July 26, 2007 Mr. Michael A. Balduzzi Sr. Vice President & COO Regional Operations, NE Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
PILGRIM NUCLEAR POWER STATION - WITHDRAWAL OF A RELIEF REQUEST (TAC NO. MD2478)
Dear Mr. Balduzzi:
By letter dated June 29, 2006, you applied for a relief request to the Pilgrim Nuclear Power Station. The relief request would have modified the Fourth 10-Year Inservice Testing Program to allow the use of alternative testing of ISTB 5.2.3 on the high-pressure coolant injection (HPCI) pump until August 29, 2008, in accordance with Title 10 of the Code of Federal Regulations, Section 50.55a.
By letter dated July 12, 2007, (Agencywide Document Access and Management System (ADAMS) Accession No. ML072010018) you suggested that NRC at its option may defer the review until Entergy provides results of the consultants assessment. Subsequently, by e-mail dated July 23, 2007, (ADAMS Accession No. ML072040360) you withdrew the relief request.
The NRC understands that the relief request will be resubmitted following completion of the independent consultants assessment of HPCI pump vibration analysis.
The purpose of this letter is to advise that the above cited application is being treated as withdrawn.
Sincerely,
/RA/
James Kim, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: See next page
ML072040360) you withdrew the relief request.
The NRC understands that the relief request will be resubmitted following completion of the independent consultants assessment of HPCI pump vibration analysis.
The purpose of this letter is to advise that the above cited application is being treated as withdrawn.
Sincerely,
/RA/
James Kim, Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-293 cc: See next page DISTRIBUTION:
PUBLIC RidsNrrDORL RidsNrrDORLLpl1-1 RidsNrrLASLittle LPL1-1 Reading RidsNrrPMJKim RidsOgcRp GHill (2)
RidsRgn1MailCenter Rids AcrsAcnwMail ACCESSION NUMBER: ML071990351 OFFICE LPLI-1/PM LPLI-1/LA LPL1-1/BC NAME JKim SLittle MKowal DATE 7/24/07 7/25/07 7/26/07 Pilgrim Nuclear Power Station cc:
Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Senior Resident Inspector U. S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station Post Office Box 867 Plymouth, MA 02360 Chairman, Board of Selectmen 11 Lincoln Street Plymouth, MA 02360 Chairman Nuclear Matters Committee Town Hall 11 Lincoln Street Plymouth, MA 02360 Chairman, Duxbury Board of Selectmen Town Hall 878 Tremont Street Duxbury, MA 02332 Office of the Commissioner Massachusetts Department of Environmental Protection One Winter Street Boston, MA 02108 Office of the Attorney General One Ashburton Place 20th Floor Boston, MA 02108 MA Department of Public Health Radiation Control Program Schrafft Center, Suite 1M2A 529 Main Street Charlestown, MA 02129 Secretary of Public Safety Executive Office of Public Safety One Ashburton Place Boston, MA 02108 Director, Massachusetts Emergency Management Agency Attn: James Muckerheide 400 Worcester Road Framingham, MA 01702-5399 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056-0426 Mr. Kevin H. Bronson Site Vice President Entergy Nuclear Operations Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Robert G. Smith General Manager, Plant Operations Entergy Nuclear Operations Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Stephen J. Bethay Director, Nuclear Safety Assurance Entergy Nuclear Operations Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Bryan S. Ford Manager, Licensing Entergy Nuclear Operations Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
Pilgrim Nuclear Power Station cc:
Mr. John T. Herron Sr. Vice President Entergy Nuclear Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations 440 Hamilton Avenue White Plains, NY 10601 Mr. John A. Ventosa GM, Engineering Entergy Nuclear Operations 440 Hamilton Avenue White Plains, NY 10601 Mr. Joseph P. DeRoy VP, Operations Support Entergy Operations, Inc.
1340 Echelon parkway Jackson, MS 39213 Mr. Michael Kansler President & CEO/CNO Entergy Nuclear Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. John F. McCann Director, Nuclear Safety & Licensing Entergy Nuclear Operations 440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene D. Faison Manager, Licensing Entergy Nuclear Operations 440 Hamilton Avenue White Plains, NY 10601 Mr. Ernest J. Harkness Director, Oversight Entergy Nuclear Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Mr. William C. Dennis Assistant General Counsel Entergy Nuclear Operations 440 Hamilton Avenue White Plains, NY 10601 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue New Orleans, LA 70113 Mr. James Sniezek 5486 Nithsdale Drive Salisbury, MD 21801-2490 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Mr. Garrett D. Edwards 814 Waverly Road Kennett Square, PA 19348 Mr. John Doering P.O. Box 189 Parker Ford, PA 19457