mailing List cc:
Techncial Specifications Task Force Donald R. Hoffman 11921 Rockville, Pike EXCEL Services Corporation Suite 100 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Rockville, MD 20852 George G. Yates Brian Mann AmerenUE Callaway Plant EXCEL Services Corporation Junction Hwy. CC and Hwy. O 11921 Rockville Pike, Suite 100 Mail Code CA-460 Rockville, MD 20852 P.O. Box 620 Fulton, MO 65251 Jim Kenny 924 Liberty Street John Messina Emmaus, PA 18049 First Energy Nuclear Operating Company 76 South Main Street Mail Sto: Akron-GO-14 Akron, OH 44308 David Bice Entergy N-GSB64 Russellville, AR 72802 Reene V. Gambrell Duke Energy Mailcode: ON03RC 7800 Rochester Highway Seneca, SC 29672
Milestones for CLIIP review of TSTF Traveler 446, Revision 2, Risk Informed Eval. of Extensions to Containment Isolation Valve Completion Times (WCAP-15791) Docket No: PROJ0753 (TAC MD6031) ScheduleDate Issue Request for Additional Information (RAI), if applicable 10/12/07 Receive TSTF RAI response letter, if applicable 11/30/07 Issue Draft TSTF Traveler to Federal Register Notice for Comment (FR NFC) 01/31/08 Issue Final TSTF Traveler Federal Register Notice of Availability (FR NOA) 04/30/08 Enclosure