MONTHYEARML0620600262006-10-0303 October 2006 Request for Additional Information Regarding License Renewal, Oregon State University Triga Reactor Project stage: RAI ML0632101822006-11-10010 November 2006 Oregon State University Triga Reactor (Ostr), Request for Extension 60 Days to Respond to the Request for Additional Information Regarding License Renewal Project stage: Request ML0633205002006-11-21021 November 2006 Oregon State University Response to Request for Additional Information Regarding License Renewal, Osu Triga Reactor, Dated October 3, 2006 Project stage: Response to RAI ML0713000102007-05-21021 May 2007 Oregon State University - Request for Additional Information Regarding License Renewal Request Project stage: RAI ML0714503072007-06-0707 June 2007 Determination of Acceptability and Sufficiency for Docketing and Opportunity for a Hearing Regarding the Application from the Oregon State University for Renewal of the Facility License for the Oregon State University Triga Reactor (OSTR) Project stage: Other ML0723305292007-06-25025 June 2007 Oregon State University Triga Reactor, Request for Extension of 45 Days to Respond to the RAI Re License Renewal, Dated May 21, 2007 Project stage: Request ML0721503622007-07-10010 July 2007 Oregon State University Response to RAI Regarding License Renewal, Oregon State University Triga Reactor Dated May 21, 2007 Project stage: Response to RAI ML0721503632007-07-27027 July 2007 Additional Oregon State University Response to RAI Regarding License Renewal, Oregon State University Triga Reactor Dated May 21, 2007 Project stage: Response to RAI ML0721900432007-07-31031 July 2007 Oregon State University Triga Reactor (Ostr), Decommissioning Funding Statement of Intent Project stage: Other ML0723405802007-08-0606 August 2007 Response to Request for Additional Information (RAI) Regarding License Renewal, Oregon State University Triga Reactor Dated May 21, 2007 Project stage: Response to RAI ML0807101392008-03-19019 March 2008 Oregon State University - Request for Additional Information Regarding License Renewal Request Project stage: RAI ML0822703832008-08-11011 August 2008 Oregon State University Submission of Relicensing Technical Specifications Revision J Project stage: Request ML0616501972008-09-0202 September 2008 Oregon State University Triga Reactor Environmental Assessment Regarding Amendment for Renewal of Facility Operating License No. R-106 Project stage: Other ML0825305092008-09-10010 September 2008 Technical Specifications for the Renewed Facility License No. R-106 for the Oregon State University Triga Reactor Project stage: Other ML0825200472008-09-10010 September 2008 Issuance of Renewed Facility License No. R-106 for the Oregon State University Triga Reactor Project stage: Approval ML0830203032008-10-30030 October 2008 Massachusetts Institute of Technology-Request for Additional Information Regarding Amendment Request Project stage: RAI ML0832204262008-11-0707 November 2008 Massachusetts Institute of Technology - Response to Request for Additonal Information Regarding Amendment Request Project stage: Request ML0831801352008-11-0707 November 2008 Massachusetts Institute of Technology - Response to Request for Additional Information Regarding Amendment Request Project stage: Response to RAI ML0907506442009-04-24024 April 2009 Massachusetts Institute of Technology - Issuance of Amendment No. 38 Number of Heat Exchangers Required by Technical Specifications Project stage: Approval 2007-07-31
[Table View] |
Text
Radiation Center Oregon State University, 100 Radiation Center, Corvallis, Oregon 97331-5903 T 541-737-2341 I F 541-737-0480 1 http://ne~oregonstate.edu/facilities/radiationcenter Oregon State UNIVERSITY June 25, 2007 Mr. Alexander Adams U. S. Nuclear Regulatory Commission Research and Test Reactors Branch A Office of Nuclear Reactor Regulation Mail Stop 012-G13 One White Flint North 11545 Rockville Pike Rockville, MD 20852-2738
Reference:
Oregon State University TRIGA Reactor (OSTR)
Docket No. 50-243, License No. R-106 Request for Additional Information (RAI) Regarding License Renewal, Oregon State University TRIGA Reactor (TAC NO. MC5155) dated May 21, 2007
Subject:
Request for Extension of 45 days to Respond to the RAI Mr. Hughes:
The RAI letter dated May 21, 2007, requested a response within 45 days from the date of the letter. We would like to request an additional 45 days for a response to the RAI. Due to travel away from work for several of our key staff members, including myself, we have not had the opportunity to thoroughly research and assemble our response. The additional 45 days should be adequate and greatly appreciated.
If you have any questions, please call me at the number above. I declare under penalty of perjury that the foregoing is true and correct.
Executed on:
?/O 7
Sincerely, Director cc:
Document Control, NRC Al Adams, NRC Craig Bassett, NRC John Cassady, OSU Rich Holdren, OSU Todd Palmer, OSU Mike Hartman, OSU