Harris Nuclear Plant NRC Annual Assessment Meeting May 23, 2007 1

Plant operation O 20 years of safe, reliable operation O Serving 550,000 homes every day O Excellent 2006 NRC performance rating 2

Operational Excellence NRC Reactor Oversight Process 3

50 60 70 80 90 100 Robinson Harris Harris 99.72 Summer Salem Point Beach Perry Monticello Braidwood Grand Gulf Waterford Diablo Canyon TMI INPO Performance Index by plant Susquehanna Prairie Island Nine Mile Oyster Creek Surry Comanche Peak Hatch Pilgrim Millstone St. Lucie Davis Besse Catawba Turkey Point 1st Quarter 2007 4 River Bend Duane Arnold Oconee Brunswick Fort Calhoun Palo Verde San Onofre Kewaunee

The Facts on Unplanned shutdowns 5

Automatic and manual reactor trips 8

7 6

5 4

4 3 Harris 2

1 1 1 1

0 0

2003 2004 2005 2006 2007 YTD 6

The Facts on Fire safety 7

Thermo-lag 8

Interam 9

Hemyc 10

Pre-test 11

During test 12

Post-test 13

Fire safety Fall 2010 - complete transition to NFPA-805 14

The Facts on Security 15

Harris Security Force Harris Security personnel O Highly-trained, 230 hours0.00266 days <br />0.0639 hours <br />3.80291e-4 weeks <br />8.7515e-5 months <br /> of training before going on-shift We do not tolerate cheating O Entire guard force re-tested O Individuals involved no longer employed 16

Fall 2007 refueling Significant tasks O Containment sump O Pressurizer weld overlay O Fire protection modifications 17

Emergency Preparedness O Evacuation studies every two years O New battery-backup siren system; installation under way O Successfully completed FEMA graded exercise in April 18

19