HNP-07-090, Withdrawal of Request for License Amendment to Use Other Containment Water Level Instruments

From kanterella
(Redirected from ML072110216)
Jump to navigation Jump to search

Withdrawal of Request for License Amendment to Use Other Containment Water Level Instruments
ML072110216
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 07/19/2007
From: Natale T
Progress Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
HNP-07-090
Download: ML072110216 (2)


Text

SERIAL: HNP-07-090 10 CFR 50.90 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 JUL 1 9 2007 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400/LICENSE NO. NPF-63 WITHDRAWAL OF REQUEST FOR LICENSE AMENDMENT TO USE OTHER CONTAINMENT WATER LEVEL INSTRUMENTS Ladies and Gentlemen:

In a letter (Serial: HNP-07-040) dated April 30, 2007, Carolina Power & Light Company doing business as Progress Energy Carolinas, Inc., requested approval of a proposed Technical Specification (TS) change for the Harris Nuclear Plant (HNP). The proposed change was to revise the TS to use other narrow range containment sump water level instruments rather than the existing narrow range containment recirculation sump water level instruments.

This amendment was to support the installation of new strainers in the Emergency Core Cooling System (ECCS) recirculation sumps during refueling outage 14 (RFO-14) in the fall 2007 as part of the response to Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors."

HNP continued to evaluate other options, in addition to the TS change, for modifying the existing ECCS sumps to comply with the commitment made to GL 2004-02. As a result, it was determined that the existing ECCS narrow range sump level instruments could be modified such that the proposed TS change would no longer be needed. On June 7, 2007, HNP discussed the proposed TS change with the NRC via telephone. Following the teleconference, HNP decided to retain the existing ECCS sump level indication in the modified sumps thus eliminating the need to revise the TS. Therefore, HNP requests withdrawal of the proposed TS change to remove ECCS sump level indicators.

Please contact Mr. Dave Corlett with any questions regarding this withdrawal at (919) 362-3137.

Sincerely Tho J. Natale Manager - Site Support Services Harris Nuclear Plant TJN/mse Progress Energy Carolinas, Inc.

Harris Nuclear Plant P. 0 Box 165 New Hill, NC27562 7

SERIAL: HNP-07-090 Page 2 c: Mr. P. B. O'Bryan, NRC Sr. Resident Inspector Ms. L. M. Regner, NRC Project Manager Mr. W. D. Travers, NRC Regional Administrator Ms. B. 0. Hall, Section Chief N.C. DENR