ML071780028
| ML071780028 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 06/18/2007 |
| From: | Lochbaum D Union of Concerned Scientists |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| FOIA/PA-2007-0299 | |
| Download: ML071780028 (16) | |
Text
Unison of Concerned Sci~entists Citizens and Scientists for Environmental Solutions Nuclear Pinocchio David Lochbaum Director, Nuclear Safety Project June 18, 2007
Nuclear Pin-occhie People associate Pinocchio with his penchant for lying*
Pinocchio was also, at least initially, a marionette who's actions, and inactions, were controlled by whoever held the puppet strings.
This 2.206 petition is all about who's lying and who's controlling the puppet strings.
Petition's "Asks"
- 1) Immediate shut down of Davis-Besse until NRC completes an independent review of Exponent report
- 2) If NRC's independent review concludes report is valid, shut down of all other PWRs until "new" issues are resolved (Davis-Besse could restart)
- 3) If NRC's independent review concludes report is not valid, revoke FirstEnergy's license to operate Davis-Besse
PRB's Responses
- 1) No
- 2) No
- 3) No
Petitioner Pleased with Responses
- 1) Nope
- 2) Nope 3). Nope Pinocchio had a long nose.
NRC has the wrong no's.
NRC's "Independent Review"
§ 50.9 Completeness and accuracy of information.
(a) information provided to the Commission by an applicant for a license or by a licensee or information required by statute or by the Commission's regulations, orders, or license conditions to be maintained by the applicant or the licensee shall be complete and accurate in all material respects.
By letter dated March 20, 2007, and numbered Serial Number 3331, the Davis-Besse licensee provided a copy of the Exponent report to the Commission.
The "independent review' UCS sought was merely for the NRC to determine if the report conforms with this federal regulation,
NRC ' S "Independent Review" Weeks after our petition was submitted, NRC demanded info from FENOC about the Exponent report.
UCS cannot believe these NRC actions will not include a 50.9 determination about the Exponent report. Why would NRC demand info about a report for which the agency has no opinion as to its completeness and accuracy?
May 14, 2007 EA-07-123 Mr. Anthony Alexander Chief Executive Officer FirstEnergy Nuclear Operating Company 76 South Main Street Akron, OH 44308
SUBJECT:
DEMAND FOR INFORMATION
Dear Mr. Alexander:
The enclosed Demand for Information (DFl) is being issued in response to information provided by FirstEnergy Nuclear Operating Company (FENOC) relative to its re-analysis of the timeline and root causes for the 2002 Davis-Besse reactor pressure vessel head degradation event.
The Nuclear Regulatory Commission (NRC) requires information in order to understand and determine the appropriateness of FENOC's actions following its receipt of a report prepared by its contractor, Exponent Failure Analysis Associates and Altran Solutions Corporation (Exponent), that provided a re-analysis of the timeline and root causes of the 2002 Davis Besse reactor pressure vessel head degradation event (2002 event). In particular, given the significant changes in the timelines, the NRC needs further detailed and specific information relative to the timing of FENOC's review of the Exponent Report and the factors it considered when determining if the conclusions should be communicated to the NRC.
The NRC also needs information to understand the depth and completeness of FENOC's evaluation of the assumptions, methods, and conclusions of the Exponent Report. In particular, the NRC requires detailed and specific information with regard to differences between the assumptions, methods, and conclusions of the Exponent Report and the technical and programmatic root cause reports previously developed by FENOC relative to the 2002 event.
This information is also needed for the NRC to determine the appropriateness of FENOC's assessment of the continued adequacy of corrective actions taken in response to the 2002 event.
NRC's "Independent Review" U.S. NUCLEAR REGULATORY COMMISSION REPORT TO CONG RESS ON THE NATIONAL ACADEMY OF SCIENCES STUDY ON THE SAFETY AND SECURITY OF COMMERCIAL SPENT NUCLEAR FUEL STORAGE March 2005 Recommendation 2C - Althoughi the committee did not specifically in vestfigate the effectiveness and adequacy of improved surveillance and security measures for protecting stored spent nuclear fue4 an assessmnent of current security mneasures sh~ould be performed by an in dep en dent organization -
Response - The NRC agrees that independent assessment of the effectiveness, adequacy, and efficiency of programs, including security program requirements for protecting SNF is desirable.
The NRC, as an independent regulatory agency, evaluates the performance of licensees in implementing these security requirements. The NRC is responsible for regulating licensees' performance in protecting spent fuel, not for directly protecting spent fuel itself.
NRC's "Independent Review" UCS sought to have NRC, as an independent regulatory agency, determine if one of its regulations (numberly 10 CFR 50.9) had been violated by one of its licensees (namely FirstEnergy).
In othuer words, was F Iirst --
EKne r g)y tyin ethen o r a re t hie y/ yi g now?
Back then, FENOC said:
'~~-Barriers Demonstrating FENOC'S Strong Safety Focus Indsiiulsu SvusiIftt IL IL Is "o
PfunMs F'
73
Now, FENOC says:
- 2. Principal Conclusions and Opinions We have reached the follow-ing overall conclusion based on the work-described in detail in the subsequent sections of this report.
The large wastage cavityv discovered in March 2002 at control rod drive mechanism (CRDMI) Nozzle. 3 in the Davis-B esse reactor pressure. vessel (RPV) head was caused by a unique, unexpected, and unforeseeable combination of high nozzle m aterial susceptibilit, to primary-n'ater stress corrosion cracking (PWSCQ), high residual stresses from. wie/ding, rapid and non-linear crack growth, and development of thermal hvydraullc conditions that resulted in accelerated attack of the RPV head alloy steel material. This event of the moment occurred around OctoberlNovember 2001 when the leak rate from an. existing J-groove weld crack combined with the leak rate from, the, CRAM Nozzle.S crack to raise the total leakage rate to 0. 1 6gpn (54, 000 gallons 4evar). This leak rate caused rapid catastrophic. material removal from the RPV head.
This event was not only. unexpected, but was not foreseen or predicted by an~y of the extensive prior experience with boric acid corrosion, or fromn anty of the inspection and analysis of CRDM cracking in nuclear plants worldwide. from 1991 through 2002. It was the first occurrence of its kind, ever.
Back then, NRC overlooked:
In April 2000, an NRC inspector was handed this "red photo" showing reactor vessel head damage at Davis-Besse.
NRC did nothing, (Except file it.)
Redl Rusty Ikric.Acid IX vpiLs on Vow[ F hinge-~ (12 RIV)
Now, NRC overlooks:
In March 2007, the NRC was given the Exponent report which directly
~
contradicts prior FENOC materials like the root cause report, response to NOV & civil penalty, etc.
NRC did TBD
Pinocchio vs. Puppet-master Fall 2001: FENOC tells NRC that Davis-Besse can keep running without inspections while North Anna, Surry, and other other highly susceptible reactors (except Cook) shut down for CRDM nozzle inspections.
Spring 2005: NRC fines FENOC record $5.45 million for numerous violations, including 50.9.
Spring 2007: FENOC tells NRC it was entirely blameless in keeping Davis-Besse running without inspections.
Today: The NRC is on which end of the puppet strings?
Or is NRC still dancing to FENOC's bidding?
Pinocchio vs. Puppet-master NRC must stop "6rearview mirror regulating,"
waiting until the boric acid dust settles before taking action.
NRC should have acted in fall 2001 instead of reacting in spring 2005.
NRC must act now to curb this rogue licensee.
Pinocchio vs. Puppet-master If thfe tirfuth. shall, set, you-free, repreatedly-faili n-g to tell the truth m-.ust cost you th.at f r,,eedom,-.,
The NRC must not allow FirstEnergy to freely tell lie after lie after lie. Enough is more than enough!
I