ML072050005

From kanterella
Jump to navigation Jump to search

Conforming License Amendment to Incorporate the Mitigation Strategies Required by Section B.5.b. of Commission Order EA-02-026 (Tac No. MD4579)
ML072050005
Person / Time
Site: Clinton Constellation icon.png
Issue date: 07/26/2007
From: Sands S
NRC/NRR/ADRO/DORL/LPLIII-2
To: Crane C
AmerGen Energy Co
Sands, S, NRR/DLPM/PD3-2, 415-3154
Shared Package
ML072050004 List:
References
EA-02-026, TAC MD4579
Download: ML072050005 (19)


Text

orri si - :n n S UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Ouly 26, 2007 Mr. Christopher M. Crane President and Chief Executive Officer AmerGen Energy Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

CLINTON POWER STATION, UNIT NO. 1 - CONFORMING LICENSE AMENDMENT TO INCORPORATE THE MITIGATION STRATEGIES REQUIRED BY SECTION B.5.b. OF COMMISSION ORDER EA-02-026 (TAC NO. MD4579)

Dear Mr. Crane:

This letter documents the results of the U.S. Nuclear Regulatory Commission (NRC) staff's regulatory assessment of the adequacy of the actions taken by the AmerGen Energy Company, LLC for the Clinton Power Station, Unit No. 1, in response to Section B.5.b. of the February 25, 2002, Interim Compensatory Measures (ICM) Order (EA-02-026) and related NRC guidance.

The ICM Order was issued following the events of September 11, 2001, as part of a comprehensive effort by the NRC, in coordination with other government agencies, to improve the capabilities of commercial nuclear reactor facilities to respond to terrorist threats.

Section B.5.b. of the Order required licensees to develop specific guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities using existing or readily available resources (equipment and personnel) that could be effectively implemented under the circumstances associated with loss of large areas of the plant due to explosions or fire, including those that an aircraft impact might create. Although it was recognized prior to September 11, 2001, that nuclear reactors already had significant capabilities to withstand a broad range of attacks, implementing these mitigation strategies would significantly enhance the plants' capabilities to withstand a broad range of threats. It should be noted that portions of the ICM Order, as well as other documents referenced in this letter, contain security-related or safeguards information, and are not publicly available.

Licensee actions to implement Section B.5.b mitigation strategies have been ongoing since the issuance of the 2002 ICM Order. In 2005, the NRC issued guidance to more fully describe the NRC staff's expectations for implementing Section B.5.b of the ICM Order. The NRC guidance relied upon lessons learned from detailed NRC engineering studies and industry best practices.

Additionally, the NRC conducted two on-site team assessments at each reactor facility that identified additional mitigating strategies for preservation of core cooling, containment integrity, and spent fuel pool cooling. In total, these efforts have added defense in depth through the use of additional equipment and strategies. Moreover, these enhancements that have strengthened the interface between plant safety and security operations now include fire-fighting response strategies; plant operations to mitigate fuel damage; and actions to minimize releases.

NOTICE: The attachments to the Safety Evaluation contain Security-Related Information. Upon separation from these attachments, this letter and Enclosures 1 and 2 are DECONTROLLED.

~E IiLW OE)UF.lr: flEZ..TED irironri TI1~M

Q&I .

%I E%I UIMI'rf

^1-0mu MITI A-rITM *LI~f%3RH AFrleKI C. M.Crane The enclosed Safety Evaluation (SE) details the interactions between the NRC staff and the AmerGen Energy Company, LLC, as well as the rest of the nuclear industry, related to the final resolution of Section B.5.b. of the ICM Order.

The NRC is incorporating requirements for the B.5.b mitigating strategies into the Facility Operating License. This letter, therefore, also transmits the license condition that captures the ICM Order Section B.5.b mitigation strategy requirements and incorporates them into the licensing basis.

This proposed license condition was transmitted by the NRC to the AmerGen Energy Company, LLC in a letter dated October 12, 2006. By letter dated January 9, 2007, the AmerGen Energy Company, LLC informed the NRC staff that it would accept the proposed license condition, with a minor change that the NRC staff finds acceptable. The effectiveness of the licensee's actions to implement the mitigative strategies contained in this license condition will be subject to future NRC review and inspection.

Consistent with the Order, an administrative license change to Facility Operating License No. NPF-62 for the Clinton Power Station, Unit No. 1, is being made to incorpprate the agreed upon license condition. This change complies with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in Title 10 of the Code of FederalRegulations (10 CFR) Chapter I. Please replace the affected pages of the Facility Operating License with the enclosed pages (Enclosure 1).

The attachments to the SE are designated exempt from public disclosure under 10 CFR 2.390(d)(1) since they contain security-related information and are Official Use Only.

If you have any questions, please contact me at (301) 415-3154.

Sincerely, Steph n P. Sands, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

1. Revised Pages of Facility Operating License No. NPF-62
2. Safety Evaluation cc w/o atts to Encl. 2: See next page III IlIk-AI-1 INI I. Nmi m.

Clinton Power Station, Unit 1 cc w/o atts to Encl 2:

Senior Vice President - Operations Support Plant Manager - Clinton Power Station Exelon Generation Company, LLC AmerGen Energy Company, LLC 4300 Winfield Road Clinton Power Station Warrenville, IL 60555 RR 3, Box 228 Clinton, IL 61727-9351 Illinois Emergency Management Agency Senior Vice President - Midwest Operations Division of Disaster Assistance & Exelon Generation Company, LLC Preparedness 4300 Winfield Road 110 East Adams Street Warrenville, IL 60555 Springfield, IL 62701-1109 Resident Inspector Director - Licensing and Regulatory Affairs U.S. Nuclear Regulatory Commission AmerGen Energy Company, LLC RR 3, Box 229A 4300 Winfield Road Clinton, IL 61727 Warrenville, IL 60555 Regional Administrator, Region III Manager Licensing - Dresden, Quad Cities U.S. Nuclear Regulatory Commission and Clinton Suite 210 Exelon Generation Company, LLC 2443 Warrenville Road 4300 Winfield Road Lisle, IL 60532-4351 Warrenville, IL 60555 Associate General Counsel Manager Regulatory Assurance - Clinton Exelon Generation Company, LLC AmerGen Energy Company, LLC 4300 Winfield Road Clinton Power Station Warrenville, IL 60555 RR 3, Box 228 Clinton, IL 61727-9351 Chairman of DeWitt County c/o County Clerk's Office Vice President - Regulatory Affairs DeWitt County Courthouse AmerGen Energy Company, LLC Clinton, IL 61727 4300 Winfield Road Warrenville, IL 60555 J. W. Blattner Project Manager Document Control Desk - Licensing Sargent & Lundy Engineers AmerGen Energy Company, LLC 55 East Monroe Street 4300 Winfield Road Chicago, IL 60603 Warrenville, IL 60555 Site Vice President - Clinton Power Station AmerGen Energy Company, LLC Clinton Power Station RR 3, Box 228 Clinton, IL 61727-9351

Enclosure 1 REVISED PAGES OF FACILITY OPERATING LICENSE NO. NPF-62 DOCKET NO. 50-461 CLINTON POWER STATION, UNIT NO. 1 Replace the following pages of the Facility Operating License with the attached revised pages.

The revised pages are identified by the date of the letter issuing these pages and contain marginal lines indicating the areas of change.

REMOVE INSERT License NPF-62 License NPF-62 Page 5 Page 5 Page 6 Page 6 Page 7 Page 7 Page 8 Page 8

License Transfer Conditions (10) Deleted.

(11) Deleted.

(12) Deleted.

(13) Deleted.

(14) AmerGen is required to provide decommissioning funding assurance of no less than $210 million, after payment of any taxes, that will be deposited in the decommissioning trust fund for CPS at the time of CPS's transfer to AmerGen.

(15) The decommissioning trust agreement for OPS must be in a form acceptable to the NRC.

(16) With respect to the decommissioning trust fund, investments in the securities or other obligations of Exelon Corporation, AmerGen Energy Company, LLC or affiliates thereof, or their successors or assigns shall be prohibited. Except for investments tied to market indexes or other nonnuclear sector mutual funds, investments in any entity owning one or more nuclear power plants are prohibited.

(17) The decommissioning trust agreement for CPS must provide that no disbursements or payments from the trust shall be made by the trustee until the trustee has first given the NRC 30 days prior written notice of payment. The decommissioning trust agreement shall further contain a provision that no disbursements or payments from the trust shall be made if the trustee receives prior written notice of objection from the Director, Office of Nuclear Reactor Regulation.

(18) The decommissioning trust agreement must provide that the agreement cannot be amended in any material respect without the prior written consent of the Director, Office of Nuclear Reactor Regulation.

(19) The appropriate section of the decommissioning trust agreement shall reflect that the trustee, investment advisor, or anyone else directing the investments made in the trust shall adhere to a "prudent investor" standard, as specified in 18 CFR 35.32(a)(3) of the Federal Energy Regulatory Commission's regulations.

Amendment No. 161 Correction letter of 6-14-2004 Revised by letter dated July 26, 2007

(20) AmerGen Energy Company, LLC shall take all necessary steps to ensure that the decommissioning trust is maintained in accordance with the application for approval of the transfer of the Clinton license to it and the requirements of the Order approving the transfer, and consistent with the safety evaluation supporting the Order.

(21) AmerGen Energy Company, LLC shall take no action to cause Exelon Generation Company, LLC, (or successors or assigns of Exelon Generation Company, LLC approved by the NRC) to void, cancel; or diminish the $200 million contingency commitment from Exelon Generation Company, LLC, (or successors or assigns of Exelon Generation Company, LLC approved by the NRC) dated December 22, 2003, or cause it to fail to perform or impair its performance under the commitment, or remove or interfere with AmerGen's ability to draw upon the commitment. Also, AmerGen Energy Company, LLC shall inform the NRC in writing at any time that it draws upon the $200 million commitment.

Amendment No. 161 Correction letter of 6-14-2004 Revised by letter dated July 26, 2007

(22) Mitigation Strategy License Condition The licensee shall develop and maintain strategies for addressing large fires and explosions and that include the follow key areas:

(a) Fire fighting response strategy with the following elements:

1. Pre-defined coordinated fire response strategy and guidance
2. Assessment of mutual aid fire fighting assets
3. Designated staging areas for equipment and materials
4. Command and control
5. Training of response personnel (b) Operations to mitigate fuel damage considering the following:
1. Protection and use of personnel assets
2. Communications
3. Minimizing fire spread
4. Procedures for implementing integrated fire response strategy
5. Identification of readily-available pre-staged equipment
6. Training on integrated fire response strategy
7. Spent fuel pool mitigation measures (c) Actions to minimize release to include consideration of:
1. Water spray scrubbing
2. Dose to onsite responders D. The facility requires exemptions from certain requirements of 10 CFR Part 50 and 10 CFR Part 70. These include: (a) an exemption from the requirements of 10 CFR 70.24 for the criticality alarm monitors around the fuel storage area; (b) an exemption from the requirement of 10 CFR Part 50, Appendix J - Option B, paragraph Ill.B, exempting the measured leakage rates from the main steam isolation valves from inclusion in the combined leak rate for local leak rate tests (Section 6.2.6 of SSER 6); and (c) an exemption from the requirements of paragraph III.B of Option B of 10 CFR Part 50, Appendix J, exempting leakage from the valve packing and the body-to-bonnet seal of valve 1 E51 -F374 associated with containment penetration 1 MC-44 from inclusion in the combined leakage rate for penetrations and valves subject to Type B and C tests (SER supporting Amendment 62 to Facility Operating License No. NPF-62). The special circumstances regarding each exemption, except-for item (a) above, are identified in the referenced section of the safety evaluation report and the supplements thereto.

Revised by letter dated July 26, 2007

An exemption was previously granted pursuant to 10 CFR 70.24. The exemption was granted with NRC Material License No. SNM-1 886, issued November 27, 1985, and relieved the licensee from the requirement of having a criticality alarm system. AmerGen Energy Company, LLC is hereby exempted from the criticality alarm system provision of 10 CFR 70.24 so far as this section applies to the storage of fuel assemblies held under this license.

These exemptions are authorized by law, will not present an undue risk to the public health and safety, and are consistent with the common defense and security. The exemptions in items (b) and (c) above are granted pursuant to 10 CFR 50.12. With these exemptions, the facility will operate, to the extent authorized herein, in conformity with the application, as amended, the provisions of the Act, and the rules and regulations of the Commission.

E. AmerGen Energy Company, LLC shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans',

which contain Safeguards Information protected under 10 CFR 73.21, is entitled:

"Clinton Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 2," submitted by letter dated May 17, 2006.

F. AmerGen Energy Company, LLC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report as amended, for the Clinton Power Station, Unit No. 1, and as approved in the Safety Evaluation Report (NUREG-0853) dated February 1982 and Supplement Nos. 1 thru 8 thereto subject to the following provision:

AmerGen Energy Company, LLC may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

G. Deleted.

Amendment No. 172 Revised by letter dated July 26, 2007

'The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.

RE . . -m. ulr

.. ... . .. . ....... ... .. "1I UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO ORDER NO. EA-02-026 AMERGEN ENERGY COMPANY, LLC CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461

1.0 INTRODUCTION

1.1 Purpose The purpose of this Safety Evaluation (SE) is to document the U.S. Nuclear Regulatory Commission (NRC) staff's regulatory assessment of the adequacy of the actions taken by the AmerGen Energy Company, LLC (the licensee) in response to the February 25, 2002, Interim Compensatory Measures (ICM) Order and the subsequent NRC letter to licensees dated February 25, 2005, transmitting NRC guidance (Phase 1 guidance document). This SE describes the basis for finding licensee strategies adequate to satisfy the requirements of the ICM Order. This SE also discusses the license condition that satisfactorily captures the mitigation strategy requirements. If the licensee makes future changes to its strategies within its commitment management program, this SE will be useful to the NRC staff in determining if the changed strategies are adequate to meet the license condition. It should be noted that portions of the ICM Order, as well as other documents referenced in this SE, contain security-related or safeguards information, and are not publicly available.

1.2 Background The February 25, 2002, ICM Order that imposed interim compensatory measures on power reactor licensees required in Section B.5.b, Mitigative Measures, the development of "specific

.guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities using existing or readily available resources (equipment and personnel) that can be effectively implemented under the circumstances associated with loss of large areas of plant due to explosions or fire." These actions were to be implemented by the end of August 2002. Inspections of the implementation of the Section B.5.b requirements were conducted in 2002 and 2003 (Temporary Instruction (TI) 2515/148). The inspections identified large variabilities in scope and depth of the enhancements made by licensees. As a result, the NRC determined that additional guidance and clarification was needed for nuclear power plant licensees.

NOTICE: The attachments to the Safety Evaluation contain Security-Related Information. Upon separation from these attachments, this Safety Evaluation is DECONTROLLED.

~~~JI~ .'.IL.I 10 "lfIAW.J 11JII 1 51IN-L-ri& I I-. INV# WK INVII I IWIV

Subsequent to the conduct of the TI 2515/148 inspections, engineering studies conducted by the NRC Office of Regulatory Research (RES) provided insights into the implementation of mitigation strategies to address the loss of large areas of a plant due to explosions or fire, including those that an aircraft impact might create. The NRC actions resulting from these studies included: (1) inspections of licensee actions that address plant-specific consequences, (2) issuance of advisories that involve processes and protocols for licensee notification of an imminent aircraft threat, and (3) identification of mitigative measures to enhance plant response to explosions or fire.

On November 24, 2004, the NRC issued a letter to licensees providing information on the Commission's phased approach for enhancing reactor mitigative measures and strategies for responding to Section B.5.b of the ICM Order. On February 25, 2005, the NRC issued guidance (Phase 1 guidance document) to describe more fully the NRC staff's expectationsfor implementing Section B.5.b of the ICM Order. Determination of the specific strategies required to satisfy the Order, elaborated on by the Phase 1 guidance document, was termed Phase 1.

Further information on the Commission's phased approach and its reliance on the Phase 1 guidance document and related workshop was described in an NRC letter to licensees dated January 14, 2005.

The NRC Phase 1 guidance document relied upon lessons learned from recent NRC engineering studies involving plant assessments, as well as industry best practices. This guidance also included the spent fuel pool mitigative measures described in a NRC letter to licensees dated July 29, 2004, "Issuance of Spent Fuel Pool Mitigative Measures." These best practices were identified during the inspections conducted in 2002 and 2003. The Phase 1 guidance document also incorporated industry comments made at two B.5.b-related workshops held on January 14, 2005, and February 2, 2005.

2.0 REGULATORY EVALUATION

Section B.5.b of the ICM Order required licensees to develop specific guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities using existing or readily-available resources (equipment and personnel) that can be effectively implemented under the circumstances associated with loss of large areas of the plant due to explosions or fire. Determination of the specific strategies required to satisfy the Order, elaborated on in the Phase 1 guidance document, was termed Phase 1.

In order to assure adequate protection of public health and safety and common defense and security, the NRC determined that differences in plant design and configuration warranted independent assessments to verify that the likelihood of damage to the reactor core, containment, and spent fuel pools and the release of radioactivity is low at each nuclear power plant. The Commission directed the NRC staff to conduct site-specific security and safety assessments to further identify enhanced mitigation capabilities. Site-specific assessments of spent fuel pools were deemed Phase 2 and site-specific assessments of reactor core and containments were deemed Phase 3.

The goal of the Phase 2 and 3 mitigation strategy assessments was for the NRC and the licensees to achieve a new level of cognition of safety and security through a comprehensive understanding of the capabilities and limitations of the plants under normal, abnormal, and I L.LF I IV U_%.F"IVIM I IA IV

severe circumstances (from whatever cause). Based on this improved understanding, licensees could take reasonable steps to strengthen their capabilities and reduce their limitations. The NRC expected that safety and security would be well served by further enhancing the licensee's severe accident management strategies for mitigating a wide spectrum of events through the use of readily-available resources and by identifying potential practicable areas for the use of beyond-readily-available resources.

During 2005, the NRC staff performed inspections (TI 2515/164) to determine licensees' compliance with Section B.5.b of the ICM Order (Phase 1). Subsequent meetings were held with licensees to resolve identified open issues. Confirmatory B.5.b Phase 1 inspections (TI 2515/168) were conducted during the period of June to December 2006. The NRC staff conducted site visits as part of the Phase 2 assessments during 2005. In 2006, the NRC staff observed licensee Phase 3 studies and conducted independent Phase 3 assessments.

On January 24, 2006, the Nuclear Energy Institute (NEI) submitted a letter (M. Fertel to L. Reyes) describing an industry proposal for resolving ("closing") Phase 2 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML060260220). The industry proposed high level functional mitigating strategies for a spectrum of potential scenarios involving spent fuel pools. In a letter to all Holders of Licenses for Operating Power Reactors dated June 21, 2006 (ADAMS Accession No. ML061670146), the NRC accepted the Phase 2 proposal pending review of site-specific details of its application and implementation.

In arriving at this conclusion, the NRC staff placed significant weight on portions of the proposal that rely on industry commitments to provide beyond-readily-available resources not previously available. These additions will significantly enhance licensees' mitigating strategies capabilities.

On June 27, 2006, the NEI submitted two letters (M. Fertel to W. Kane). In one of the letters, the NEI proposed a license condition to capture the Section B.5.b requirements and addressed items deferred from Phase 1 to Phase 2 (ADAMS Accession No. ML061790400). The license condition includes 14 items in the same broad categories as the February 25, 2005, Phase 1 guidance document; fire fighting response strategy, plant operations to mitigate fuel damage, and actions to minimize releases. The proposal suggested that the implementing details found to be an acceptable means of meeting the license condition would be treated as commitments, and managed in accordance with NEI 99-04, "Guidelines for Managing NRC Commitment Changes." In the second letter, the NEI proposed generic strategies for closure of Phase 3 (ADAMS Accession No. ML061860753). The required strategies for all three phases would be covered by the license condition and all implementing details would be managed by NEI 99-04.

The February 25, 2005, Phase 1 guidance document included 34 expectations. Two of these items were deferred to Phase 2 and seven items (i.e., six expectations and one element of a seventh expectation) were deferred to Phase 3. The NRC staff reached agreement with licensees on the non-deferred items under Phase 1.

Table 1 provides a cross reference of how the 34 elements of the February 25, 2005, Phase 1 guidance document and Phases 2 and 3 mitigating strategies correspond to the sections of the license condition.

On June 29, 2006, the NRC staff issued a letter to the NEI conditionally accepting its proposed license condition and strategies (ADAMS Accession No. ML061790306). The letter reiterated

ii~~*i~ ir - rr-r *-rn' n- ~ iIrlTnU -TIIr" that mitigation strategies in NEI's proposals that were identified during the Phase 2 and 3 assessments, which utilize reasonable, evident, readily-available resources (as identified in the February 25, 2005, Phase 1 guidance document) are required pursuant to Section B.5.b of the ICM Order. The implementing details of the required strategies will be implemented by commitment and managed in accordance with the NEI commitment management guideline, NEI 99-04. The NRC staff believes the NEI proposal reasonably justifies excluding from formal regulatory controls those additional strategies identified during the site-specific Phases 2 and 3 assessments that the NRC previously deemed required under Section B.5.b of the ICM Order, but not identified in NEI's proposals. Inherent in this conclusion is recognition of the addition of beyond-readily-available resources included in the proposals. The implementing details of mitigation strategies included in the proposal, including those that utilize beyond-readily-available resources, will be treated as commitments, which will become part of the licensing basis of the plant. Additional strategies identified during site-specific assessments which licensees deem acceptable and valuable to promote diversification and survivability, will be incorporated into licensees' Severe Accident Management Guidelines, Extreme Damage Mitigation Guidelines, or appended to other site implementation guidance. To verify compliance, the NRC staff evaluated the site-specific implementation and documentation of the proposed Phases 2 and 3 mitigating strategies for each U.S. nuclear power plant.

3.0 TECHNICAL EVALUATION

The NRC staff's technical evaluation for strategies identified in Phase 1 of Section B.5.b is found in Appendix A. The NRC staff's technical evaluation for strategies identified in Phases 2 and 3 of Section B.5.b is found in Appendix B.

The Mitigating Strategies Table (MST) is included as Appendix C. The purpose of the MST is to capture, at the functional level, a summary of licensee strategies for compliance with the 34 measures presented in the February 25, 2005, Phase 1 guidance document and to indicate how the 34 items correlate to the 14 items in the license condition.

4.0 REGULATORY COMMITMENTS The implementing details of the mitigating strategies required by the license condition are identified in licensee submittals dated January 9, 2007 (ADAMS Accession No. ML070i 70466),

and May 16, 2007 (ADAMS Accession No. ML071420301). These details will be implemented by commitment and managed in accordance with the NEI commitment management guideline, NEI 99-04. The NRC staff concludes this provides reasonable controls for mitigating strategy implementation and for subsequent evaluation of licensee-identified changes.

Because the 14 items required by the license condition correlate to the 34 items presented in the February 25, 2005,'Phase 1 guidance document and the mitigating strategies within NEI's Phase 2 and 3 proposals, and because the implementing details will be managed under NEI 99-04, the NRC staff is satisfied that there will be sufficient controls to ensure that the strategies are adequately maintained.

orr~mI:z..JE WILPPSS....AW

5.0 CONCLUSION

Based on the NRC staff's review described in Appendices A, B, and C of this SE, the licensee's responses to the February 25, 2005, Phase 1 guidance document and the spent fuel pool and reactor core and containment mitigating strategy assessments meet the requirements of Section B.5.b, Mitigative Measures, of the February 25, 2002, ICM Order that imposed interim compensatory measures on power reactor licensees. The NRC staff concludes that full implementation of the licensee's enhancements in the submittals identified in Section 4.0, above, constitutes satisfactory compliance with Section B.5.b and the license condition, and represents reasonable measures to enhance the licensee's effectiveness in maintaining reactor core and spent fuel pool cooling and containment integrity under circumstances involving the loss of large areas of the plant due to fires or explosions.

The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendments will not be inimical to the common defense and security or to the health and safety of the public.

Attachments (Official Use Only - Security-Related Information - ADAMS Accession No. ML072050483):

1. Phase 1 Assessment (Appendix A)
2. Phases 2 and 3 Assessment (Appendix B)
3. Mitigating Strategies Table (Appendix C)

Principal Contributors: David J. Nelson Michael K. Webb Nathan T. Sanfilippo Date: July 26, 2007

?T:ulm. :mm sir..-- orm ~ n-. ~

A;- l I. - n i n a A ..lI s! awnI .*1 , w".i A mp inl~lm liann ql l Table 1 CROSS REFERENCE BETWEEN LICENSE CONDITION AND GUIDANCE DOCUMENT ELEMENTS License Condition section Guidance Document Elements A. Fire fighting response strategy with the following elements:

1. Pre-defined coordinated fire response strategy and B.1.b Staging of personnel guidance B.1.e Outside organization Support B.1.j Treatment of casualties B.1.k Site assembly areas (mass casualties)

B.1 .m Industry best practice - feeding fire protection ring header

2. Assessment of mutual aid fire fighting assets B.1.c Airlifted resources B.1.f Mobilization of fire fighting resources - existing or new MOUs B.1.g Mobilization of fire fighting resources - coordination with other than local mutual aid fire fighting resources (i.e, Industrial facilities, large municipal fire departments, airports, and military bases)
3. Designated staging areas for equipment and B.1.a Staging of equipment materials B.1.h Controlling emergency response vehicles (includes rad monitoring)
4. Command and Control B.1.d Command and control B.1.i Communications enhancements
5. Training of response personnel B.1.1 Training considerations w- . ............................. I VlilVlf im mill fflrý

in

~--n n~in~rflU

~t- [IDI~IrflW~iq B. Operations to mitigate fuel damage considering the following:

1. Protection and use of personnel assets B.2.a Personnel considerations
2. Communications B.2.b Communications measures
3. Minimizing fire spread B.2.h Compartmentalization of plant areas
4. Procedures for implementing integrated fire response B.2.c Procedures (Included in Phase 3 strategies) strategy B.2.d Evaluation of vulnerable buildings and equipment (Included in Phase 3 strategies)

B.2.e Industry best practice - Containment venting and vessel flooding B.2.f Industry best practice for compensatory function (Included in Phase 3 strategies)

B.2.g Best practice for use of plant equipment B.2.i Best practice involving plant areas potentially affected by fire or explosions (Included in Phase 3 strategies)

B.2.k Best practice for establishing supplemental response capabilities B.2.1 Best practice for establishing supplemental response capabilities

5. Identification of readily-available, pre-staged B.2.g Best practice for use of plant equipment - portable equipment generator and transformer (Included in Phase 3 strategies)

B.2.j Best practice involving reliance on portable and offsite

__equipment (Included in Phase 3 strategies)

- W5 a w YMVýýý . Rpvý II mVI !

iii -. -- ~ ram A n

6. Training on integrated fire response strategy B.2.n Training conIsiderations
7. Spent fuel pool mitigation measures B.2.m.1 Dispersal of Fuel B.2.m.2 Hot fuel over rack feet B.2.m.3 Downcomer area B.2.m.4 Enhanced air circulation (Included in Phase 2 strategies)

B.2.m.5 Emergency pool makeup, leak reduction/repair (Included in Phase 2 strategies)

C. Actions to minimize release to include considerations of:.

1. Water spray scrubbing B.3.a Water spray scrubbing B.3.b Prestaging of equipment
2. Dose to onsite responders B.3.c Dose projection models (Included in Phase 3 strategies)

MVIC,

Pkg ML072050004 (Letter & Encl 2: ML072050005, Encl 1:ML072060002 , Attachments to SE (OUO): ML072050483)

OFFICE NRR/LPLIV/PM NRR/PSPB/LA NRR/DPR/PSPB NRR/LPL3-2/PM NRR/LPL3-2/BC NAME MFields JBurkhardt DNelson SSands Rgibbs, CGratton for for DBaxley DATE 7/25/07 7/23/07 7/25/07 7/25/07 7/25/07 C. M. Crane July 26, 2007 The enclosed Safety Evaluation (SE) details the interactions between the NRC staff and the AmerGen Energy Company, LLC, as well as the rest of the nuclear industry, related to the final resolution of Section B.5.b. of the ICM Order.

The NRC is incorporating requirements for the B.5.b mitigating strategies into the Facility Operating License. This letter, therefore, also transmits the license condition that captures the ICM Order Section B.5.b mitigation strategy requirements and incorporates them into the licensing basis.

This proposed license condition was transmitted by the NRC to the AmerGen Energy Company, LLC in a letter dated October 12, 2006. By letter dated January 9, 2007, the AmerGen Energy Company, LLC informed the NRC staff that it would accept the proposed license condition, with a minor change that the NRC staff finds acceptable. The effectiveness of the licensee's actions to implement the mitigative strategies contained in this license condition will be subject to future NRC review and inspection.

Consistent with the Order, an administrative license change to Facility Operating License No. NPF-62 for the Clinton Power Station, Unit No. 1, is being made to incorporate the agreed upon license condition. This change complies with the standards and requirements of the Atomic Energy Act of 1954, as amended, and the Commission's rules and regulations set forth in Title 10 of the Code of FederalRegulations (10 CFR) Chapter I. Please replace the affected pages of the Facility Operating License with the enclosed pages (Enclosure 1).

The attachments to the SE are designated exempt from public disclosure under 10 CFR 2.390(d)(1) since they contain security-related information and are Official Use Only.

If you have any questions, please contact me at (301) 415-3154.

Sincerely,

/RA/

Stephen P. Sands, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461

Enclosures:

1. Revised Pages of Facility Operating License No. NPF-62
2. Safety Evaluation cc w/o atts to Encl. 2: See next page DISTRIBUTION (w/o attachments to Safety Evaluation)

PUBLIC RidsNrrPMMFields RidsOgcRp LPL3-2 Reading File RidsNrrPMSSands GHiII, OIS RidsAcrsAcnwMailCenter RidsNrrLADBaxley AFrazier, NSIR RidsNrrDorl (CHaney/JLubinski) RidsNsirDsp RidsNrrDorl~pl3-2 RidsNrrDorlDpr RidsRgn3MailCenter RidsNrrLAEWhitt ADAMS Accession Nos.: Pkg ML072050004 (Letter & Encl 2: ML072050005, Encl 1:ML072060002, Attachments to SE (OUO): ML072050483)

OFFICE NRR/LPLIVIPM NRR/PSPB/LA NRR/DPR/PSPB NRR/LPL3-2/PM NRR/LP*-*(BC NAME MFieldfor JBurkhardt DNelson SSands ,I.-* RGibbs Ifor DBaxley I i5p 7~E

....................... IrnlzsiC

- -r-r%

11k1r'rr-%R A9rlPIkl 0

C. M. Crane -

The enclosed Safety Evaluation (SE) details the interactions between the NRC staff and the AmerGen Energy Company, LLC, as well as the rest of the nuclear industry, related to the final resolution of Section B.5.b. of the [CM Order.

The NRC is incorporating requirements for the B.5.b mitigating str ies into the Facility Operating License. This letter, therefore, also transmits the lic se condition that captures the ICM Order Section B.5.b mitigation strategy requirements incorporates them into the licensing basis.

This proposed license condition was transmitted b the NRC to the AmerGen Energy Company, LLC in a letter dated October 12, 2006. By lett dated January 9, 2007, the AmerGen Energy Company, LLC informed the NRC Staff that it ould accept the proposed license condition, with a minor change that the NRC staff finds ac ptable. The effectiveness of the licensee's actions to implement the mitigative strategies co ained in this license condition will be subject to future NRC review and inspection.

Consistent with the Order, an admin' trative license change to Facility Operating License No. NPF-62 for the Clinton Power tation, Unit No. 1, is being made to incorporate the agreed upon license condition. This cha e complies with the standards and requirements of the Atomic Energy Act of 1954, as ended, and the Commission's rules and regulations set forth in Title 10 of the Code of Fede a! Regulations (10 CFR) Chapter I. Please replace the affected pages of the Facility Operatin License with the enclosed pages (Enclosure 1).

The attachments to the SE re designated exempt from public disclosure under 10 CFR 2.390(d)(1) since they co ain security-related information and are Official Use Only.

If you have any please contact me at (301) 415-3154.

Sincerely, Stephen P. Sands, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-461 k

Enclosures:

1. Revised Pages of Facility Operating License No. NPF-62
2. Safety Evaluation cc w/o atts to Encl. 2: See next page DISTRIBUTION (w/o attachments to Safety Evaluation)

PUBLIC RidsNrrPMMFields RidsOgcRp LPL3-2 Reading File RidsNrrPMSSands GHiII, OIS RidsAcrsAcnwMailCenter RidsNrrLADBaxley AFrazier, NSIR RidsNrrDorl (CHaney/JLubinski) RidsNsirDsp RidsNrrDorlLpl3-2 RidsNrrDorlDpr RidsRgn3MailCenter RidsNrrLAEWhitt ADAMS Accession Nos.: Pkg ML072050004 (Letter & Encl 2: ML072050005, Encl 1:ML07, Attachments to SE (OUO): ML07)

OFFICE NRR/LPLIV/PM NRR/PSPB/LA NRR/DP PSPB NRR/LPL3-2/PM NRR/LPL3-2/BC NAME MFields,*7 DBaxley 15t or SSands RGibbs DATE aM-¶ RC-DO OFFICIAL RECOAID COPY I )FIUI~L UOIJ 112....  ;.junrn: flEZTEO l1IrunL1.~TIohi