August 7, 2007 Mr. Robert J. Duncan II Vice President Carolina Power & Light Company P.O. Box 165, Mail Zone 1 New Hill, NC 27562
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, LICENSE RENEWAL APPLICATION
Dear Mr. Duncan:
By letter dated November 14, 2006, Carolina Power & Light Company submitted an application pursuant to 10 CFR Part 54, to renew the operating license for Shearon Harris Nuclear Power Plant, Unit 1, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Roger Stewart, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3137 or e-mail MLH5@nrc.gov.
Sincerely,
/RA/
Maurice Heath, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-400
Enclosure:
Requests for Additional Information cc w/encl: See next page
ML072180069 OFFICE LA:DLR PM:RLRA:DLR BC:RLRA:DLR NAME IKing MHeath LLund DATE 08/07/07 08/07/07 08/07/07
DISTRIBUTION:
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, LICENSE RENEWAL APPLICATION HARD COPY DLR R/F E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes MHeath SHernandez LRegner
Shearon Harris Nuclear Power Plant, Unit 1 cc:
David T. Conley Associate General Counsel II -
Legal Department Progress Energy Service Company, LLC P.O. Box 1551 Raleigh, NC 27602-1551 Resident Inspector / Harris NPS c/o U. S. Nuclear Regulatory Commission 5421 Shearon Harris Road New Hill, NC 27562-9998 Ms. Margaret A. Force Assistant Attorney General State of North Carolina P.O. Box 629 Raleigh, NC 27602 Public Service Commission State of South Carolina Post Office Drawer 11649 Columbia, SC 29211 Ms. Beverly Hall, Section Chief Division of Radiation Protection N.C. Department of Environment and Natural Resources 3825 Barrett Drive Raleigh, NC 27609-7721 Mr. J. Paul Fulford, Manager Performance Evaluation and Regulatory Affairs PEB 5 Carolina Power & Light Company P.O. Box 1551 Raleigh, NC 27602-1551 Mr. Eric McCartney Plant General Manager Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 3 New Hill, NC 27562-0165 Mr. Chris L. Burton Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Chairman of the North Carolina Utilities Commission P. O. Box 29510 Raleigh, NC 27626-0510 Mr. Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Mr. Tommy Emerson, Chair Board of County Commissioners of Chatham County P. O. Box 87 Pittsboro, NC 27312 Mr. Thomas J. Natale, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165 Mr. David H. Corlett, Supervisor Licensing/Regulatory Programs Shearon Harris Nuclear Power Plant Carolina Power & Light Company P. O. Box 165, Mail Zone 1 New Hill, NC 27562-0165
Shearon Harris Nuclear Power Plant, Unit 1 cc: Mr. John H. ONeill, Jr.
Shaw, Pittman, Potts & Trowbridge 2300 N Street, NW Washington, DC 20037-1128 Ms. Julie Keys Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-2708
Enclosure SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION (RAIs)
RAI 2.4-1 Section 2.4.1.1 Containment Structure of the license renewal application (LRA), page 2.4-4, states The welded attachments to the metallic liner (e.g., floor beams, seismic restraints, leak channels, equipment/pipe supports, etc.) do not perform a pressure retaining function associated with the containment vessel. For this reason, the welded attachments are not included with the liner components. These welded attachments are evaluated with the specific commodity groups. Please identify these specific component commodity groups, as well as their intended functions, for the welded attachments.
RAI 2.4-2 Section 2.4.1.1 Containment Structure of the LRA, page 2.4-7, states that the insulation for Type II cold penetrations is not in scope because the concrete surrounding the penetration will always be below the maximum local area temperature of 200 0 F.
Please state the criteria employed for determining the inclusion of insulation within the scope.
RAI 2.4-3 Section 2.4.2.12 Emergency Service Water and Cooling Tower Makeup Intake Structure of the LRA, Table 2.4.2-12, does not include screens and stop logs. Clarify whether screens and stop logs are in the scope. If not, provide justification for their exclusion from the scope.
RAI 2.4-4 Section 2.4.2.16 Fuel Handling Building of the LRA, Page 2.4-48, states Design criteria have been used to assure that the collapse of adjacent non-seismic Category I structures would not impair the integrity of the seismic Category I structures or components should an earthquake occur. Please specify what design criteria have been used and explain how these design criteria can assure that the collapse of adjacent non-seismic Category I structures would not impair the integrity of the seismic Category I structures or components.