June 25, 2007 LICENSEE: Wolf Creek Nuclear Operating Corporation FACILITY: Wolf Creek Generating Station, Unit 1
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 14, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND WOLF CREEK NUCLEAR OPERATING CORPORATION, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE WOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Wolf Creek Nuclear Operating Corporation held a telephone conference call on June 14, 2007, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Wolf Creek Generating Station, Unit 1, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the participants and Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary. A mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-3703 or e-mail VMR1@nrc.gov.
/RA/
Verónica M. Rodríguez, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-482
Enclosures:
- 1. List of Participants
- 2. List of Requests for Additional Information cc w/encls: See next page
ML071690318 DOCUMENT NAME: C:\\FileNet\\ML071690318.wpd OFFICE PM:RLRB:DLR LA:DLR BC:RLRB:DLR NAME V. Rodriguez Y. Edmonds R. Auluck DATE 06/25/07 06/22/07 06/25/07 TELEPHONE CONFERENCE CALL WOLF CREEK GENERATING STATION, UNIT 1 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS JUNE 14, 2007 PARTICIPANTS AFFILIATIONS Verónica M. Rodríguez U.S. Nuclear Regulatory Commission (NRC)
Naeem Iqbal NRC Phil Qualls NRC Lorrie Bell Wolf Creek Nuclear Operating Corporation (WCNOC)
Bill Selbe WCNOC Jeff Suter WCNOC Eric Blocher Strategic Teaming and Resource Sharing Alliance (STARS)
Paul Crawley STARS Richard Geiger STARS REQUESTS FOR ADDITIONAL INFORMATION WOLF CREEK GENERATING STATION, UNIT 1 LICENSE RENEWAL APPLICATION JUNE 14, 2007 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Wolf Creek Nuclear Operating Corporation held a telephone conference call on June 14, 2007, as a followup discussion and request for clarification to the applicants response to the following request for additional information (RAI) concerning the Wolf Creek Generating Station (WCGS),
Unit 1, license renewal application (LRA). The applicants response to this RAI was submitted by letter dated May 2, 2007.
RAI 2.3.3.14-5 Updated Safety Analysis Report (USAR) Table 9.5.1-2 lists various types of fire water suppression systems. The staff requests that the applicant verify whether the fire water suppression systems in the areas listed below are within the scope of license renewal in accordance with the Title 10 of the Code of Federal Regulations (10 CFR 54.4(a)) and subject to an aging management review in accordance with 10 CFR 54.21(a)(1). If not, the staff requests that the applicant provide a justification for their exclusion.
Manual pre-action sprinkler system:
north cable penetration (inside containment) south cable penetration (inside containment)
Automatic water spray system:
hydrogen seal oil unit main transformer startup transformer auxiliary transformer station service transformer engineered safety feature transformer Automatic pre-action sprinkler system:
fuel building rail road bay lower cable spreading room upper cable spreading room cable trays (auxiliary building elevation 1974'-0", 2000'-0",
2026'-0") diesel generator rooms area below turbine generator (operating floor and mezzanine floor) turbine generator Manual water spray system:
auxiliary feedwater pump (turbine driven) steam generator feed pump Automatic wet-pipe sprinkler system:
turbine lube oil storage room auxiliary boiler room turbine lube oil reservoir room condenser pit (area beneath the main condensers) dry waste compactor (radwaste building) access control area (control building) pipe space and tank area (control building) cable area above access control area vertical cable chases (auxiliary building) vertical cable chases (control building) auxiliary feedwater pipe chase area (auxiliary building) turbine building outage office Discussion: Based on the discussion with the applicant, the staff indicated that the response to this RAI requires clarification. The applicants response lists fire water suppression systems that are not within the scope of license renewal. The staff finds this inconsistent with the WCGS USAR Section 9.5. The staff requested that the applicant justify why these components were not included within the scope of license renewal pursuant to 10 CFR 54.4(a)(3) as some of them are required for compliance with 10 CFR 50.48, and 10 CFR Part 50, Appendix A, Criterion 3 (GDC 3). The applicant will provide its formal response in writing.
Letter to Wolf Creek Nuclear Operating Corporation, from V. Rodriguez, dated June 25, 2007
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JUNE 14, 2007, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND WOLF CREEK NUCLEAR OPERATING CORPORATION, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE WOLF CREEK GENERATING STATION, UNIT 1, LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes VRodriguez CJacobs JDonohew GPick, RIV SCochrum, RIV CLong, RIV NIqbal
Wolf Creek Generating Station cc:
Jay Silberg, Esq.
Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-7005 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 311 Burlington, KS 66839 Chief Engineer, Utilities Division Kansas Corporation Commission 1500 SW Arrowhead Road Topeka, KS 66604-4027 Office of the Governor State of Kansas Topeka, KS 66612 Attorney General 120 S.W. 10th Avenue, 2nd Floor Topeka, KS 66612-1597 County Clerk Coffey County Courthouse 110 South 6th Street Burlington, KS 66839 Thomas A. Conley, Section Chief Radiation and Asbestos Control Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366 Vice President Operations/Plant Manager Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Supervisor Licensing Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 U.S. Nuclear Regulatory Commission Resident Inspectors Office/Callaway Plant 8201 NRC Road Steedman, MO 65077-1032 Kevin J. Moles, Manager Regulatory Affairs Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Lorrie I. Bell, Project Manager Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839 Mr. Gordon A. Clefton Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708